You are on page 1of 8

GOV-ST-41-1-APP02

Rev. date : 1 Sep 2020


Job Risk Assessment Form Rev. no. 03
Page : 1 of 8

Job Risk Assessment JRA No: CE/QTLM/SCF/IS/0522/074


Company Name: Cape East Prepared by : Date:
Group : Central Maintenance Approved by : Deepak Purkuti Date:
Department :
Job Location : Equipment:
Title of Job : To erect and dismantle Scaffolding for

Mandatory PPE required:       

Risk Score Residual


Sequence of Job Steps Potential Hazards Potential Effects before Control Measures
Risk
mitigation after mitigation
 Fitness to work  Injury / Illness to the  Ensure All Employees to be fit to work.
Mobilization and demobilization of 4-L 1–L
 Lack of knowledge individual.  Only personnel having appropriate training
manpower and equipment to and from job
site.  Wrong practices and  Resulting to error and and certifications to be mobilized for the
procedures confusing leading to scope of activities.
 Equipment failure serious injury or fatality  All personnel shall complete Client
 Damage /loss to property induction to be familiar with the site, scope,
 Damaged to equipment / hazards, Cape/ Client expectations.
property loss  Conduct pre-mobilization checks for the
equipment and inspection by QATALUM
personnel (where applicable)
 Where applicable, equipment shall be
inspection by QATALUM and only
mobilize equipment with valid certification.
 All personnel being mobilized shall be
issued with appropriate PPE for their
specific task.
Access to Workplace  Permit Violation  Injury / illness to the  Qatalum PTW together with the applicable
4-L 2–L
 Hazards related to process individual JSA shall be strictly adhered for entering
 Mechanical Hazards  Incident potentially cause inside the plant area.
 Slips, Trip and Falls damage  Ensure where applicable, gas test is

6/11/2022 Uncontrolled when printed 1


GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 2 of 8

Risk Score Residual


Sequence of Job Steps Potential Hazards Potential Effects before Control Measures
Risk
mitigation after mitigation
 Falling Materials  Material Damage / loss conducted by Client representative and the
 Damage to plant and area released is free from hazards.
equipment’s  Personnel shall be familiar with the Permit
Controls, Hazards and controls as per JRA
and the scope of work covered.
 Maintain high degree of vigilance whilst
moving around site. Do not interfere with
sensitive parts.
 As far as is reasonably practicable, all work
areas shall be kept free from trailing cables,
timber packing, tools, equipment and waste
cleared away as soon as possible.
 Do not block the plant access and
emergency equipment.
 Barricading by means of hazard tape
around material/ equipment mobilized on
site.
 All personnel are to maintain a safe
working distance from others working
overhead.
 Personnel are not to walk / work under
suspended loads.
 Hazardous environment  Exposure to Environmental  Ensure PTW and supporting documents
4-L 2-L
 Equipment failure incident potentially cause including appropriate JHA and Method
Work Preparation including PPE. damage Statement are available for the scope of
 Falling of materials  Damaged to equipment / work to be carried
property loss  Review JSA for the specific scope and
 Material Damage / loss ensure controls are adequate prior to start
the work.
 Conduct recorded toolbox talk prior to job
start to explain job specific hazards and
control measures to the work crew.
 Carry out inspection of all equipment
including PPE prior to donning to ensure
no visible damages.
 Periodic review of equipment inspection
certification to ensure validity and fit for
purpose.
 Ensure material shifted to workface is in
6/11/2022 Uncontrolled when printed 2
GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 3 of 8

