You are on page 1of 2

Standard Building Contract Civil Engineering Contract- NJPC 2000 Contract

ZGCC4

Architect is team leader. Engineer is the team leader. Project manager is the team leader

Quantity Surveyor prepares BOQ Engineer prepares BOQ using Quantity surveyor/ Engineer
using system of measurement of standard method of measurement of prepares BOQ. Method used
building work (clause 11). Civil Engineering Quantities (clause depend on scope of work (clause
59). 4-contract documents).

Clause 5 states that Architect Clause 17 states that Engineer should Clause 20 states that
should provide all necessary provide all necessary information Administrator should provide all
information, supervise and ,supervise and approves setting out necessary information for setting
approves setting out of works. of works. out.

Approved and recommended by Revised and recommended by The committee chosen in the
Zimbabwe Institute of Quantity Zimbabwe Institute of Engineers, current edition of the contract
Surveyors, Institute of Architects of Federation of Civil Engineering govern the contract.
Zimbabwe, Construction Industry Contractors, Zimbabwe Association
Federation of Zimbabwe. of Consulting Engineers.

Payment certificates certified by the Payment certificates prepared and The Administrator certifies
Architect (clause 22). certified by the Engineer (clause62). payment certificates (clause 36).

Clause 25 states that disputes Clause 69 states that disputes are Clause 37 states that disputes are
arising are resolved via arbitration. resolved first by mediation, if it fails, resolved by an adjudicator, then
arbitration is adopted. arbitrator if the first fails.

Clause 18-Architect certifies Clause 47-Contractor is liable to Clause 35-Administrator issues


certificate of non-completion and penalties for delay through liquidated certificate of non-completion, and
Liquidated and ascertained and ascertained damages after being liquidated and ascertained
damages apply. granted extension of time. damages apply.

Nominated sub-contractor is Employer/Engineer nominates the Administrator nominates the sub-


selected/nominated by Architect to nominated sub-contractor (clause 61) contractor (clause 22).
do the specialist work (clause 20).
Clause 16-Contractor provides Clause 23-Contractor insures for new Cause 14- For existing building,
insurance for new projects and if projects and if the works are employer provides project
the works are additions and/or additions and/or alterations, insurance. For new works,
alterations, employer provides employer provides insurance for the principal contractor provides all
insurance for the works. works. risk insurance.

Variations are ordered by Architect Variations are ordered by Engineer Clause 37 allows for fluctuations
and priced using bill rates, fair and priced using bill rates, fair and adjustments to the contract
valuation and day works (clause10) valuation and day works (clause 61). sum.

Clerk of works is an inspector on Engineer’s representative inspects Consultant team inspects works
behalf of employer and works works under the Engineer’s and works under the
under Architect’s directions (clause directions and on his behalf (clause administrator’s instructions
9). 2). (clause 9.5 and 9.6).

You might also like