TMC M&E CRM Logs Process Flow


START In case of breakdown or fault, call (Corrective Maintenance)
CRM to notify

To refer to TERAS
Customer Call Centre
process flowchart

Sub-Con
Be present at site (within 2 hour) –
Send location and photo to M&E TE

Sub-Con

Rectify the defect accordingly

Sub-Con
NO NO
Require second
Log Settled? Fill up SMR form (Status: Pending)
level repair?

YES Sub-Con
YES
Sub-Con Sub-Con Notify TERAS of the delay. Fill EOT
form and submit to TERAS.
Fill up SMR form (Status: Completed) To issue SMR with detail
of defect and rectification
procedure. (to include TERAS
M&E TE (LPT2)
quotation where To submit EOT with justification and
Acknowledge SMR Form (signed) necessary) work program to LPT2.

M&E TE (LPT2)
Sub-Con TERAS
To issue NOD and submit Acknowledge SMR Form (signed)
Close Log in the CRM system
to LPT2
Sub-Con

END To refer to Update Log status in CRM system

NOD process
flowchart