You are on page 1of 3

Project : Dasman Residential Development Date: 6/19/2020

Consultant: Al Jazera Consultants


Contractor: KMC Holding Company
Ceramic Tiles for Typical Floor

APARTMENT NUMBER
DESCRIPTION TOTAL REMARKS
1 2 3

FLOOR TILES (600 x 600)


122.500 123.300 80.900 326.700 TYPE H60048WH
TOILETS 300 x 600 (WALLS &
FLOORS) 71.700 77.600 64.700 214.000 TYPE H63061
MAIDS ROOM 300 x 600
(WALLS & FLOORS)
47.600 42.500 36.620 126.720 TYPE C63026

LOBBY (FLOOR) 600 x 600


43.400 TYPE H60088

LOBBY (WALL) 1200 x 600


44.000 TYPE H62088

GARBAGE CHUTE WALL 300 x 600


7.600 TYPE C63026

GARBAGE CHUTE FLOOR 300 x 600


2.000 TYPE C63026
Project : Dasman Residential Development Date: 19/Jun/20
Consultant: Al Jazera Consultants
Contractor: KMC Holding Company
Summary of Walls Finishes

SRL WALL FINISHES


FLOOR LEVEL REMARKS
NO.
TYPE 1 H60048WH TYPE 2 H63061 TYPE 3 C63026 TYPE 3 C63026 TYPE 4 Conkrit White SD71 TYPE 4 Conkrit White SD71 TYPE 5 H60088 TYPE 5 H62088

DESCRIPTION 600mm x 100mm (Skirting) 300mm x 600mm 600mm x 100mm (Skirting) 300 mm x 600 mm 600mm x 100mm (Skirting) 600mm x 600mm 600mm x 100mm (Skirting) 1200 mm x 600 mm
1 1ST - 26TH FLR 5.75 2A-01 Foyer 12.74 2A-02 Toilet 3 30.22 2A-09 Toilet 4 44.01 01-01 Elev. Lobby
16.48 2A-04 Master bedroom 21.62 2A-03 Toilet 1 35.47 3A-12 Toilet 4 Apt 1 - 3B
13.61 2A-05 Bedroom 1 18.24 2A-06 Toilet 2 23.11 3B-12 Toilet 4 5.70 01-01 Elev. Lobby Apt 2 - 3A
9.82 2A-07 Living/Dining Rm 24.99 3A-07 Toilet-2 17.12 3B-12 Toilet 4 4.10 01-02 Elev. Lobby Apt 3 - 2A
11.03 2A-08 Kitchen 25.37 3A-10 Toilet 1 7.59 01-05 Garbage Chute 4.90 01-06 Elev. Lobby
4.48 2A-10 Dressing Room 13.49 3A-11 Toilet 3
7.90 3A-01 Foyer 20.24 3B-08 Toilet 2
1.88 3A-02 Living 23.49 3B-11 Toilet 1
1.90 3A-03 Dining 17.12 3B-13 Toilet 3
10.80 3A-04 Kitchen
13.07 3A-05 Bedroom 1 0.84 2A-06 Toilet 2
11.84 3A-06 Passage 0.38 2A-02 Toilet 3 20.80 26-04 Changing Rm 55.86 26F-01 Elev. Lobby
11.66 3A-08 Bedroom 2 0.75 3A-07 Toilet 2 20.80 26-05 Changing Rm
19.48 3A-09 Master Bedroom 0.36 3A-11 Toilet 3
9.44 3B-01 Foyer 0.48 3B-08 Toilet 2
11.00 3B-02 Kitchen 0.36 3B-13 Toilet 3
7.98 3B-03 Living/Dining
5.30 3B-04 Passage
5.40 3B-05 Dressing Rm
13.62 3B-06 Bedroom 2
18.26 3B-07 Bedroom 1
13.18 3B-09 Master Bedroom
7.85 3B-10 Dressing Room

SUB-TOTAL 1 5,793 4,511 0 2,838 0 42 368 1,156 multiplied by


25 flrs
29.59 B3-07 Store 12.400 GF-15 Corridor 25.870 GF-16 Changing Rm
BASEMENT 3 23.760 B2-07 Store 6.950 GF-18 Lobby 14.480 GF-16A Toilet 50.962 B3-06 Lift Lobby
BASEMENT 2 23.100 B1-13 Store 8.600 GF-19 Corridor 13.030 GF-16B Shower Stall 58.818 B2-06 Lift Lobby
BASEMENT 1 21.780 B1-21 Store 13.030 GF-16C Shower Stall 57.558 B1-05 Lift Lobby
GROUND FLOOR 15.80 GF-07 Guard's Rm 35.420 GF-20/21 Garbage 24.130 GF-17 Changing Rm
9.240 GF-02 Store 14.480 GF-17A Toilet
7.260 GF-12 Store 13.030 GF-17B Shower Stall
13.750 GF-13 Store 13.030 GF-17C Shower Stall
17.750 GF-08 G. Rm Toilet

