You are on page 1of 11

Appendix 1.

1
Instructions to Bidder
List of Reputable Manufacturers

APPENDIX 1.1

LIST OF REPUTABLE MANUFACTURERS

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

This page is intentionally left blank

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

Appendix 1.1: List of Reputable Manufacturer

The manufacturers for the items of plant listed in Table A-1 below should be ISO 9001-2000
and ISO 14001-2004 and OHSAS 18001: 1999 certified and must submit such certificate
which is valid to date and should also submit their first issued certificate. The ISO certificate
must mention the product or service which is being sourced from the manufacturer.

Critical plant/equipment to be supplied under this Contract shall meet the minimum
criteria as set out in Table A-1.

All the equipment of different vendors shall be designed and manufactured in accordance
with the codes and standard specified in the Project Requirement (Section 4) of the tender
document.

If any equipment is designed and manufactured by any other code, then the Bidder shall
submit test certificates from international reputable quality auditor to justify and authenticate
that the material, design and manufacturing quality meets or exceeds the specified codes
and standards. Failure to comply with this requirement will result in rejection of the
subcontractor/vendor.

No exception to this requirement can be made during the Project execution.

Bidders shall furnish testimonies/certificates from the end user in support of the minimum
criteria for the following equipment listed hereunder in Table A-1.

TABLE A-1
No. Description of Item Minimum Criteria to be met

1. Gas Turbine and Manufacturer must be one of those listed in Table A-


Generator 2 List of Reputable Manufacturers for Industrial Gas
Turbines and Generators. In addition, the proposed
model should have at least two (2) years reliable
operating history outside the manufacturer’s home
country with a minimum of 12,000 fired hours.

2. Steam Turbine i. Manufacturer must be in the steam turbine


manufacturing business for at least ten (10)
years;
ii. Manufacturer should have designed,
manufactured, supplied, tested and
commissioned at least two (2) units of similar
capacity with a minimum of 40,000 hours
operating hours and at least 6,000 operating
hours in one (1) year;
iii. Manufacturer must have supplied at least ten (10)
units of steam turbines of similar or higher
capacity outside the manufacturer’s home
country; and
iv. Manufacturer must have supplied steam turbines
of similar or higher capacity to at least three (3)
countries outside of the manufacturer’s home
country of which one (1) must be an OECD
member country.

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 1
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Description of Item Minimum Criteria to be met

3. Steam Turbine Generator i. Manufacturer must be in the generator


manufacturing business for at least twenty (20)
years;
ii. Manufacturer should have designed,
manufactured, supplied, tested and
commissioned at least two (2) units of the
proposed model;
iii. Manufacturer must have supplied at least ten
(10) units of turbo-generators of similar or higher
capacity outside the manufacturer’s home
country; and
iv. Manufacturer must have supplied turbo-
generators of similar or higher capacity to at least
three (3) countries outside of the manufacturer’s
home country of which one (1) must be an OECD
member country.

4. HRSG Manufacturer must be one of those listed in Table A-


2 List of Reputable Manufacturers for HRSG. In
addition the proposed model should have at least two
(2) years reliable operating history outside the
manufacturer’s home country with a minimum of
12,000 hours.

5. Air Cooled Condenser i. Manufacturer must be in the steam turbine


condenser manufacturing business for at least
ten (10) years;
ii. Manufacturer must have supplied at least ten
(10) of similar or higher capacity units outside the
manufacturer’s home country; and
iii. Manufacturer must have supplied similar or
higher capacity units to at least three (3)
countries outside of the manufacturer’s home
country of which one (1) must be an OECD
member country.

6. Generator Circuit i. Manufacturer must be in the relevant


Breakers manufacturing business for at least ten (10)
years;
ii. Manufacturer must have delivered at least fifty
(50) GCB units of the proposed model or higher
capacity for gas turbine or steam turbine
generators;
iii. Manufacturer must have supplied similar or
higher capacity units to at least three (3)
countries outside of the manufacturer’s home
country of which one (1) must be an OECD
member country.

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 2
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Description of Item Minimum Criteria to be met

7. Generator Step-up Manufacturer must be one of those listed in Table A-


Transformers 2 List of Reputable Manufacturers for GSU
Transformers.

