Professional Documents
Culture Documents
ERECTED TANKS
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
CONTENTS
1. Scope
2. Purpose
3. Reference
4. Responsibility
5. Method Of Construction
6. Identification Of Materials
7. Erection
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
1 SCOPE:-
This procedure covers detailed activities for fabrication, erection and testing of the storage tanks, and also
equipment & manpower required for the same. All the tasks / activities need to be carried out with atmost care
with good workmanship and in accordance with the specifications to achieve satisfactory completion of the whole
activities.
2 PURPOSE:-
The purpose of this document is to follow proper methodology to carry out the activities in a proper sequence for
Erection and Testing of the Fuel Tanks (59-B-22-1&2)
3 REFERENCE:-
API 650
ASME Sec IX, ASME Sec V.
Approved Drawing / Specification.
4 RESPONSIBILITY:-
The responsibility of implementation of this procedure rests with CROWN STEEL & with the supervision of ATTIQ UR
REHMAN CONTRACTING EST.
SITE MANAGER: -
The Site manager is responsible over all for the implementation of the method statement
To ensure that the team of engineers and foremen and operatives are aware of this method statement.
To ensure that all resources (labor, material and equipment) are available to carry out the work as planned
He shall be responsible for implementing the company safety plan overall.
QC Engineer: -
The QA/QC Engineer is responsible for ensuring that the operations have been performed as per the specification.
Also for ensuring that the inspections are done as per Quality Control Procedure and that the Inspections
For managing all the necessary inspections, inclusive of witnessing, recording and reporting the results.
To ensure that all the inspections are executed efficiently and expeditiously in order to comply with the schedule
HSE Officer: -
He shall be responsible for the overall safety of personnel, materials and equipment, and follows.
To ensure all the operations at the site are conducted and maintained safely throughout.
To coordinate and preside over regular site safety meetings, to attain and maintain effective communications.
Site HSE Officer will be fluent conversant in the relative safety regulations of the company and the statutory
requirements of the Kingdom of Saudi Arabia.
METHOD OF STATEMENT FOR FIELD
ERECTED TANKS
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
SUPERVISOR: -
Supervisor is responsible directly to the operations.
Arrange and provide everything that is required for the operation.
Communicate methods of operation to the team and follow all methods accordingly method of statement.
If there is any deviation between the operation and method statement, immediately report to HSE officer and site in
charge
5 METHOD OF CONSTRUCTION:-
See below detail
6 IDENTIFICATION OF MATERIALS:-
Each Piece of Plates, fitting or any other component of tankage system shall be clearly identified by marking heat
no. on the part using hard punching.
Each weld joint shall be marked with joint Number with Welder Number.
7. FIELD ERECTION:-
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
Vacuum Test
Fig 3
METHOD OF STATEMENT FOR FIELD
ERECTED TANKS
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
After fit-up of bottom plates, mark the tank inner radius on the bottom plates.
Care shall be taken that the shell plate erected to the diameter marked on the bottom plate.
Jigs and fixtures shall be use to align the shell plates.
The 1st shell courses shall be erected by conventional method using crane. See the fig 5.
Shell plate horizontal and vertical plate clearances are maintained by key plates, shims and wedges.
Key plates are secured to the shell, driven wedges maintain the gap for welding.
Shims maintain the clearance on the horizontal weld see fig 6
Balance shell courses shall be erected by the same method as on figure.4, 5 & 7.
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
Fig 5
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
Fig7
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
Clean weld joints from both sides by wire brushing and grinding.
After completion of welding from both sides remove all the temporary jigs and fixtures and flush grind the tacks.
(Do the weld fill up wherever required)
Check the peaking, plumb ness, circumference and the radius, offer for inspection to the satisfaction of the client
QC.
The shell to bottom joint area from both sides shall be cleaned thoroughly to carry out the chalk-diesel test.
Apply chalk solution from inside. Apply diesel by a hand spray pump from outside, Hold it as per instruction of the
QC and check the root weld inside for any defect.
If any defect found the defect shall be repaired by grinding the defect area for the sound metal plus 150mm from
both end of the defect.
Conduct the chalk - diesel test on the repair spot. Carry out the whole process until the repair cleared to the
satisfaction of QC.
All unwanted materials and scrap shall be removed from inside of the tank.
RT shall be carried out as per API-650.
9. APPURTENANCES INSTALLATION:
Flanges to pipe joint shall be prefabricated and required NDT shall be completed before erection.
Mark the nozzle location as per drawings. Cut the openings by gas cutting after proper Inspection-by-inspection
authority.
Erect the nozzles as per the orientation & the elevation shown in the drawing.
Install reinforcement pads wherever required before nozzle erection.
Orientation, elevation & projection shall be maintained as per drawing and offer for the inspection clearance.
Welding shall be as per WPS and to be welded by the qualified welder.
All the reinforcement pad weld shall be pneumatically tested as per API 650.
Reinforcement Pad pneumatic test shall be carried out to the satisfaction of the QC.
Install the ladder and platform handrail and conduct the welding as per drawing.
10.NDT Testing:
Oil & Chalk Test ( Bottom to 1st Shell joint)
METHOD OF STATEMENT FOR FIELD
ERECTED TANKS
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
14. SAFETY:-
Safety Precautions should be followed during erection as per site requirement.
Welding cables and power cables to be laid properly as per site rules.
Proper housekeeping and clean condition shall be maintained at site as per the requirement.
15. RECORDS:-
Foundation Hand Over Report.
RFI (Request for Inspection).
Welding Inspection Report.
Vacuum Box Test Report.
Oil-Check Test report.
PT Test Report (Penetration Test Report).
RT Test Report (Radiography Test Report).
Hydrostatic Rest Report.
Painting Report.
METHOD OF STATEMENT FOR FIELD
ERECTED TANKS
Crown Specialized For Steel Contracting Co. Ltd Document Id: CS-005 Rev. No. 02
Completion Certificate.