Professional Documents
Culture Documents
A - PG - 029 - Anl - 08: Destructive Testing of Weld Connections
A - PG - 029 - Anl - 08: Destructive Testing of Weld Connections
Issue: 2
A_PG_029_Anl_08 Substitute for:
A_PG_029_Anl_08 / 08.10.2004
Correction note to this edition: Changes for documentation, Testing sequences, Macro Sections, description destructive testing.
The required penetration usually is fixed by the customer. If there are no requirements of the customer the
definitions of Annex 9 must be used. The results of the test must be documented in a quality control chart. This
can be done on paper or in digital form. On components without critical characteristics, a visual check of the
macro section (effective weld seam cross-section and seam height) is sufficient.
The required dimensions have to be considered from the valid weld drawing or the Annex 9.
C/ Photographic documentation
At weld seams with special requirements (e.g. critical issues CCs/ BCCs) the macro sections must be
documented additionally with a photographic documentation system.
The following information must be recorded with the picture: penetration, effective weld seam thickness,
component number and the number of the macro section.
Notice
The testing method has to be defined by the project team.
If there is no decision by the project team, the standard method A/ will be applied.
Issue: 2
A_PG_029_Anl_08 Substitute for:
A_PG_029_Anl_08 / 08.10.2004
2. Testing intervals
Testing intervals for prototype manufacturing
See VA “Prototype Manufacturing (at product groups and plants)”
Minimum requirements:
To *:
a) 1 welding fixture/ day, but with a fixed sequence of the fixtures
e.g. 3 welding fixtures:
Week 1: A-B-C-A-B
Week 2: C-A-B-C-A
Week 3: B-C-A-B-C
etc.
b) At production lines with identical welding cells with only one fixture, the cells have to be tested in a fixed
sequence, i.e. they are treated like fixtures in example a).
c) Final assemblies and sub assemblies are tested separately as described under topic a). On final
assemblies, only the weld seams between the sub assemblies have to be tested.
To **.
a) Additional demand for macro sections has to be taken out of the same welding fixture. On this component
only the not-ok weld seam has to be tested.
b) Critical or uncertain weld connections must be tested in a higher sequence, e.g. every 4 h or directly before
the batch delivery.
c) Macro sections has to be carried out after the following process changes:
Change of the welding speed, welding direction, position of manipulator, welding sequence, change of
welding torch and power source.
Issue: 2
A_PG_029_Anl_08 Substitute for:
A_PG_029_Anl_08 / 08.10.2004
Series production:
For a ‘not ok’ result of the macro-section test, the documentation of the destructive shop floor testing method
has to be checked immediately, the respective connection has to be crosschecked by means of the shop floor
test, and a visual inspection of the affected weld seam in the intermediate box of the series process has to be
executed.
For re-release of production after optimization, a macro section has to be repeated for the affected weld seam
to prove the effectiveness of the taken measures. The result has to be documented.
For a ‘not ok’ result of the shop floor method, the complete intermediate box and, if necessary, the in-house
stock have to be blocked.
Note: In some cases, it is not allowed to rework welding errors due to customer instructions or internal
determinations (risk step resulting from the FMEA).
These parts must be scrapped immediately!
The serial numbers of the scrapped assembly have to be documented.
Issue: 2
A_PG_029_Anl_08 Substitute for:
A_PG_029_Anl_08 / 08.10.2004
Bending test:
The specimen must be prepared in such a way,
that the weld seams can be bent by hammer or
special tools. The cuts must be deeper than the
weld seam, ensuring that only the weld seam is
tested and not the base material. The specimen
must be bent parallel to the surface of the
component.
Pull Test:
Issue: 2
A_PG_029_Anl_08 Substitute for:
A_PG_029_Anl_08 / 08.10.2004
Squeeze test