8. 275kV XLPE Cables i. Manufacturer must be in the relevant


manufacturing business for at least ten (10)
years; and
ii. Manufacturer must have supplied similar or
higher capacity 275kV XLPE cables to a
minimum of three (3) TNB and/or SESB projects.

9. Distributed Control Manufacturer must be one of those listed in Table A-


System 2 List of Reputable Manufacturers for DCS.

10. Interconnection Facilities, i. Subcontractor must be in the relevant high


Substation Works and voltage substation and transmission line
Transmission Works contracting work for at least five (5) years;
Subcontractor. ii. Subcontractor must have successfully completed
at least three (3) high voltage substation projects
with TNB and/or SESB; and
iii. Subcontractor must have successfully completed
at least two (2) high voltage transmission line
projects with TNB and/or SESB.

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 3
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

Table A-2 List of Reputable Manufacturers

No. Plant/Equipment Manufacturer/Subcontractor/Vendor


1. Industrial Gas Turbine a. Alstom d. Mitsubishi Heavy
and Generator b. Ansaldo Energia Industries
(Mandatory) c. General Electric e. Siemens

2. HRSG (Mandatory) a. Doosan Heavy e. NEM Modular HRSG


Industries & Systems
Construction Co. Ltd. f. Nooter-Eriksen Inc
b. Hamon Deltak g. Vogt Power
c. Kawasaki Heavy International Inc.
Industries
d. Mitsubishi Heavy
Industries

3. Generator Step-up a. ABB g. Meidensha Electric


Transformers b. Areva h. Mitsubishi Electric
(Mandatory) c. General Electric i. Siemens
d. Hyosung j. Toshiba
e. Hyundai
f. Japan AE Power
Systems

4. Distributed Control a. ABB f. Honeywell


System (Mandatory) b. Allen Bradley g. Siemens
(Rockwell) h. Toshiba
c. Alstom i. Yokogawa
d. Foxboro
e. General Electric

5. Steam Turbine a. Alstom h. Mitsubishi Heavy


(Preferred)1 b. Ansaldo Energia Industries
c. Dong Fang Steam i. Shanghai Electric
Turbine Co Ltd. Power Generation Co
d. General Electric Ltd.
e. Harbin Turbine Co j. Siemens
Ltd k. Toshiba
f. Hitachi
g. Kawasaki Heavy
Industries

6. Air Cooled Condensers a. Evapco-BLCT d. SPX Technology


(Preferred)2 b. GEA-BTT
c. Hamon

1
The manufacturers listed are those preferred by the Owner. The Bidder may propose other
manufacturers but such manufacturer must meet the experience requirement as stated in Table A-1.
2
Same note as No.1 above.

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 4
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Plant/Equipment Manufacturer/Subcontractor/Vendor


7. Deaerator and Feed a. Alstom f. KNM Process Systems
Water Storage Tanks b. BHI Sdn Bhd.
(Preferred)3 c. Ebara g. Shanghai Electric
d. Hyundai Heavy Power Generation Co.
Industries Co., Ltd . Ltd
e. Jinan Pressure h. Stork Thermeq.B.V
Vessel Factor

8. Condensate Extraction a. Alstom Bergeron c. Termomecanica


Pump (Preferred) b. Sulzer d. Torishima

9. Cycle Makeup Water a. Anderson k. H20 Innovations


System (Preferred) b. Aquatech l. Hyflux
c. Boustead Salcon m. Kaidi Water
d. CEEP n. Purac
e. CHEC Water o. Siemens
f. DCX Technologies p. United Group
Sdn Bhd q. Veolia Water
g. Degremont r. Wabag
h. ECO TEC
i. Enersave
j. GE Water

10. Boiler Feed Water a. Ebara d. Torishima


Pumps b. KSB e. Weir
(Preferred) c. Sulzer

11. Dosing System of a. CCM Water Systems e. Suzhou Saihua


Water/Steam Cycle b. Enpro Industries Instrument Control Co.,
(Preferred) c. Prominent Ltd.
d. Straton f. Zhenjiang East China
Electric Power
Equipment Factory

