Professional Documents
Culture Documents
System Requirements Well Intervention Equipment: Norsok Standard
System Requirements Well Intervention Equipment: Norsok Standard
D-002
Rev. 1, October 2000
This NORSOK standard is developed by NTS with broad industry participation. Please note that
whilst every effort has been made to ensure the accuracy of this standard, neither OLF nor TBL or
any of their members will assume liability for any use thereof. NTS is responsible for the
administration and publication of this standard.
Telephone: + 47 22 59 01 00 Fax: + 47 22 59 01 29
Email: norsok@nts.no Website: http://www.nts.no/norsok
Copyrights reserved
System requirements well intervention equipment D-002
Rev. 1, October 2000
CONTENTS
FOREWORD 2
INTRODUCTION 2
1 SCOPE 5
2 NORMATIVE REFERENCES 5
3 TERMS, DEFINITIONS AND ABBREVIATIONS 7
3.1 Definitions 7
3.2 Abbreviations 7
4 GENERAL REQUIREMENTS 8
4.1 General 8
4.2 Design principles 8
4.3 Design principles references and standards 8
4.4 Verification, testing and marking 13
4.5 LCC and regularity 15
4.6 Process and ambient conditions 15
4.7 Layout and working environment requirements 15
4.8 Special requirements for skid base structures 16
4.9 Utility interfaces 16
4.10 Operational requirement 17
5 WELL INTERVENTION WELL CONTROL SYSTEM 18
5.1 Equipment configuration 18
5.2 Equipment requirements 21
5.3 Control system 30
6 SNUBBING EQUIPMENT 35
6.1 General 35
6.2 Snubbing equipment requirements 36
6.3 Data acquisition system 39
6.4 Power package 40
6.5 Circulating system 40
6.6 Well control system 40
6.7 Workstring and BHA 41
7 COILED TUBING EQUIPMENT 42
7.1 General 42
7.2 Coiled tubing equipment requirements 42
7.3 Power package 46
7.4 Coiled tubing workstring (steel coiled tubing) 46
7.5 Coiled tubing reel 47
7.6 Control cabin 48
7.7 Data acquisition system 49
7.8 Well control system 49
7.9 BHA 50
8 WIRELINE EQUIPMENT 51
8.1 General 51
8.2 Wireline equipment requirements 51
FOREWORD
NORSOK (The competitive standing of the Norwegian offshore sector) is the industry initiative to
add value, reduce cost and lead time and eliminate unnecessary activities in offshore field
developments and operations.
The NORSOK standards are developed by the Norwegian petroleum industry as a part of the
NORSOK initiative and supported by OLF (The Norwegian Oil Industry Association) and TBL
(Federation of Norwegian Manufacturing Industries). NORSOK standards are administered and
issued by NTS (Norwegian Technology Center).
The purpose of NORSOK standards is to contribute to meet the NORSOK goals, e.g. to develop
standards that ensure adequate safety, value adding and cost effectiveness and thus are used in
existing and future petroleum industry developments.
The NORSOK standards make extensive references to international standards. Where relevant, the
contents of a NORSOK standard will be used to provide input to the international standardisation
process. Subject to implementation into international standards, the NORSOK standard will be
withdrawn.
INTRODUCTION
The main objective of this NORSOK standard is to contribute to optimise the design of well service
and intervention facilities, their systems and equipment with respect to utilisation, operational
efficiency, life cycle cost and to stipulate acceptable safety levels.
NORSOK standard D-002 is an overall improvement and expansions of the former standards for
coiled tubing, snubbing and wire line equipment, and replace the following NORSOK standards:
1 SCOPE
This standard describes the design, installation and commissioning principles and requirements for
the well intervention equipment and their systems and equipment.
2 NORMATIVE REFERENCES
The following standards include provisions which, through reference in this text, constitute
provisions of this NORSOK standard. Latest issue of the references shall be used unless otherwise
agreed. Other recognized standards may be used provided it can be shown that they meet or exceed
the requirements of the standards referenced below.
NPD Regulations
NORSOK D-001, Drilling facilities.
NORSOK E-001 Electrical systems,
NORSOK E-002 Adjustable speed motor drives.
NORSOK H-001 HVAC Heating, ventilation and air conditioning
NORSOK N-001, Structural design.
NORSOK N-003, Actions and action effects.
NORSOK S-001, Technical Safety.
NORSOK S-002, Working Environment.
NORSOK S-003, Environmental Care.
NORSOK Z-010 Installation of Electrical, Instrument & Telecommunication
NORSOK Z-015, Temporary Equipment.
ISO 10423 Petroleum and Natural Gas Industries – Drilling and Production Equipment –
Specification for Valves, Wellhead and Christmas Tree Equipment
ISO 10424 Petroleum and Natural Gas Industries – Drilling and production equipment –
Rotary drilling equipment
ISO 13533 Petroleum and Natural Gas Industries – Drilling and production equipment –
Specification for drill through equipment
ISO 13535 Petroleum and Natural Gas Industries – Drilling and production equipment –
Hoisting equipment
ISO 13626 Petroleum and Natural Gas Industries – Drilling and production equipment –
Drilling and well servicing structures – Specification
ISO 14693 Petroleum and Natural Gas Industries – Drilling and production equipment –
Drilling equipment
API Spec 4F Drilling and well servicing structures
API Spec 5CT Specification for Casing and Tubing (U.S. Customary Units)
API Spec 6A Specification for Wellhead and Christmas Tree Equipment
API Spec 7 Specification for Rotary Drill Stem Elements (replace with ISO 10424 when
issued)
API Spec 7K Specification for Drilling Equipment
API Spec 8C Specification for Drilling and Production Hoisting Equipment (PSL 1 and PSL
2), (replace with ISO 13535 when issued)
API Spec 9A Specification for Wire Rope
API Spec 16A Specification for Drill Through Equipment, (replace with ISO 13533 when
issued)
API Spec 16C Choke and kill system
API Spec 16D Specification for Control Systems for Drilling Well Control Equipment.
NACE-MR-0175, Sulphide Stress Cracking Resistant Metallic Materials for Oilfield Equipment.