Risk Score Residual


Sequence of Job Steps Potential Hazards Potential Effects before Control Measures
Risk
mitigation after mitigation
good serviceable condition and enough to
complete the scope for the shift.
 No excess material shall be left unattended
at workface.
 Identify the requirements of workplace
control including barricading and arrange
as appropriate where required.
 PSTA shall be carried out by each
individual.
 Competent and trained personnel to be
12-H 3-L
assigned for the task.
 Arrange storage of materials near
workplace using mechanical handling
Erection and Dismantle of scaffolding  Wrong Manual Handling  Exposure to Manual Handling (where practical) to reduce manual
incident/injury. handling.
 Maintain manual handling techniques for
shifting / lifting of scaffold materials.
Whilst raising tubes and boards company
manual handling assessment and procedure
shall be followed.
Adequate supervision at site by performing
party always.
 Dropped Objects.  Damage to plan and  Dropped object management procedure to
12-H 3-L
equipment’s be followed.
 Property loss  Ensure personnel are trained on dropped
object prevention.
 Incident injury
 Exclusion / drop zone shall be identified,
and adequate barricading provided to
prevent unauthorized access.
 Ensure all tools tied up with lanyard.
 Use tools Bag / Pouches to transport
scaffolding tools.
 Use certified lifting bags or basket in
serviceable condition for shifting scaffold
materials to and from high elevation.
 Hand balling may be used for shifting tubes
and boards.
 Ensure gin wheels are attached to the
scaffolding structure and secured at both
6/11/2022 Uncontrolled when printed 3
GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 4 of 8

Risk Score Residual


Sequence of Job Steps Potential Hazards Potential Effects before Control Measures
Risk
mitigation after mitigation
ends with double / swivel couplers.
 Rope to be used shall be long enough
without knots and kinks.
 Establish Twist to confirm technique to
communicate/Co-ordinate with scaffolding
crew during hand transfer operation.
 Lowering and raising scaffolding materials
will be performed safe and steady manner,
and at controlled speed.
 Inspect all scaffolds pertaining to design
drawings
 Ensure toe boards placed and platforms
closely boarded & secured without gaps.
 Do not leave loose materials at scaffolding
platform.
 Carry out dropped object inspection as per
procedure
 Slip / Trips / Falls.  Injury / Injury to the  Good Standard of House Keeping shall be
12-H 3-L
individual. maintained. (A place for everything and
 Higher Risk of Serious everything in its place always).
incident injury / Fatality  Materials stored away from access without
obstructions.
 Falling from height  Use full body harness with double lanyard
Working at height. 12-H 3-L
 Higher Risk of Serious whilst working above 2 meters and ensure
incident injury / Fatality 100% tie –off.
 Use Chin Strap for helmet while working at
height.
 Ensure harness is hooked on safe
anchorage point and hooked above waist
height as practicably possible.
 Anchorage point shall be of load bearing
and structure of adequate strength.
 Clear platform & no gap between boards.
 Handrails & Mid rails rigidly secured to
prevent fall.
Secure ladders ensure 3-point contact
whilst climbing and descending ladders.
 Scaffolding work will be suspended in case
of high wind / adverse weather condition.
6/11/2022 Uncontrolled when printed 4
GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 5 of 8

Risk Score Residual


Sequence of Job Steps Potential Hazards Potential Effects before Control Measures
Risk
mitigation after mitigation
 SIMOPS Failure  Collations between two team  Job safety risk assessments to be cascaded
9-M 3-L
 Booster bus Bar potential to cause incident to all operatives and followed at all times.
 Electrical /Injury  Any changes in environment causing
 Electrocution / electric additional risks will lead to immediate
shocked stoppage of work and review of current
 Injury / illness Risk assessment.
 SIMOPs endangering each other to be
Working near the electrical  Lack of awareness avoided jobs designated priority wise.
Equipment  Resulting to error and
confusing leading to serious  Ensure no other works are ongoing in the
injury or fatality. same area without adequate SIMOPs plan.
 Do not extend any materials to buster bus
bar area.
 Do not extend any material beyond
Working in energize area  Electrical Shock  Electrocution / electric basement fens
shocked
 All personnel shall have completed the
 Injury / Illness to the Qatalum HSE site induction
individual.
 Risk assessment Method of statement and
 Higher Risk of Serious work permit briefing and task prestart talk
incident injury / Fatality to all persons connected with the activity.
 Proper and close coordination with
operations personnel.
 Apply the personal padlock before entering
and start the work. Follow the isolation
procedure.
 Do not operate any electrical Equipment.
 Proper isolation (Lock out / Tagout) system
by authorize person only.
 Apply the personal padlock before entering
and start the work. Follow the isolation
procedure.
 Don’t operate any equipment.
Adverse weather  Heat stress  Higher Risk of Serious Illness  Rest Shelter and Ablutions at Site
12-H 3-L
 Sun Stroke / Fatality  Awareness
Hot Weather Working
 Dehydration  Erratic Behavior  Regular Breaks, Drink Water
 Poor physical fitness  Weakness, Unsteady Gait  Provide Adequate Drinking Water Nearby
 Exhibiting symptoms of  Body Temperature elevated & Implement Appropriate Work Rest
fatigue  Convulsions Scheme
 Loss of Consciousness  Operatives Are Given Information on Heat
Stress and Exhaustion During Tbt.
6/11/2022 Uncontrolled when printed 5
GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 6 of 8

Risk Score Residual


Sequence of Job Steps Potential Hazards Potential Effects before Control Measures
Risk
mitigation after mitigation
 Operatives Are Instructed to Take Regular
Breaks and Drink Water as Per Project
Heat Stress Index.
 Provide adequate cold water on site at all
times. Always provide adequate shelter on
site. Water flasks to be provided to all
operatives
 Reduce, as much as possible, the number of
activities performed outdoors
 Ensure that workers remain well hydrated
 Higher Risk of Serious Illness  Maintain personal hygiene
COVID - 19 COVID19 Infection / Spread 9-M 3-L
/ Fatality / Environmental  Masks and gloves are mandatory for self as
of Virus / Transmission
Conditions that may affect well other precautionary.
exposure  Avoid sharing tools & equipment.
 Adhere to social distancing 1.5 m.
 Try to be paperless for procedures.
 Ensure all the team who involved in the job
should have good health.
 Report to senior if anyone feeling sick or
fever.
 Follow MOPH as well as Qatalum
guidelines for self and others awareness
Area cleaning  Ongoing at all times as you work, the area
shall be cleaned and unwanted materials to
be removed.

6/11/2022 Uncontrolled when printed 6


GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 7 of 8

Likelihood or probability

1 2 3 4 5
Rare Unlikely Moderate Likely Almost certain

Property damage Might well be


Practically
Injury/illness Environmental Quite possible or expected or
(actual loss, USD) impossible, has Unlikely, but has Possible or has
has been has been
never occurred been occurred in been occurred
occurred once a occurred more
in similar similar industry in Qatalum
year in Qatalum than once per
industry
year in Qatalum
Minor incident but no
1 Insignificant immediate signs of No effect to environment < 5,000 1–L 2–L 3–L 4–L 5–L
injury/illness
Environmental incident
2 Minor First Aid Case 5,000 – 25,000 2–L 4–L 6–M 8–M 10 – M
potentially cause damage
LTI temp. disability
Environmental incident
3 Moderate Restricted Work Case 25,000 – 100,000 3–L 6–M 9–M 12 – H 15 – H
resulting minor damage
Medical Treatment Case
4 Major Single fatality Environmental incident 100,000 – 1,000,000 4–L 8–M 12 – H 16 – H 20 – H
resulting major damage to
6/11/2022 Uncontrolled when printed 7
GOV-ST-41-1-APP02
Rev. date : 1 Sep 2020
Job Risk Assessment Form Rev. no. 03
Page : 8 of 8
Severity or

LTI perm. disability Qatalum


Multiple fatality Environmental incident
5 Catastrophic Perm. disability > 10 people resulting major damage to > 1,000,000 5–L 10 – M 15 – H 20 – H 25 – H
surrounding community
Risk = Severity x Likelihood L = Low Risk (≤ 5) M = Medium Risk (6 – 10) H = High risk (≥ 11)

MANAGING RISKS

6/11/2022 Uncontrolled when printed 8

You might also like