Etapele activitatii /Job Pericole Impact posibil Contingenta
No. / Hazards / Possible impact Masuri de control / Control measures / Contingency
steps
Before operating the Crane check for and ensure all ground
Crushing injuries (IN) workers and other vehicles are well clear of the work area (PSS &
crane operator)
Emergency Response
Ensure reverse beepers are audible and flashing lights are working
Plan
Collision with other site Damage to equipment (PL) at all times while moving (crane operator)
Operate and mobilise the Project incident reporting
vehicles and workers (A, Operating speed when driving the Crane must be done at creeping or
3. Crane
N) Equipment loss (PL) extremely slow speed (walking speed) (crane operator)
and investigation
procedure
Ground surfaces must be inspected to ensure sufficient compaction
Contingency plan
to operate on, if in doubt seek advice from the Site Manager (crane
Delay in ops (SQ) operator & PSS)
No work to be undertaken if weather conditions (wind, rain etc.)
affect the safety of the lifting operations (PSS & crane operator).
4. Lifting Potential rollover of Ensure that personnel not involved in operations is kept clear Emergency Response
Crane- Unstable or Crushing injuries (IN) of working area (VC) Plan
uneven ground Maintain good communications (operator) Project incident reporting
surface; overload (N) Team work; lifting/lowering only under supervision; the assistant to and investigation
Damage to equipment (PL) ensure lifting/ lowering equipment is safe- give clearance for procedure
Swinging loads (N) lowering equipment Contingency plan
Equipment loss (PL) Load attachments to crane to be completed by qualified riggers (PSS).
Struck by object (N)
Choose a sling of adequate capacity and determine the best means
Breaking wires and Delay in ops (SQ) of attachment (PSS & rigger/ slinger)
fittings- wires under Position the lifting assembly over the centre of gravity and aim for a
tension (N) direct lift (rigger/ slinger)
Ensure all workers, including the riggers are well clear before lifting
Falling objects (N) the load (PSS)
Smoothly and gradually raise the load to max. 1 m off the ground and
hold. Check the slinging and balance of the load (crane operator &
banksman).
When the load is stable, continue the lift until it is high enough to
clear all objects in its path (crane operator & banksman)
Tag Lines are to be used if the load is raised above shoulder height
(operator)
Maintain visual sight of crane driver at all times; If crane driver is out
of sight, lifting is to stop immediately (banksman)
Ensure safety devices are maintained as operational and that operators
know the location of these devices and how to use them.
Protective equipment to be worn as per the above- incl. safety
harness (operator)
Page 2 from 4
Etapele activitatii /Job Pericole Impact posibil Contingenta
No. / Hazards / Possible impact Masuri de control / Control measures / Contingency
steps
No work to be undertaken if weather conditions (wind, rain etc.) affect
the safety of the lifting operations (PSS & crane operator).