NACE-TM-0177 Labory Testing of Metals Resistance to Sulfide Stress Cracking and Stress
Corrosion Cracking in H2S Environment. Item no 21213
ASTM-E466-82 Standard Practice for Conduction Force Controlled Constant Amplitude Axial
Fatigue Tests of Metallic Materials
ASTM-E468-90 Standard Practice for Presentation of Constant Amplitude Fatigue Test Results
for Metallic Materials
ASTM-E739-91 Standard Practice for Statistical Analysis of Linear or Linearized Stress-Life
(S-N) and Strain-Life (e-N) Fatigue Data
ASTM-A450 Standard Specification for General Requirements for Carbon, Ferritic Alloy,
and Austenitic Alloy Steel Tubes
3.1 Definitions
3.1.1
barrier
envelope of one or several dependent barrier elements preventing fluids or gases
from flowing unintentionally from the formation, into another formation or to surface
Should: Verbal form used to indicate that among several possibilities one is
recommended as particularly suitable, without mentioning or excluding others,
or that a certain course of action is preferred but not necessarily required.
May: Verbal form used to indicate that among several possibilities, one is suitable,
without mentioning or excluding others, but not necessarily required.
3.1.2
qualified
special proof for being fit for the intended purpose
NOTE To be documented by design, calculation and function testing and verified by 3 rd party or
independent surveyor.
3.1.3
maximum expected wellhead pressure
maximum shut in wellhead pressure plus additional pressure from well intervention activities
3.2 Abbreviations
BHA bottom hole assembly
BOP blow out preventer
BPV back pressure valve
CE European Conformity Assessment Mark
EEA European Economic Area
ESD emergency shut down
FAT factory acceptance test
HVAC heating ventilation and air conditioning
LCC life cycle cost
MTBF mean time between failure
MTTR mean time to repair
NPD Norwegian Petroleum Directorate
UPS un-interruptable electrical power supply
ANSI American National Standards Institute
4 GENERAL REQUIREMENTS
4.1 General
The well intervention equipment shall be designed, built and equipped in compliance with
applicable regulations and this NORSOK standard.
The objectives shall constitute the basis for definition and revision of the acceptance criteria for risk
in connection with well activities, and for the choice of risk reducing measures.
System and equipment are to be protected against excessive loads and pressure.
System and equipment are to provide two independent levels of protection to prevent or minimise
the effects of a single malfunction or fault in the process equipment and piping system, including
their controls.
Different types of safety devices to reduce the probability for common cause failures should provide
two levels of protection.
All equipment shall be located to ensure safe operation and, if located in hazardous areas, shall be
suitably protected for installation in such areas. Reference is made to NORSOK standard Z-015
regarding relevant discipline requirement for design and installation of service containers, such as
fire and gas, electrical, HVAC, etc. for temporary equipment.
The facilities shall be designed to minimise risks of personnel injuries, environmental hazards and
economic loss. Reference is made to NORSOK standard S-001, NORSOK standard S-002,
NORSOK standard S-003 and NPD Regulations.
Planning, design, fabrication, operation and maintenance of well intervention equipment shall be
according to documents listed in Table 1, Table 2, Table 3, Table 4 and Table 5.
Table 1 Snubbing
Note: ( ) means standards under preparation
Equipment Norsok ISO API Other
Substructures / N-001 (13626) 4F NS-3472 Steel structures – Design rules
masts / gin pole BS-7072 Code of practice for inspection and
repair of offshore containers
DNV Lifting Appliance
DNV Offshore standard OS-E101 Drilling
Plant
Pipe handling DNV Offshore standard OS-E101 Drilling
system; Plant
Jack/pulling unit; (13535) 8C DNV Offshore standard OS-E101 Drilling
Plant
Rotary / power (13535) 8C DNV Offshore standard OS-E101 Drilling
swivel Plant
Work window N-001 (13626) 4F NS-3472
DNV Offshore standard OS-E101 Drilling
Plant
Slip bowls / (13535) 8 C DNV Offshore standard OS-E101 Drilling
carriers (14693) 7K Plant
Make up / brake (14693) 7K DNV Offshore standard OS-E101 Drilling
out tongs Plant
Winch package / 9A DNV Offshore standard OS-E101 Drilling
hoisting equipment Plant
Circulating swivel (10423) 6A NACE-MR-0175
(15156) DNV Offshore standard OS-E101 Drilling
Plant
Kelly valves (13535) 8C NACE-MR-0175
(10424) 7 DNV Offshore standard OS-E101 Drilling
(15156) Plant
Workstring (10424) 7
(11960) 5CT
BHA 9001: BS 308: Parts 1, 2, & 3.
Chapter BS 4656: Parts 1, 2, 3, & 4.
4.5 4.7
& 4.16
Table 3 Wireline
BOP accumulator unit system Z-015 16D DNV Offshore standard OS-E101
w/ BOP control hoses Z-010 16E Drilling Plant
E-001 FEA-M (1990)
E-002
4.4.1 Verification
Verification of design, fabrication and testing shall be carried out and implemented according to an
overall and clearly defined verification programme and verification basis There shall be
independence between those who carry out the work, and those who are responsible for the
verification.
The verification may thus comprise control of calculations, drawings and fabrication by going
through what have been done or carrying out independent or own calculations. The verification may
also include trials or testing of equipment and systems.
By independence means that the verification shall be carried out by someone other than the one who
has performed the work which is to be verified, or the one who has prepared the verification basis,
and also that there shall be organisational independence regarding reporting in the chain of
command.
An important condition is that the verifying unit has the necessary competence and resources to carry
out the verification. Verifications shall be carried out in accordance the requirements in this
NORSOK standard. Consideration of complexity shall be included in the evaluation, as well as the
probability for or the consequences of failure or faults, which may occur.
The verification shall be documented and should comply with issuance of e.g. design verification
report and product certificate.
At FAT the well intervention equipment shall, to the extent possible, be tested as a complete
system, with all subsystems integrated. Loads and signals shall be simulated and recorded.
During commissioning and start-up, the various systems and their drilling instrumentation package
shall be utilised to verify the sensor data.
4.4.3 Marking
Equipment shall be clearly marked as follows with identification and operational limitations,
relating the equipment to certificates and fabrication documentation:
Equipment identification:
• manufacturer’s name or mark;
• equipment type no.;
• equipment serial no.
There shall be consistency between units used for marking and units displayed on instruments.
Machinery placed on the market after 8 April 1995 shall be designed, manufactured and
documented in accordance with the requirements of the Machinery Directive 98/37/EC/Forskrift om
maskiner Best. nr. 522. The requirement entails that the individual contractor, sub-contractor etc.
shall ensure that machinery taken into use has received CE marking and that it is accompanied by a
declaration of conformity.
