COMPLIANCE REPORT KOLKATA

VINDHYACHAL STPP STAGE-V


FLUE GAS DESULPHURIZATION PLANT SYSTEM PACKAGE
VENDOR: M/S ALSTOM INDIA LTD KOLKATA
ALSTOM JOB NO. : EEP000034
NTPC JOB NO: 2260

DOCUMENT NO ALSTOM:
DOCUMENT NO NTPC:
DOCUMENT TITLE:
NTPC TRANSMITTAL LETTER NO: CC:PE109:21871
DATE: 16-09-2016

RESOLUTIONS / ACTION BY
NTPC COMMENTS
ALSTOM

1. Manufacturer Stamp With Signature Action taken by Alstom

2. Document may be forwarded to QA for Action taken by Alstom


observations
3. Deck Sheet profile and design calculations Incorporated

4. Calculation considering negative tolerance Not Required, since No Negative thickness


on bare metal thickness, only Positive
tolerance on bare metal
5. Sheets Calculation Incorporated

6. Double line section diagram for inner and outer Incorporated


section clarity
7. Comments on Profile Drawing Incorporated