Professional Documents
Culture Documents
:
CO. LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
CONTENTS
1 INTRODUCTION
2SCOPE OF WORK
4 WORK PROGRAMME
6 METHODOLOGY
7 QUALITY ASSURANCE
SPCL ABFPL
Signature
Name
Date
Page 1 of 12
SHAPOORJI PALLONJI & CO. Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
1. INTRODUCTION:
This method statement describes the outline procedure to be followed for Piling
Work, including the method & activities required for installation of bored cast in
situ Test Piles & Working Piles by Dry Boring/Bentonite Slurry, to be executed at
Proposed Plant and Office Building Works For Alstom Bharat Forge Power
Limited at Sanand, Ahmedabad.
2. SCOPE OF WORK:
To carry out Piling work up to the required depth as per GFC drawings issued by
ABFPL.
4. WORK PROGRAMME:
The Excavation work shall be carried out in accordance with the submitted
program to ABFPL.
1. Centre of the pile location shall be marked correctly as per the GFC
drawing.
2. The location shall be identified by reference pillars/points within the site. It
is also suggested to establish two points outside the site.
3. In case, piles deviate beyond tolerable limits of the designed location or
alignment, the Engineer-in-charge shall be informed immediately.
4. Pile boring up to the specified depth should be executed by Rotary
Drilling Method´.
5. A temporary casing should be provided during the boring operations up to
the specific depth of 3 to 4 m, to avoid any collapse of surrounding soil
within the borehole.
Page 3 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
6. The inside portion of the casing shall be free from projections and
encrusted concrete.
Page 4 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
In this method pile bore shall be done using Rotary drilling rig up to
required depth using temporary guide casing/Bentonite slurry.
This method can be adopted in all types of soils for drilling operations. A
hydraulic drilling rig can be employed for cased bored piles with the casing
driven directly through the rotary head.
The piling boring operation shall be duty sequenced. Rotary Drilling with
Bentonite Mud method is adopted for boring.
1. Verticality of Kelly bar and drill mast shall be checked before boring
operation by plumb line/spirit level/level indicator attached with the rig.
2. Initially Auger/Drilling tool attached to Kelly bar will be centered on the
pile point and necessary reference points with respect to centre of pile
will be marked at right angles.
3. The boring shall be carried using drill auger /bucket initially to few
meters.
4. Then install the temporary casing 3-4m long using the rotary drive with
casing head adopter arrangement. The verticality and centre line of
casing should be always checked during installation using plumb
bob/spirit level & reference points respectively.
5. The centre line of guide casing shall be checked with respect to the
reference points before continuing further boring.
6. The bore shall be filled with bentonite slurry fed from bentonite tanks.
The bentonite slurry filled in the bore imparts stability by applying
hydrostatic pressure on wall against the impermeable membrane thin
film along the bore hole.
7. Bentonite head shall be maintained throughout the period. Head will be 2
m above ground water table.
8. Pumping of Bentonite is by high pressure pumps/ Diaphragm pumps thus
carry cuttings to surface, which will be passed through settling tank to
remove cuttings and spoils prior to recirculation.
9. Quality of slurry during preparation, boring and prior to concreting shall
Page 5 of 16
be monitored by in-situ checks.
Page 6 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
Page 7 of 16
longitudinal bars shall be made by lapping. Laps shall be tack-welded to
prevent distortion of the reinforcement cage. The number of joints in
Page 8 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
longitudinal steel bars shall be kept to a minimum and the joints should be
staggered.
3. The lateral ties/spirals shall fit closely around the main longitudinal bars
and be fixed to them by approved binding wire, the free ends of which
shall be turned towards the centre.
4. Clear cover to all main reinforcement in pile shaft shall be not less than
50mm and shall be maintained by suitable spacers. Suitable and adequate
cover blocks of durable material shall be provided to achieve the same.
The cover blocks shall be placed all along the length of reinforcement cage
with adequate number in the upper portion over the length of the
temporary casing. The cover blocks shall be aligned for smooth lowering
of the cage into the pile bore and for lifting of the temporary casing
without displacing the reinforcement cage from its position. The cover
blocks shall be manufactured with concrete of equivalent grade of
concrete designated for the pile, using the same grade and type of
cement. Alternately, the cover block shall be of more durable material
approved by client / consultant, which will not lead to corrosion of the
reinforcement or spalling of the concrete cover.
5. Placement of reinforcement cage:
Reinforcement cage shall be lowered into bore by gravity only after bore
cleaning is completed taking care to see that no collapse of soil takes
place during lowering. For piles requiring multiple lengths of reinforcement
cages, the first length of cage shall be lowered and held in position above
the bore, with top of the bars adequately strengthened, on which upper
cage is placed in position, lapped and joined in place. This portion of the
cage is then lowered. It is important to ensure that the laps are welded
before lowering.
6. U Bar shall be welded at the effective distance of 100 mm from the
reinforcement top. Latter this U bar will be tied with hook of casing top
enabling to control the reinforcement top level.
Page 9 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
6.3.7.2 Concreting
Concreting should be done with the use of tremie pipe method, to permit
deposition of concrete in successive layers, without permitting the
concrete within the placer to fall through drilling mud. Only freshly mixed
concrete shall be used. Concreting of the pile should be done immediately
after cleaning of the bore hole and placing of the reinforcement cage and
should be uninterrupted. In case of any interruption during the concreting
procedure, due to unexpected reasons, further decision should be taken in
accordance with IS: 2911.
Following points are to be noted during concreting by Tremie Pipe Method:
Page 11 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
11. Rate of placing concrete in the pile shaft shall not be less than 6m
length of pile per hour.
12. Top of concrete shall be checked with funnel type arrangement and if
fetches aggregate present in the concrete then only it shall be made
understood that concrete top level has been achieved.
13. Concrete cube samples to be taken at site at the rate 1 set (of 6 cubes,
i.e. 3 for 7 days and 3 for 28 days) / 50 cubic-meters from each RMC
source in a shift. ( refer IS 4926-2003, 6.3.2)
14. Test procedure and acceptance criteria for concrete cube test are as per
IS 516 and IS 456.
15. Random inspection shall be done by excavating pile after 7 days of
casting to review process/end result is in line with requirement.
As-build condition of each pile and all test record shall be submitted to the
Engineer as report.
Page 12 of 16
7. QUALITY ASSURANCE:
Page 13 of 16
SHAPOORJI PALLONJI & CO.
LTD. Doc. No.:
Proposed Plant and Office Building
Rev. No.:
Works For Alstom Bharat Forge Power
Limited
Page 14 of 16
work.
Page 15 of 16
SHAPOORJI PALLONJI & CO.
Doc. No.:
LTD.
Proposed Plant and Office Building Rev. No.:
Works For Alstom Bharat Forge Power
Limited
7. A first aid person shall be present at site and a first aid kit shall be
provided in site office.
8. All record of operator and plant certificate shall be kept on site at all
the times.
9. Emergency call numbers shall be posted on site for contact in
emergency.
Page 16 of 16