By marketing («place on the market») is meant the first time a product, against payment or free of
charge, is placed at disposal with a view to distribution or use within the EEA. The NPD has in co-
operation with other authorities, defined the following criteria for when a product is considered
placed on the market:
• when the right to utilize of the product passes over from a manufacture within the EEA area to
the next link in the chain of distribution;
• when the equipment is imported from a country outside the EEA area, and the right to utilize of
the product passes over from importer to the next link in the chain of distribution;
• when the equipment was offered and is available for direct sale from the manufacture or from an
importer and the purpose was to direct sale to users;
• when a manufacturer or an importer takes into use equipment imported by him.
The requirement contained in this section applies only to machinery comprised by the Machinery
Regulations. This entails that the requirement applies only to machinery used on fixed installations.
The reason for this is that Machinery Regulations are not applicable to ships and mobile offshore
units.
The design basis shall be defined for the following load combinations:
• operational load;
• snow and ice loads;
• earthquake conditions (optional);
• impact from transportation;
• wind conditions;
• the structure shall as a minimum be designed for continuos operation with regards to hook load,
rotary load for wind speeds up to 30 m/s, 10 min. mean values, considering a reference height of
50 m above lowest astronomical tide, unless otherwise specified.
4.7.1 General
All work areas in connection with well intervention equipment shall be arranged to ensure the safety
of personnel and operations, working environment and pollution control, in accordance with
NORSOK standard S-001, NORSOK standard S-002 and NORSOK standard S-003 and project
safety goals.
The layout of the well intervention equipment shall give due consideration to areas that may be
critical to dropped objects, especially in connection with materials and equipment handling.
The layout shall ensure that maintenance and service can be carried out in a safe and ergonomically
efficient way.
The control cabins for snubbing, coiled tubing, wireline equipment and pumping units shall be
designed to withstand a total outdoor area noise level impact of 90 dB (A) and be designed
according to values defined in NORSOK standard S-002, annex A, for driller cabins. The total noise
level shall not exceed 65 dB (A) inside the cabin.
The power packages, fluid and N2 pumping units and accumulator packages for snubbing, coiled
tubing and wireline operations shall be designed according to values defined in NORSOK standard
S-002. The equipment shall be designed in such a manner that the total noise level from the
equipment shall not exceed 82 dB (A) and the equipment shall not contribute to exceed a max area
noise level as defined in NORSOK standard S-001, i.e. 85 dB (A) on pipe deck area.
Contaminated fluids shall be collected and routed to a dedicated slop tank system. All other fluids
from the well intervention equipment, rigged up on top of the skid base substructure, shall be
discharged to the installations drain points.
Mechanic, electric, hydraulic and pneumatic interface connections shall be compatible with rig or
platform connections.
The following utilities should typically be supplied by the platform facilities to support the well
intervention equipment:
The extent of maintenance, which is overdue, should be limited. Prior to start-up of demanding
phases of the activities there should not be any maintenance on critical equipment overdue.
In order to maintain an acceptable safety level, it is important that adequate safety routines are
established in connection with maintenance, e.g. in connection with pressure relief, fire protection,
alerting personnel, fencing off areas etc.
Function testing of the positive and negative weight indicator system shall be performed prior to
each job.
Documentation and verification to be submitted to verify acceptable rig up versus forces and
bending momentum’s, downhole tools, well control system, frames, main equipment and pumps
expected work conditions inside set safety limits.
Coiled tubing
• Dual stripper. X
• Coiled tubing body (string) X
• End connector X
• One dual check valve in the BHA X
• Alternatively – plugged end of coiled tubing. X
Wireline
Slickline operations
Stuffing box for solid wireline. X
Braided cable
Grease injection head with relevant sized flowtubes. X
Coiled tubing
• One combined shear/seal ram X
• One pipe ram X
• One slip ram X
• Minimum one kill line inlet X
• Minimum one manual gate valve and/or plug valve X
on the kill line and minimum one remote hydraulic
operated gate and/or plug valve. Alternatively
remote valve can be replaced with one manual valve
and a check valve.
5.2.1 General
Equipment
5.2.2 Pump down plugs, stabbing valves, back pressure and check valves
Check valves
A minimum of dual check valves installed in workstring. X
A minimum of dual check valves shall be on work location. X
The check valves shall allow balls to pass through. X
5.2.4 Stuffing box, grease injection head, hydraulic line wiper and
Equipment Wireline
Stuffing box
The hydraulic actuated packing nut to be operated from the hydraulic control panel. X
Stuffing box shall be equipped with a qualified device preventing hydrocarbon leaks
in case of wireline breakage
Grease injection head
A line wiper and stuffing box to be included in the grease injection head assembly. X
The grease injection inlet manifold to include a check valve.
Integral check valve system to be included and two ports for grease injection.
Grease injection head stuffing box shall be equipped with a qualified device
preventing hydrocarbon leaks in case of wireline breakage
Hydraulic line wiper
Hydraulic actuated rubber element operated from hydraulic control unit. X
5.2.5 Pipe, stripper, slip, tubing, wireline shear blind, shear / seal, safety head rams and
annular preventer requirements
Equipment Snubbing Coiled Wireline
tubing
General
The BOPs shall have a mechanical locking system to enable X X X
locking of the rams in closed position.
Indicator ”pins” for open and close status of the BOP should X X X
be included.
Pipe and slip ram hang off capacity compatible with the X X
workstring weight.
Annular preventer
The annular preventer shall be able to close and seal off at X If used
max. shut in / max. expected operating pressure rating on
open hole. The annular preventer shall operate (close) on
both stationary and running objects. Stripping through the
annular with the specified workstring shall be possible
without damaging the tubular. If used
X
The annular preventer shall be furnished with accumulator(s)
as a surge dampener for emergency stripping of pipe and
tubular.
1
Workstring
2
Wire
Safety head
Riser
The riser shall as a minimum have the following specifications:
Kill line for wireline should be minimum 50,8 mm (2 in) nom size. X
All outlets and inlets on the BOP system shall have metal to metal 1) 2) 2)
seals. The outlets and inlets shall be fitted with at least two valves.
1) All outlets and inlets.
2) All outlets and inlets below shear/seal ram.
In the case of manually operated chokes, the circulating pressure and the choke manifold pressure
shall be displayed on or close to the manifold. All pressure indicators gauges should be through
hydraulic pressure deboosters with remote output.