SUB-TOTAL 2 5,793 4,511 16 3,019 28 173 368 1,323

5% wastage 290 226 1 151 2 9 18 66

5% spare parts 290 226 1 151 2 9 18 66

6,372 LM 4,962 m2 18 LM 3,321 m2 32 LM 190 m2 404 LM 1,456 m2


Project : Dasman Residential Development Date: 19/Jun/20
Consultant: Al Jazera Consultants
Contractor: KMC Holding Company
Summary of Floor Finishes

SRL FLOOR FINISH


FLOOR LEVEL REMARKS
NO.
TYPE 1 H60048WH TYPE 2 H63061 TYPE 3 C63026 TYPE 4 Conkrit White SD71 TYPE 5 H60088
DESCRIPTION 600 mm x 600 mm 300 mm x 600 mm 300 mm x 600 mm 600 mm x 600 mm 600 mm x 600 mm

1ST - 26TH FLOOR 5.70 2A-01 Foyer 1.85 2A-02 Toilet 3 6.40 2A-09 Toilet 4 32.50 01-01 Elevator Lobby Apartment 1 - 3B
17.60 2A-04 Master bedroom 5.35 2A-03 Toilet 1 7.00 3A-12 Toilet 4 5.50 01-02 Apartmen Lobby Apartment 2 - 3A
12.70 2A-05 Bedroom 1 3.65 2A-06 Toilet 2 7.40 3B-12 Toilet 4 5.40 01-06 Apartmen Lobby Apartment 3 - 2A
32.70 2A-07 Living/Dining Room 4.40 3A-07 Toilet-2 2.00 01-05 Garbage Chute
8.30 2A-08 Kitchen 5.94 3A-10 Toilet 1
3.85 2A-10 Dressing Room 2.25 3A-11 Toilet 3
5.85 3A-01 Foyer 2.70 3B-08 Toilet 2
37.90 3A-02 Living 4.20 3B-11 Toilet 1
10.15 3A-03 Dining 3.13 3B-13 Toilet 3
10.05 3A-04 Kitchen
20.70 3A-05 Bedroom 1
8.65 3A-06 Passage 5.25 26-04 Changing Room 30.50 26F-01 Elevator Lobby
12.00 3A-08 Bedroom 2 5.25 26-05 Changing Room
18.02 3A-09 Master Bedroom
7.45 3B-01 Foyer
11.45 3B-02 Kitchen
38.50 3B-03 Living/Dining
9.60 3B-04 Passage
4.32 3B-05 Dressing Room
13.60 3B-06 Bedroom 2
13.43 3B-07 Bedroom 1
18.02 3B-09 Master Bedroom
6.12 3B-10 Dressing Room
SUB-TOTAL 1 8,167 837 570 11 1,116 multiplied by 25 floors
30.400 GF-15 Corridor
BASEMENT 3 10.300 B3-07 Store 8.10 GF-16 Changing Rooms 23.650 B3-06 Lift Lobby
BASEMENT 2 7.100 B2-07 Store 2.00 GF-16A Toilet 23.650 B2-06 Lobby
BASEMENT 1 7.900 B1-13 Store 2.00 GF-16B Shower Stall 25.550 B1-05 Lobby
GROUND FLOOR 6.950 B1-21 Store 2.00 GF-16C Shower Stall
13.700 GF-20/21 Garbage Room 7.10 GF-17 Changing Rooms
2.300 GF-02 Store 2.00 GF-17A Toilet
3.45 GF-12 Store 2.00 GF-17B Shower Stall
5.60 GF-13 Store 2.00 GF-17C Shower Stall
21.00 GF-07 Guard's Room 8.00 GF-18 Lobby
2.93 GF-08 Guard's Room Toilet 13.00 GF-19 Corridor

SUB-TOTAL 2 8,167 837 651 89 1,188

5% wastage 408 42 33 4 59

5% spare parts 408 42 33 4 59

NET TOTAL 8,983 m2 920 m2 716 m2 98 m2 1,307 m2