12. Closed Circuit Cooling a. Alfa Laval e. LHE


Heat Exchanger b. APV Manufacturing f. TSM Tech Co. Ltd
(Preferred) Co. Ltd. g. Wonil T&I
c. GEA
d. Hisaka

13. Water Treatment a. Aquatech h. lnfilco Degremont


System (Preferred) b. CHEC Water i. Purac
c. DCX Technologies j. Siemens
Sdn Bhd k. Veolia Water
d. Enersave l. Wabag
e. GE Water m. Westech Engineering
f. Hungerford & Terry Inc.
Inc.
g. Kaidi Water
3
For items 7 to 28, the listed manufacturers are those preferred by the Owner. The Bidder may
propose alternative manufacturers of equal standing and track record but the final selection will be
subject to Owner’s approval during contract negotiations.

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 5
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Plant/Equipment Manufacturer/Subcontractor/Vendor


14. Air Compressor a. AtlasCopco d. Ingersoll-Rand
(Preferred) b. Cameron e. Kobelco
c. IHI f. Sullair

15. Crane and Hoist a. Dalian Huarui Heavy e. Kone


(Preferred) Industry International f. Meloni Tecno Handling
Corporation Ltd. g. MHE Demag
(DHI•DCW Group) h. VME Material Handling
b. Demag Sdn Bhd
c. Eurocrane (Suzhou)
Ltd.
d. Henan Weihua
Machinery Co. Ltd.

16. Piping a. Baosteel q. Shanghai Changsen


(Preferred) b. BASSI LUIGI & C. Pipe Engineering Co.,
Spa Ltd
c. Beijing Datang Union r. Shenyang Dongguan
Electric Power Power Technology
Technology Co., Ltd Group Co.
d. BHR Hochdruck- s. SMST
Rohrleitungsbau t. South China Piping
GmbH lndustry Corporation
e. Cimtas u. Sumitomo
f. Dylan Belgie bvba v. Sung Kwang Bend Co.
g. Hengyang Valin w. Tectubi
Steel Tube Co. Ltd x. Tenaris
h. JFE y. TPCO
i. Kim Seng Huat z. Trouvay & Auvin Gulf
Hardware PTE LTD BSC
j. Michigan Seamless aa. V&M
Tube bb. Van Leeuwen
k. Nippon Steel cc. WuxiZhenda
l. Pantech dd. Wyman-Gordon
m. Posco ee. Yangzhou Chengde
n. Plymouth Tube Co. Steel Pipe Co.
o. Pantech
p. Seonghwa Industrial
Co., Ltd.

17. Steam Turbine Bypass a. Bopp & Reuther d. Tecnoil


Valves (Preferred) GmbH e. Weiland & Tuxhorn
b. CCI
c. Sempell AG (Tyco
Group)

18. Control Valves a. ABB Control Valves k. MIL Controls Limited


(Preferred) b. Bopp & Reuther l. Mogas
GmbH m. Samson
c. CCI n. Sempell
d. Copes Vulcan o. Shanghai Valve
e. Dresser Factory Co., Ltd

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 6
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Plant/Equipment Manufacturer/Subcontractor/Vendor


f. Emerson Process p. SUFA
g. Fisher Controls q. Weiland & Tuxhorn AG
h. Flowserve r. Weir Valves and
i. Harbin Boiler Valve Controls
Manufacturer Co.,
Ltd
j. Masoneilan

19. Large Bore HP or Alloy a. CNNC Sufa j. Kumwoo Co. Ltd.


Steel Valve (Preferred) Technology Industry k. L&T
Co., Ltd l. Neles Jamesbury
b. Dalian DV m. Neway Valve(Suzhou)
c. FLOAUTO Co. Ltd
d. GAOTE n. Pacific
e. Henan Kaifeng High o. Shanghai Valve
Pressure Valve Co., Factory Co., Ltd
Ltd p. Siekmann Econosto
f. HP Valves Oldenzaal GmbH & Co. KG
B.V. q. SUFA
g. K.V.T r. Tyco
h. KOSO s. Velan
i. KSB