The manifold should also be fitted with a connection facility for an optional pressure gauge with
low increment readings.
Lines and hoses between the BOP stack and the choke manifold system shall, together with their
connections and valves on the high pressure side of the choke manifold, as a minimum have the
same working pressure rating as the BOP stack.
The operation of the secondary well control system shall be from minimum two control panels, one
control panel located at the operator's workstation, and one control panel located in a safe area.
The operation of the tertiary well control system shall as a minimum be operated from a safe area.
The accumulator unit(s) to operate the secondary and tertiary well control system shall be located in
a safe area in order to avoid exposure in the event of an uncontrolled well control situation, i.e.
away from the well area and close to an escape way. The rig-floor is normally not considered as a
safe area. The control panel(s) for operating the secondary and tertiary well control systems may be
integrated into the BOP accumulator unit(s).
5.3.1 General
The control system shall consist of the following for Snubbing, Coiled tubing and Wireline:
• Control panels which clearly indicates (e.g. Indicator with status of the functions shall be
included by means of lights or selector valve) information for the panels whether the functions
are in open or closed position
• The control panels with motion selector valves and switch buttons shall be equipped with a
securing device against unintentional operation of essential functions (e.g. shear ram). Accidental
operation shall not occur.
• The BOP control system and panels shall be equipped with alarms for low accumulator pressure,
loss of power and low level of control fluid.
• Regulators in the system shall remain unaffected in the event of loss of power.
• BOP ram operating pressure shall as a minimum be regulated from the BOP accumulator unit.
• Maximum response time when the BOP is located on a surface installation, 30 seconds.
Response time refers to the time it takes from the closing function is activated from the panel,
until the BOP function is in closed position.
• Equaliser, bleed off, kill line and choke line valves maximum response time for snubbing: 1
second
The accumulator capacity for operating a BOP stack with associated systems shall as a minimum
have sufficient volumetric capacity to close, open and close all the installed BOP functions plus 25
% of the volume for one closing operation for each one of the said BOP rams.
The following BOPs operated from the well control system shall be used as basis when calculating
the accumulator capacity:
As a minimum for dimensioning total accumulator volumes and capacities (isotherm, adiabatic slow
charge and fast operation) shall be included.
Alternatively a dedicated shear ram auxiliary pressure system (shear boost system) may be installed
to meet the minimum requirements to cut the workstring if the remaining accumulator pressure is
not sufficient to enable cutting after having performed operations as described above.
The accumulator system shall be separate from all other hydraulic circuits, i.e., only the well control
system can take fluid from the storage accumulators.
The accumulator system shall be designed such that the loss of an individual accumulator and/or
bank will not result in more than 25 % loss of the required total accumulator system capacity.
The control panels shall have an ergonomic layout and be designed according to NPD Regulations
and NORSOK standard S-002
5.3.2 Function requirements for accumulator unit and panels for primary and secondary
well control functions
Panel located on the BOP accumulator unit and panel (located in the operator cabin/
workbasket) to be equipped with functions for as follows:
Snubbing Coiled tubing Wireline
Regulators for as follows: Acc. unit Work Acc. unit Coiled Acc. unit Wireline
basket tubing cabin
cabin cabin
BOP ram activation X If used X If used If used If used
pressure-manifold pressure.
Annular preventer regulator. X X If used If used
Active stripper regulator. If used If used
Upper stripper regulator. X
Lower stripper regulator. X
Alarms for as follows:
Low accumulator pressure. X X X If used X If used
Loss of power supply. X X X If used X If used
Low level of control fluid. X X X If used X If used
Pressure monitoring:
Accumulator pressure X X X X X X
BOP ram activation/ X X X X X X
manifold pressure.
Annular preventer pressure. X X If used If used
Active stripper pressure. If used If used
Upper stripper pressure. X
Lower stripper pressure. X
Basic BOP ram/valve open
and close functions:
Annular preventer. X X If used If used
Stripper ram 1. X X
Stripper ram 2. X X
Upper pipe ram. X X
Shear/blind ram. X X
Lower pipe ram. X X
Equaliser loop valve. X X
Bleed off valve. X X
Kill line valve. X X X
Choke line valve. X X
Shear/seal ram. X X X X
Pipe ram. X X
Slip ram. X X
Wireline ram. X X
Wireline ram (inverted). X X
Flow monitoring:
BOP fluid monitoring. X X X X X X
5.3.4 Tertiary BOP control system (for safety head) for snubbing, coiled tubing and
wireline
The basis for design of the BOP accumulator unit for operating the safety head
(defined as the tertiary well control system) is the same as for the BOP accumulator system to
operate the secondary well control functions.
This includes accumulator capacity design, BOP hoses design, shear boost (if used) system,
regulators and monitoring of pressure internal on the unit, alarms, volume monitoring (flow) and
indicator status on open and close functions.
5.3.5 Choke control system for snubbing, coiled tubing and wireline
Operation of a remote controlled choke, if installed, shall take place from a suitable panel. The
panel shall at least indicat
6 SNUBBING EQUIPMENT
6.1 General
The snubbing equipment with associated systems shall be capable of handling the workstring, well
conditions and other work parameters specified by the work program. This clause describes the
minimum functional requirements for snubbing equipment.
The snubbing well intervention system will normally consist of the following main items:
The system shall be designed to and be capable of handling tubular such as, but not limited to, in an
efficient way:
The system design shall allow for performing Wireline work and electric logging operations within
the workbasket/snubbing unit working platform area, considering space, height, equipment
handling, access to the equipment and weather protection.
The equipment should be equipped with a four point lifting arrangement for both horizontal and
vertical handling of modules where applicable.
Access in connection with operation and maintenance of equipment shall be catered for by suitable
and safe access from deck or installed work platforms. From current practice it follows that the
various work platforms in structures (including platform for installation of casings) shall be
adequately equipped with safety devices, lifts, stairs or ladders for safe access, see NORSOK D-001
standard.
Lubrication points with difficult access in the workover area, such as sheaves, shall be routed to a
readily accessible area. Sufficient number of hang off points of required capacity for travelling
assembly, manual rig tongs and work winches shall be installed. All hang off points and/or padeyes
shall be properly marked with safe working load, and the design shall ensure that safe working load
does not exceed 20 % of the breaking load.
The snubbing unit working platform area shall in relevant areas be designed for dropped object
protection, i.e. to withstand the impact from the heaviest expected tubular falling from a height of
1,5 m.
