Professional Documents
Culture Documents
LABOUR
34. Rates of wages & hours and conditions of labour
The contractor is required to comply with all statutory
requirements relating to wages & conditions of
employment which are applicable in the area where wk
is being carried out
If there are no any statutory provisions the contractor will
pay wages which are fairly general in line with wages
given in the area where work is being carried out
Accommodation and care for employees
Contractor required to provide sanitary and first aid
services and potable water where necessary also provide
and maintain accommodation
Health and safety
Contractor required to provide healthy and safety
facilities for the workers and to comply with health and
safety codes which are issued by Zimbabwe occupation
and Safety council @ the time of tender
MATERIALS AND WORKMANSHIP
Quality of materials & workmanship & tests
may instruct
Contractor to facilitate and assist with instruments ,
machines, labour etc as they are required for examining
measuring and testing any wk
Contractor to is required to supply samples of materials
for testing before incorporation in the wks
All samples of materials which are provided for in the
bills of quantities to be supplied by the contractor @ his
cost but if not @ the cost of the employer
Cost of making tests
Cost of making tests is borne by the contractor if their
provisions is in the bills of quantities as the contractor
will allow for same in his tender
Cost of tests which are not provided for
If any test is provided for by the Eng which is not
intended or provided for in the BOQ or spec or is not
particularized
OR though intended and provided for is ordered by the Eng
and is carried out by an independent person @ any other
place than the site or place of the manufacture, the cist of
such is borne by the contractor and if workmanship &
materials is not in accordance with the provisions of the
contract or Eng’s instructions
BUT, if everything is in accordance then by the employer
Access to site
The contractor is required to facilitate access to site and
other places where work is being prepared, or materials is
being manufactured to the Eng & any other person
authorized by the him
Examination of wk before covering up
All wks need to be examined and approved by the Eng
before covering up or put out of view
The contractor is required to allow the Eng to examine &
measure the wks before they are covered up
The Eng is required to check all the foundation s before
permanent wk is placed
The contractor to give due notice to the Eng whenever
such wk or foundations is or are ready for examination
The eng should not unreasonably delay unless the Eng
considers it unnecessary and advise the contractor
accordingly
Uncovering and making openings
The contractor is required to uncover and make good any
part of the works or make openings as may be directed by
the Eng
Following such instructions if everything is found to be in
accordance with contract then such cost of uncovering and
reinstating is borne by the employer but if not by the contractor
Removal of improper work and materials
The Eng has power during progress of wk to order removal of
materials which are not oin accordance with the contract
He also has the power to make substitutions of proper and
suitable material
The removal and proper re execution of any wk in respect of
material sand workman ship which is not in accordance with
the contract
Default of contractor in compliance
If contractor defaulted in complying with such orders
The employer is entitled to employ and pay other person
to do the same and all the expenses borne by the
contractor and will be recoverable from the contractor
40: SUSPENSION OF WORKS
The contractor can suspend progress of works or any part
of the works on written order of the Eng.
Following such order the Contractor is required to protect
and secure the works during such suspension
The contractor is paid in accordance with clause 52& or
62 extra cost (if any) incurred in giving effect to such
instruction under this clause
Exceptions are given where suspension
Provided for in the contract
Necessary by reasons of weather conditions or by default on
part of the contractor
Necessary for proper execution of the wks or for safety of the
wks or any part thereof
Such necessity should not be the default of the Eng or the
employer or any of the defined risk in clause 20
The Eng is required to include any delay occasioned by suspension
into account in determining extension of time to which the contractor
is entitled under clause 44, except where suspension is provided for
in the contract or necessitated by reasons of some default on part of
the contractor
Suspension lasting more than 3 months
order of the Eng for 3 months without any written order to resume
such wks
The contracytor may serve a written notice to the Eng requiring
works
If the employer wish to take any portions of the wks
after completion or partial completion
The employer is given the power to do so, provided the
normal progress of wk is not obstructed
Maintenance and Defects
wks
If the contractor fails to do the wks as mentioned and
within the period specified
The employer is entitled to carry such wks with his
own workman or other contractors
If in carrying out such wks the contractor was suppose
to have carried @ his own cost. The employer is
entitled to recover such cost from the contractor
Temporary reinstatement (restoration)
51 (1) Variations
The Eng is allowed to make variations in terms of
quality and quantity of the wks
He also has power and authority to order the contractor
on the following
i) Increase or decrease quantity of any wk included in
the contract
ii) Omit such work
iii) Change the character or quality or kind of such wk
iv) Change the levels, lines , positions and dimensions
of any part of the wk
v) Execute additional wk or any kind necessary for
the completion of the wk including removal and
replacement of materials
Including also removal and reconstruction of wk
previously approved by the Eng as being in
accordance with the contract
No variation in any way vitiate or invalidate the
contract
The value of such variation is taken into account in ascertaining
the amount of the contract price
2) Order of variation to be in writing
Contractor not allowed to make any variations without a written
order from the Eng unless the Eng desires to give it verbally
and confirm it in writing either before or after carrying out of
the order
No order in writing is required for increase or decrease in
quantity of wk scheduled where such increase or decrease is
not a result of an order given under this clause but the increase
or decrease is as a result of the Quantities exceeding or being
less than those stated in the bills of Quantities
52: Valuation of variations
The Eng determines the amount to be added or
deducted from the sum named in the tender in
respect of
Any extra or additional wk done or wk omitted in
terms of clause 51
All such wk shall be valued @ the rates set out in the
contract. If in the opinion of the Eng the same rates
should be applicable
If the contract does not have any rates applicable. The
Eng and the contractor shall fix such prices
consistent with the rates set out in the contract
2) Authority of the Eng to fix the rates
If the nature of omission, addition or increase or
decrease in quantity whether ordered or arising
under sub clause 51(2) result in change of method
or scale of operation process of construction or
source of supply
And in the opinion of the Eng will render the rate in
the contract in applicable
The Eng in agreement with the contractor will fix such
rate or price as far as possible in consistent with the
rates or prices set out in the contract
No increase in contract price under sub clause (1) or
variation of rate or price under sub clause (2) shall be
made
Unless as soon as practicable notice is given in
writing or in case of extra wk or additional wk it
should be given before the commencement or soon
The Eng should write to the contractor of his intention
to vary a rate or price as the case maybe
Failure to agree
57.Quantities
The quantities set out in the bill of quantities are
estimated quantities and they are not supposed to be
taken as actual or correct quantities of the wks
58. The Eng is required to ascertain and determine
the value of the wks done in accordance with the
contract
The Eng or Rep are required to make measurements
and are required to give notice to the contractor
when making such measurements who shall also
attend or sent a qualified agent
If the contractor fails to attend or neglect or omit to
(b)
Overdue payments
The contractor is entitled for interest @ a rate per annum
equivalent to the prevailing commercial bank rate for
overdrafts +2% on all monies payable to him but unpaid
Urgent Repairs