20. Water & Steam Valve a. Bopp & Ruether p. Mogas


(Preferred) b. CMI Pasguini q. Neles Jamesbury
c. Conval r. Newman
d. Crosby Valve s. Raimondi
e. Dewrance t. Samshin
f. Douglas Cherro u. Sempell
g. Dresser v. Severn Glocon
h. Fisher Sanmar w. Shanghai Valve
i. Flowserve - Edward FacTory
Valves x. Toa Valve
j. Fouress y. Tyee Sanmar
k. Hangzhou World z. Velan
Wide Valve Co. aa. Volvo Metal
l. HP Valve BV bb. Weir- Atwood & Morrill
m. ILSHIN cc. Weir Valves and
n. LCM Controls
o. MIL Controls dd. Yarway/Keystone

21. Programmable Logic a. ABB i. Rockwell APL


Controllers (Preferred) b. Allen-Bradley j. Schneider
c. Emerson k. Siemens
d. Forney l. Westinghouse
e. Foxboro m. Yokogawa
f. General Electric
g. Honeywell
h. Modicon

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 7
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Plant/Equipment Manufacturer/Subcontractor/Vendor


22. Medium/High Voltage a. ABB e. Mitsubishi
Switchgear (Preferred) b. Areva f. Schneider
c. Siemens g. Toshiba
d. Hitachi

23. Pneumatic/Hydraulic a. Fisher d. Rotork


Actuator (Preferred) b. Emerson e. Samson
c. Siemens f. GE Energy

24. Motorised Actuator a. Auma c. Siemens


(Preferred) b. Emerson d. Rotork

25. Protection Relays and a. ABB d. Schneider


Metering Equipment (for b. Areva e. Hitachi
Facility only) (Preferred) c. Siemens f. GE

26. Large Motors (Preferred) a. ABB Motors i. Leechun Electric


b. Converteam j. Reliance Electric
c. Crompton Greaves k. Shanghai Electric
Ltd Machinery Works
d. GE l. Siemens
e. Harbin Electric m. TECO/Westinghouse
Machinery Works n. Toshiba
f. Hitachi o. WEG
g. Hyundai p. Xiangtan Electric
h. Kirloskar Electric

27. Fire Fighting (Preferred) a. Agbar f. Sukiada Engineering


b. ARS Sdn Bhd
c. Minimax g. Sukitronic
d. Muhibbah h. TYCO
Engineering Sdn
Bhd
e. Sanco

28. Fabricated a. Amalgamated Metal w. Mid America


Steel/Structural Steel Corp, AMC x. MMC Tepat Teknik
(Preferred) b. Asturi Metal Builders y. POSCO
(M) Sdn Bhd z. PMI
c. Bachmann aa. PSP Industries
d. BESTEEL bb. REA China
e. Betterman Engg cc. Shanghai Baoye
f. Bhilai Engineering Construction Corp. Ltd
Corporation dd. Shanghai Pwr Erection
g. CH Steel No. 2 Co.
h. Diamond ee. Shanghai Techshine
Engineering Thermal Pwr
i. Era Buildsys ff. Shin Eversendai
j. Eurotech Engineering (M) Sdn
Engineering Bhd Shin Feng
International Co. Ltd gg. Shree Alloys
k. FElDA hh. Songda-Jurong

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 8
Appendix 1.1
Instructions to Bidder
List of Reputable Manufacturers

No. Plant/Equipment Manufacturer/Subcontractor/Vendor


l. Fouress ii. Tonica Sdn Bhd
m. Guangdong Shipyard jj. Torsco
International kk. Triple S
n. Hai Phong Equip ll. United Engineers
Manuf & Shipbuilding mm. Vana Halla Heavy
Co., Ltd Industries Co., Ltd.
o. Han-Viet Heavy lnd & nn. Vantage Steel Works
Construction Corp oo. Vatana Phaisal
p. Indira Industries pp. Victor Buyck
q. KELIN qq. Visavakit Patana
r. Kencana Torsco Sdn rr. Wuxi Chuxin
Bhd ss. Xinlai
s. KNM Process tt. Zhejiang Feida
Systems
t. Lilama
u. Lisemco
v. LVEP

[300]MW Gas-Fired Combined Cycle Power Plant Project at Lahad Datu, Sabah 9