All permanently manned working areas shall be weather protected. The primary work area shall be
covered with a non-skid material.
The substructure shall be designed to form an adequate foundation for the structure/mast or hoisting
structure and the snubbing unit working platform area, and provide required elevations and handling
space for BOPs and optional x-mas trees etc. The substructure shall be designed to withstand all
combined loads from, mast or hoisting structure and snubbing unit working platform area with full
loading, BOP handling loads, if applicable, as well as equipment installed in the substructure itself.
The complete design shall be considered for lubrication (space out) of applicable BHA such as
running and pulling perforating and gravelpack assemblies when rigged up on a live well.
The workbasket/snubbing unit work platform area shall be unmanned and equipment remotely
operated in normal “drilling” and tripping operations. The horizontal transportation system and the
horizontal to vertical transportation system shall be remote operated with the possibility for
• stowage, make up, break out and suspension of workstring, collars, casings and tubing in the
rotary table;
• transport of workstring, casing, collars etc. to and from storage location in front of “ V- door “ to
the snubbing unit working platform area. The complete string of tubular shall be stored on a
location where it require no platform crane handling between the storage location to the
snubbing unit workbasket/working platform area (drillfloor).
An anti collision system should be installed to prevent collision between the main hoisting
equipment, the pipehandling equipment and structures.
The hydraulic hoses to the unit shall have sufficient lengths to position the hydraulic support system
at the required distance from the well area. All hoses in suspension from a connection shall be
equipped with quick disconnect complete with locking feature including dust plug and cap.
The unit shall be equipped with an anti buckling guide tube system to support the workstring and
the inside diameter to suit actual workstring
Window shall be designed with load rating equivalent to the jack and/or pulling unit with feature for
hanging off the workstring.
6.2.5 Slips
The slips design rating shall be equivalent to at least the maximum thrust of the jack/pulling unit
system and shall be remote operated.
The slips shall be equipped with a cross port relief valve system to prevent hydraulic and
mechanical damage in the event of forced opening of equivalent function.
If an old system with conventional tongs are used the following applies:
• the height from the tong post arm to the workbasket handrail shall be adequate to accommodate
the power tong and with a suspension and trolley arrangement to allow swinging of tong away
from the centre line;
• tong suspension arrangement to allow the introduction of a spring to prevent overload of tong
arm during make-up of tubular joints;
• to incorporate tong backup attachment eye, rated at the maximum horizontal force resulting
from the maximum tong torque capacity.
One set of tubing tong with slide heads for both tong and back-up to fit the tube and upset
connection of the workstring.
The winch package to contain an automatic fail-safe brake in the event of hydraulic failure and the
safe working load on the winch shall be determined by the work program.
Winch package can be voided if design of unit do not require such system.
The system shall contain a hydraulic arrangement for raising and lowering of the gin pole.
The workbasket shall have two independent escape exits and be equipped with wind walls for
weather protection, and a workstring mark board in the workbasket area for operator quick reference
of workstring depth.
The layout of the operator cabin shall ensure full operational control and view from the operator’s
position to the various parts of the work floor area.
The control cabin shall have an ergonomic layout and be designed according to NPD Regulations
and NORSOK standard S-002.
The control cabin shall facilitate all necessary controls and monitoring equipment to operate the
complete snubbing unit and well control equipment as defined in clause 5.
• the operator cabin shall have an ergonomic layout and shall be equipped with laminated glass,
oil resistant wiper or cleaner and a suitable mechanical ventilation system;
• the roof and windows shall have adequate strengthening or protection against falling objects.
• due consideration to be given to visibility on control system visual display unit screens;
• jack "snub" and "heavy" force limitation shall be pre-set at power pack manifold local
adjustments in workbasket and cabin shall not override the pre-set value;
• there shall be individual hydraulic circuits for jack, pipe-handling system, BOP and auxiliary
system. Each circuit shall have an adjustable pressure safety relief and pressure indicator;
• interlock shall be provided to prevent inadvertent opening of the stationary and the travelling
heavy slips simultaneously. It shall be possible to manually over ride this interlock.
The controls and monitoring equipment shall as a minimum include the following:
The snubbing unit shall be equipped with a data acquisition system to monitor and record the
following parameters:
The power package shall be designed and sound proofed in accordance with NPD Regulations.
Provisions shall be made for a manual ESD system that is operated locally and remotely from the
workbasket/control cabin.
The power package shall be certified for operating in Zone II areas and in accordance with
NORSOK standard Z-015.
Provisions shall be available for remote and local control. Individual adjustment and pre setting of
the operating limits for maximum pull and push forces to the snubbing unit shall be possible. These
shall be protected from adjustment during normal operating conditions.
If the power package is used for charging the accumulator system for the well control equipment,
the hydraulic circuit from the well control accumulators shall be separate from the other hydraulic
circuits. Only the well control system shall be able to take hydraulic pressure from the dedicated
accumulators.
Pin connection on swivel shall be compatible with the safety valve requirements.
Minimum circulating hose length shall be equal to one single joint and end connection equipped
with safety clamps and chain.
6.7.1 General
The workstring shall meet the operational requirements with respect to maximum anticipated
pressure, temperature, torque, tension and compression. The workstring shall be inspected and a
verification report shall be issued stating approved and found suitable for operation as a minimum.
The tubing shall have documented tracability. A pipe tracking system may provide documented
tracability.
During operations the workstring limitation for over pull shall be set to 80% of manufacture's
tensional yield/torsional yield of the workstring.
For live well interventions, the type of connection for use in the workstring above the BPVs (check
valves) to meet the requirement of minimum two independent gas tight metal- to - metal seals. The
seals to withstand internal and external pressure.
Drifts (2 each size), stabbing guides (2 each size), necessary x-overs and overshots for fishing the
workstring components shall be included.
6.7.3 Others
All other equipment or tools in the BHA shall be qualified and designed to withstand all expected
down hole forces and conditions.
7.1 General
A coiled tubing unit with associated systems shall be capable of handling the workstring, well
conditions and other work parameters specified by the work program. This clause describes the
minimum functional requirements for a coiled tubing unit with associated equipment.
The well Intervention system for coiled tubing will normally consists of the following main items:
• injector head;
• tubing guide arch (gooseneck);
• injector support frame(s);
• injector lifting frame;
• power package;
• coiled tubing workstring (steel coiled tubing);
• coiled tubing reel;
• control cabin;
• data acquisition system;
• well control system;
• BHA.
7.2.1.1 General
The injector head shall have a pulling capacity of 140 % of the maximum expected load for the
operation and pushing (snub) capacity of 120 % of the maximum anticipated load for the operation.
The outer frame structure shall provide a base for the tubing guide arch and injector lifting sling.
The outer frame structure shall be designed for lifting the total weight of the injector head including
the stripper assembly, BOPs, BHA and lubricator/riser system as required for the operation.
Provisions shall be made for anchoring at minimum four anchor points or alternative system with
equal strength according to design criteria for the system to be used.
The drive chain shall be easily replaceable in the field or be equipped with replaceable gripper
blocks.
The traction force shall be adjustable from the control cabin and be capable of generating sufficient
friction to push or pull the workstring at maximum rated loads without slippage or damage to the
workstring.
The traction system shall have a fail-safe device preventing loss of traction pressure in case of a
broken hose.
The traction system shall be provided with an accumulator system for each traction circuit at the
injector head.
Provisions shall be available to provide traction in the event of power supply failure.
The tension system should be provided with an accumulator system at the injector head.
Provisions shall be available at the injector head, control cabin or power unit, for individual
adjustment and pre-set of the operating limits for maximum pull and push forces to the injector
head. These shall be protected from adjustment during normal operating conditions.
The hydraulic drive system shall be capable of pushing or pulling the maximum rated load at a
speed of 10 m/min.
The hydraulic system shall be fail safe and stop the chains from moving if hydraulic power is lost.
Charts for hydraulic pressure with corresponding load and available hydraulic pressure shall be
provided.
Provisions shall be made for hydraulic drive lockout when the reel brake is engaged.
The injector head weight indicator system shall be equipped with a fail-safe transport-locking
device, i.e. the transport locking device shall either be fully locked or fully open.
Provisions shall be made for easy replacement of the weight indicator in the field and a back-up
weight indicator system shall be provided.
The injector head should be equipped with a system for monitoring tubing and chain slippage.
Provisions shall be made for installing a 3rd party depth counter system for logging services.
The tubing guide arch and support base shall be designed to withstand the forces imposed by the
back-tension from the reel. On floating vessels the vessel movement will generate additional forces
that has to be accounted for.
A weak point may be built in to the tubing guide arch system for operations on floating installations.
The strength of the tubing guide arch must be documented.
Provisions shall be made for safe access of all the top rollers of the tubing guide arch.
Provisions shall be made for allowing the workstring to enter or exit the tubing guide arch tangent
to the curve of the tubing guide arch.
Provisions shall be made for allowing the workstring to enter or exit the tubing guide arch from the
angle made by spooling the workstring across the width of the reel. The tubing guide arch shall
support the side loads.
The injector support frame system should be designed to withstand the expected dynamic, static and
bending forces it will be subjected to during normal operations. The operational limits for the
system shall be clearly identified to enable operation within the design criteria. When the injector
support frames are designed to transmit the load from the coiled tubing to the deck during
operations, the maximum pull- and snub force capacity of the injector head shall be included in the
design.
Provisions should be made for moving the injector 3 ways (up and down and sideways in north-
south and east-west directions).
Work platform(s) to access relevant working areas shall be provided.
Provisions shall be made for anchoring at minimum four anchor points or alternative system with
equal strength according to design criteria for the system to be used.
Provisions shall be made for anchoring personnel safety harness at suitable areas.
The lifting frame shall withstand the maximum anticipated loads for the operation. It shall contain a
work window in which the injector head, stripper and BOP can operate isolated from the motion of
a floating vessel.
The lifting frame should have an integrated hydraulic or electric winch/system for independent
handling of the injector, well control equipment and other hook-up equipment. Air operated winch
systems for lifting the injector head should be avoided. The winch/system shall be remotely
operable from the work platform in the lifting frame and/or from the rig floor. It shall be capable of
lifting the injector head with a speed that is higher than the vertical motion of the rig. The load
capacity shall minimum be 30 % above the weight of the injector head assembly above the quick
connector plus the weight of the heaviest anticipated BHA and the forces required to open/unlatch
the quick connector.
The lifting frame should have an integrated hydraulic man rider winch that is remotely operable
from the work platforms in the lifting frame and/or from the rig floor.
The lifting frame shall have a system to guide and prevent horizontal movement of the injector
during operations.
Provisions should be made for handling and make/brake of BHA in the lifting frame.
Provisions shall be made for anchoring personnel safety harness at suitable areas.
The power package shall be designed and sound proofed in accordance with NPD Regulations and
NORSOK standard S-002.
Provisions shall be made for a manual ESD system that is operated locally and remotely from the
control cabin.
The power package shall be certified for operating in Zone II areas and in accordance with
NORSOK standard Z-015.
Provisions shall be available at the injector head, control cabin or power unit, for individual
adjustment and pre-set of the operating limits for maximum pull and push forces to the injector
head. These shall be protected from adjustment during normal operating conditions.
If the power package is used for charging the accumulator system for the well control equipment,
the hydraulic circuit from the well control accumulators shall be separate from the other hydraulic
circuits. Only the well control system shall be able to take hydraulic pressure from the dedicated
accumulators.
The workstring shall have documentation of fatigue cycle history, weld location, tapers, length,
property de-rating and inspection record.
The workstring shall meet the operational requirements with relation to maximum calculated
pressure, temperature, hydraulics, tension and compression. A tubing force calculation shall be
performed for each operation.
The workstring shall be leak tested and drifted prior to each mobilisation. Workstring with e-line
installed may be drifted if applicable.
The workstring shall be quality checked (continuously inspected) and a verification report shall be
issued stating the status and suitability for the upcoming operation(s) prior to each mobilisation. The
tubing quality check shall as a minimum include wall thickness, surface condition, outside diameter,
corrosion, ovality and ballooning.
The workstring should be inspected continuously during the operation to maintain a real time string
condition record. The inspection prior to mobilisation may be omitted if the workstring is
continuously inspected during the operation.
The workstring shall never exceed more than 80 % of manufacturer's specified yield strength as
new. Any de-rating shall be according to recognised standards, e.g. API RP 5 C7 [27]
A system for maintenance and preservation (internal and external) of the workstring shall be in
place.
Access and work platforms shall be provided at suitable areas for normal operations.
The drive system shall be capable of driving the reel faster than the maximum (operating) speed of
the injector head. It shall provide the required tension necessary to bend the workstring over the
guide arch and onto the reel and provide sufficient torque to accelerate the reel drum from stationary
to maximum (operating) speed with the reel drum fully loaded of workstring filled with fluid.
