Engr. Paolo Tolentino
Engineering Supervisor
1. OBJECTIVE
a. To identify if overheating happens to electrical equipment at present condition.
b. To check the working condition of electrical equipment and minimize or eliminate sudden
equipment breakdown.
2. SCOPE OF ACTIVITY
a. Thermographic Scanning
i. Prepare tools and equipment.
ii. Open panel doors/covers.
iii. Take thermal image.
iv. Put back panel doors/covers.
4. SAFETY REQUIREMENTS
a. Contractor to abide on company rules, regulations and standard operating procedures
b. Wear Personal Protective Equipment at all times during execution of work
c. Proper Lock out and Tag Out of electrical equipment
d. Safety Signages
e. Grounding of electrical equipment
5. SECURITY REQUIREMENTS
a. Accomplished work permit by the service provider
b. Notify tenants about schedule of power shutdown by the Owner
c. Set up Signage/Barricade as may needed
d. Wearing uniform and ID inside the building premises
e. Submit list of equipment being owned by the service provider
6. PROPOSED SCHEDULE
a. Pre-PMS Thermal Scanning :
Day 1 Generic Date / 9:00 AM until onwards.
b. Preventive Maintenance Service :
Day 2 Generic Date / Saturday / 8:00 AM until on or before 5:00 PM
c. Post-PMS Thermal Scanning :
Day 3 (One Week After PM) / 9:00 AM until onwards.
7. ACTIVITY PRE-CONDITION
a. Secure approved Building Work Permit
b. Coordination of power shutdown with Meralco and tenants by the Owner
c. Check the power supply for testing of equipment
d. Toolbox meeting/Safety Orientation
8. TENTATIVE PLANNED OF WORK ACTIVITY
Item Scope of Works Timeline Responsible
1 Toolbox Meeting 8:00AM-9:00AM EXQUIS/BONI
Safety Orientation
Dissemination of scope of works to personnel concern
2 Power Shutdown 9:00AM BONI/MERALCO/EXQUIS
Switch- off the Main Circuit Breaker
Meralco personnel/s remove the disconnecting fuse at the post
Check the residual voltage on the system
Follow Lockout Tagout (LOTO) Procedure
Install Grounding Cluster
4 PMS of LVSG 9:00AM-2:00PM EXQUIS
Conduct visual inspection of Enclosure and ACB
Perform PMS on ACB
Conduct electrical test
Check and retightening cable terminal connection
General cleaning
5 PMS of EE Rooms (20 floors) 9:00AM-4:00PM EXQUIS
Conduct visual inspection of each panel
Perform cleaning and retightening
General cleaning
6 Final Inspection and checking 4:00PM EXQUIS/BONI
7 Energization 5:00PM BONI/MERALCO/EXQUIS
Removal of cluster and lockout
Final Inspection and checking
Energization Sequence
8 Demobilization 5:00PM BONI/MERALCO/EXQUIS
Turn-over Test Results
Exit meeting
Demobilization
9. GANTT CHART
Operations personnel may coordinate with the following for any related concern/s: