You are on page 1of 1

SAUDI ARAMCO ID/PID - REV 0 (Standards Cutoff - August 2004)

SATR NUMBER DATE APPROVED QR NUMBER DATE


SAUDI ARAMCO TEST REPORT
WEEKLY and CUMMULATIVE WELD STATUS REPORT SATR-W-2019 30-Apr-13 WSR-071 23-Feb-19
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR LOCATION

JAZAN REFINERY AND TERMINAL PROJECT (EPC-14) 25-00024-0002 HANWHA / HIDADA JAZAN
SAUDI ARAMCO USE ONLY
SATIP NUMBER SATIP ACTIVITY NUMBER CONTRACTOR INSPECTION LEVEL MAIN CONTRACTOR (LSTK) INSP. LEVEL SAUDI ARAMCO INSPECTION LEVEL QTY. INSP. MHR's SPENT TRAVEL TIME

HCC-ITP-CS14301/02 5.6 & 5.15 H R R

PROJECT WELD STATUS REPORT - (Rev.01)


WEEKLY WELD REJECTION STATUS FROM 14-Feb-19 TO 20-Feb-19
A B C D E F G H I J K L M N O P Q R S

Joints Welded RT RT RT RT Tracer Welds Joints Joints Re-Shoot Number Weld Length Length Weld Reject Rate (%) Reject Rate (%) RT Reject Rate Alarm
RT
Categories This Week Requested This Completed This Accepted This Rejected Required Re-Shoot Last Week of RT'd (Meter) Defects (Meter) Joint Method Linear Method Backlog (Green-<5%)
Backlog
(Linear in Meter) Week Week Week This Week This Week This Week (Backlog) RT Crews This Week This Week This Week This Week Alarm (Red>5%)

1 100% 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!


Fab Shop

10%+ 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!


Welds

3 Additional Welds 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!


4 Sub-Total 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
5 100% 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
Field Welds

6 10%+ 0.000 0 0 0 0 0 0 0 0 0.000 0.000 #DIV/0! #DIV/0! 0 0 #DIV/0!


7 Additional Welds 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
8 Sub-Total 0.000 0 0 0 0 0 0 0 0 0.000 0.000 #DIV/0! #DIV/0! 0 0 #DIV/0!

WEEKLY
TOTAL
0.000 0 0 0 0 0 0 0 0 0.000 0.000 0.00% #DIV/0! 0 0 0%

CUMULATIVE WELD REJECTION STATUS FROM 12-Oct-17 TO 20-Feb-19


A B C D E F G H I J K L M N O P Q R S
Joints Welded RT RT RT RT Tracer Welds Tracer Welds Re-Shoot Re-Shoot Weld Length Length of Weld Reject Rate (%) Reject Rate (%) RT Reject Rate Alarm
RT
Categories To Date (Linear Requested Completed Accepted Rejected Required Completed Required Completed RT'd (Meter) Defects (Meter) Joint Method Linear Method Backlog (Green-<5%)
Backlog
in Meter) To Date To Date To Date To Date To Date To Date To Date To Date To Date To Date To Date To Date Alarm (Red>5%)

1 100% 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!


Fab Shop

10%+ 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!


Welds

3
Additional Welds 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
4 Sub-Total 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
5 100% 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
Field Welds

6 10%+ 587.408 203 203 151 29 13 12 23 19 44.730 0.236 14.29% 0.53% 3 3 1%


7 Additional Welds 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 #DIV/0!
8 Sub-Total 587.408 203 203 151 29 13 12 23 19 44.730 0.236 14.29% 0.53% 3 3 1%

COMMULATIVE
587.408 203 203 151 29 13 12 23 19 44.730 0.236 14.29% 0.53% 3 3 14%
TOTAL

PREPARED BY: QC VERIFIED BY: REVIEWED & VERIFIED BY: REVIEWED BY:
CONSTRUCTION REPRESENTITIVE QC INSPECTOR/SUPERVISOR MAIN CONTRACTOR or LSTK REPRESENTITIVE PID REPRESENTITIVE

NAME NAME NAME NAME

SIGN SIGN SIGN SIGN

DATE DATE DATE DATE

You might also like