The reel drive system shall be variable, adjusted and controlled from the control cabin.
The coiled tubing reel core diameter shall, as a minimum be 48 times the coiled tubing diameter. A
smaller core diameter can be utilised providing the fatigue life of the workstring is de-rated
accordingly.
The level wind system shall be designed to withstand the bending and side load forces from the
workstring. A guiding system with an override function shall be provided for proper spooling of the
workstring on and off the reel drum.
The level wind system should be equipped with a remotely operated tubing clamp.
The coiled tubing reel shall have a reel brake system that automatically engages with loss of
hydraulic power. This system must have provisions for manual override when operating on floating
vessels/semi-submersibles.
The coiled tubing reel shall have a brake system that is designed to prevent operation of the injector
head when the coiled tubing reel brake system is engaged.
An additional brake system should be installed and to be activated in the event of drive gear or
chain failure. This could either be a capillary brake system or an additional drive motor with internal
brake.
The coiled tubing reel shall have a pig and ball launcher system by-pass and an isolation valve
between the launcher and workstring end termination. The launcher system shall have an internal
diameter equal to or greater than the internal diameter of the workstring.
The coiled tubing reel shall be provided with additional piping as follows: Inlet and isolation valves,
swivel joint, pressure sensing device and connection point for pressure relief valve.
The control cabin shall facilitate all necessary controls and monitoring equipment to operate the
complete coiled tubing unit.
The controls and monitoring equipment shall as a minimum include the following:
a) injector head;
• in hole- and out of hole control;
• traction control;
• tension control;
• high/low gear or displacement control (when applicable);
• emergency traction control;
• injector drive pressure supply pressure;
• in hole- and out of hole pressure;
• traction pressures;
• tension pressure;
• depth counter;
• weight indicator (positive and negative weight);
• wellhead pressure.
c) power package;
• normal stop control;
• ESD control;
d) stripper;
• upper and lower stripper control;
• upper and lower stripper pressure.
e) BOP.
• shear and seal ram control;
• pipe ram control;
• slip ram control;
• BOP accumulator pressure supply;
• BOP control pressure;
• BOP fluid volume control (flow meter) (see also well control system clause 5).
Provisions shall be available at the injector head, control cabin or power unit, for individual
adjustment and pre-set of the operating limits for maximum pull and push forces to the injector
head. These shall be protected from adjustment during normal operating conditions.
7.9 BHA
7.9.1 General
The BHA shall be designed to withstand all expected downhole forces and conditions.
• end-connector;
• dual check valve (BPV).
NOTE The dual check valve can be replaced with a tested plug.
Provisions shall be made for pumping balls through the dual check valve.
7.9.4 Others
All other equipment or tools in the BHA shall be qualified and designed to withstand all expected
down hole forces and conditions.
8 WIRELINE EQUIPMENT
8.1 General
The wireline unit with associated systems shall be capable of handling the tool string, well
conditions and other work parameters specified by the work program. This section clause describes
the minimum functional requirements for a wireline unit with associated equipment.
The well intervention system for wireline will normally consists of the following main items:
• wireline unit;
• control cabin;
• data acquisitions;
• clamps/sheaves and hay pulley;
• power package;
• pressure test pump;
• wellhead pump;
• well control system;
• logging container (for logging and well tractor);
• wireline mast (crane);
• transport and storage racks for wireline equipment;
• slick, braided and electrical line down hole tools.
The brake system shall have a minimum capacity equal to drum pulling capacities. The drive system
shall be capable of holding the load sufficient in neutral position until brake is activated. The unit
shall be equipped with a spooling device or back-up drum for slickline.
The cabin shall have protection over windows facing upwards and equipped with splint safe
windows. There shall be minimum one extra seat
The control cabin shall facilitate all necessary controls and monitoring equipment to operate the
complete wireline unit. The controls and monitoring equipment shall as a minimum include and be
located such that operator at all times can read the following:
a) controls;
• depth counter;
• weight indicator;
• level wind control;
• reel brake;
• reel forward /reverse;
• cable speed when required for the operation.
b) BOP.
• shear seal ram;
• wireline rams;
• BOP control pressure;
• flow monitoring;
• BOP accumulator pressure.
• depth;
• tension;
• cable speed;
• tubing pressure.
Load limit requirement for sheaves and hay pulley: maximum line pull x 2 x safety factor.
Maximum line pull not to exceed 80% of the wire breaking strength and minimum safety factor: 2.
All locking devices shall have a double safety feature.
Fishing clamps for securing and pulling the wireline during fishing operations. The clamps shall be
tested to line breaking strength, and documented on a load test formulary.
Provisions shall be made for a manual ESD system that is operated locally and remotely from the
control cabin.
The power package shall be certified for operating in Zone II areas and in accordance with
NORSOK standard Z-015.
If the power package is used for charging the accumulator system for the well control equipment,
the hydraulic circuit from the well control accumulators shall be separate from the other hydraulic
circuits and only the well control system shall be able to take hydraulic pressure from the dedicated
accumulators.
The pump shall be rated to following working pressures as required for the operation:
Pump pressure
6,9 MPa 34,5 MPa 69,0 MPa 103,4 MPa
(1 000 psi) (5 000 psi) (10 000 psi) (15 000 psi)
The pump shall be rated to the following working pressures as required for the operation:
34,4 MPa (5 000 psi)/ 69,0 MPa (10 000 psi)/ 103,4 MPa (15 000 psi)
9 DOCUMENTATION
9.1 General
The following equipment is considered to be comprised by this category and shall be presented
according to NS 5820:
• snubbing equipment;
• coiled tubing equipment;
• wireline equipment.
a) substructures;
b) masts with bolts and shackles;
c) hoisting machinery with complete associated equipment;
d) running tools and workstring (tubular) and BHA;
e) BOP with choke manifold;
f) wellhead arrangement;
g) hydraulic and flange and clamp connection unit to wellhead;
h) lifting equipment/cranes;
i) deadline anchor for the wire rope of the draw-work;
j) wire rope of the draw-work;
k) testing equipment with piping arrangement;
l) high pressure piping systems and pressure vessels;
m) wire line masts and units;
n) coiled tubing equipment;
o) snubbing equipment;
p) pipehandling equipment;
q) pumping equipment;
r) power generation packages;
s) BOP control systems.
a) name of equipment;
b) production number;
c) name of manufacturer and supplier;
d) description of design and manufacture, indicating safety factors;
e) verification of design and strength control;
f) material certificates and confirmation as to where materials have been used;
g) welding procedure specifications and qualification;
h) confirmations with that manufacture, inspection and final control have been subjected to
independent verification;
i) report from testing including testing conditions, and information on how testing has been carried
out;
j) independent verification of design assumptions with regard to strength;
k) supplier’s operation and maintenance specifications, with indication of operational criteria and
limitations;
l) marking of equipment.
Updating of items in the case of modification of equipment with regard to verification of equipment,
which is lacking in documentation, adequate deviation procedure will include, but not be limited to
As stipulated by this provision, equipment shall be designed, manufactured, installed, operated and
maintained in a way that ensures its ability to resist the most extreme loads that it may become
subjected to during drilling and well operations. In connection with operations in cold climatic
conditions, the requirements to design temperature must be considered in relation to the possibility
of maintaining a controlled operation temperature at all times.
9.2.1 Downhole tools and strings for snubbing, coiled tubing and wireline
a) name of equipment;
b) production number;
c) name of manufacturer and supplier;
d) description of design and manufacture, indicating safety factor used;
e) verification of design assumptions with regard to strength, carried out by an independent survey
institution;
NOTE Depending on organisational independence, this function may be taken care of by the manufacturer.
f) material certificates and confirmation as to where materials have been used;
g) statement of manufacture and inspection signed by manufacturer and surveyor/surveying firm or
body.
Additional documentation for snubbing, coiled tubing and wireline should include
a) name of equipment;
b) production number;
c) name of manufacturer and supplier;
d) description of design and manufacture, including safety factors used. Verification of design
assumptions with regard to strength, carried out by an independent survey institution. Depending
on organisational independence, this function may be taken care of by the manufacturer;
e) supplier's operation and maintenance specifications, with indication of operational criteria and
limitations;
f) material certificates, including chemical analysis, mechanical strengths (hardness, tensile and
yield) and physical dimensions;
g) inspection report, including non-destructive inspection of coiled tubing body and welds,
locations of all imperfections and details of drift ball test;
h) report from testing including testing conditions, and information on how testing has been carried
out. Minimum required is hydrostatic test report;
i) repair record;
j) statement of manufacture and inspection signed by manufacturer and surveyor/surveying firm
and body;
k) weld procedure qualifications for welds, including x-rays;
l) weld log, including bias weld and butt weld locations;
m) welding procedure specifications and inspection/verification specifications;
n) drying procedure used.
a) log of tubing repairs, including: location of manufacturer’s welds, location of section welds,
tubing cut off, added and re-used and reason for repair;
b) log of outside diameter, ovality and wall thickness testing;
c) estimated cumulative damage and remaining life time, including evaluation and location of butt
and field welds;
d) operational limits for outside diameter and wall thickness;
e) history log of all previous jobs, including parameters influencing life time;
f) documentation on receiving-quality control of the coiled tubing;
g) marking of equipment;
h) updating of items in the case of modification of equipment;
i) quality audit of the manufacturing process;
j) pre-job inspection and testing documentation;
k) insulation (merging) test record for coiled tubing with e-line installed.
a) name of equipment;
b) production number;
c) name of manufacturer and supplier;
d) description of design and manufacture, indicating safety factor used;
e) material certificates including chemical analysis and mechanical strengths;
f) report from testing including testing conditions, and information on how testing has been carried
out;
g) quality audit of the maker's manufacturing process;
h) inspection reports;
i) physical dimensions.
ANNEX A
(informative)
Operator: D-002
Project: Rev. 1
Document no: Sep. 2000
Date and revision:
Structures snubbing
Derrick/mast /hoisting structure and hoisting 1510 kN 2930 kN
equipment minimum capacity (340 klbf) (658 klbf)
Rotary table load rating 1510 kN 2930 kN
(340 klbf) (658 klbf)
BOP handling equipment – maximum load rating kN (klb) kN (klb)
Pad eyes / hang off points for travelling
assemblies, minimum safe working load capacity 49 kN 49 kN
(11,0 klbf) (11,0 klbf)
Pad eyes/hang off points for rig tongs, work
winches etc., minimum safe working load 24 kN 24 kN
capacity (5,4 klbf) (5,4 klbf)
3
-Ref: D-001 chapter 4.4
minimum
Topdrive maximum continuos torque – minimum 9 kNm 29 kNm
(6,6 klb·ft) (21,4 klb·ft)
Topdrive breakout torque - minimum kNm (klb·ft) kNm (klb·ft)
Topdrive makeup torque – minimum 80 kNm 80 kNm
(59,0 klb·ft) (59,0 klb·ft)
Topdrive/rotary speed at maximum continuous 120 rpm 160 rpm
torque
Topdrive/rotary minimum speed at maximum 10 rpm 10 rpm
torque
Topdrive/swivel maximum speed 160 rpm 220 rpm
Topdrive/swivel minimum pressure rating 34,5 MPa 51,7 MPa
(5 000 psi) (7 500 psi)
Rotary table – minimum internal diameter 0,345 m 0,345 m
(1,13 ft) (1,13 ft)
Rotary table – minimum load rating 1510 kN 2930 kN
(340 klbf) (658 klbf)
Rotary table - minimum 160 rpm 220 rpm
Rotary table - torque, minimum 9 Nm 29 Nm
(6,6 lbf·ft) (21,4 lbf·ft)
Lifting height – to be defined. m (ft) m (ft)
System/equipment NORSOK I NORSOK II Your
choice
Pipehandling systems
Associated equipment
Minimum capacities unless otherwise specified:
Work winches 30 kN 30 kN
(6,7 klbf) (6,7 klbf)
Manrider winches 1,5 kN 1,5 kN
(337 lbf) (337 lbf)
ANNEX B
(informative)
The requirements for the safety head are to cut the actual work string in use including any wire, tube
and cable inside, and provide sealing in the bore after shearing with maximum working pressure
inside the safety head body. Additional equipment that the safety head should be capable to cut and
provide sealing effect after shearing, are listed below:
NOTE Ref. item 6 and 7, the requirements should be performed with the coiled tubing in
compression, neutral and in tension equal to 20,7 MPa (3000 psi) wellbore pressure.
ANNEX C
(informative)
ANNEX D
(informative)
BIBLIOGRAPHY