Professional Documents
Culture Documents
TASLA
6.6.1.2 Polymer Modified Cement Mortars are used for repairs on old hardened concrete for
repairing defects on exposed concrete surface only. For larger repair areas with thickness
in excess of 50 mm, concrete, as repair material, is a better option. For thicker
applications, over larger areas, it is desirable to use appropriate reinforcing mesh fixed
with U-nails. These shall use Polymers admixed in specified proportions, based on
selection criterion given in Chapter 5. Other materials shall be same as in Portland
Cement Mortars stated above. However, these shall follow the given relevant
specifications, if specified.
6.6.1.3 Epoxy Mortars: These mortars consist of resin, hardener and silica sand and are applied
over an epoxy bonding coat over old hardened concrete surface.. These mortars attain
strength in few hours. These mortars have very high strength and are abrasion resistant,
water resistant and can be used in few millimeter thickness overlays. These are used
for repairs at locations where
l It is difficult to use epoxy bonded concrete,
l Depth of repair is less than 40 mm or
l Repair areas are small (less than 0.1 sqm) and few in number.
When depth of repair exceeds 15 mm but is less than 40 mm, the build up of patch
repair over large areas shall be in layers using appropriate reinforcing mesh fixed with
U-nails or shear keys. 6
HARD WOOD
If the epoxy is used as bonding material between the repair material and the substrate,
the method is termed as Epoxy Bonded Dry Pack. Its application shall be limited to
areas that are small in width and relatively deep but not less than 25 mm in depth..
The application areas include core holes, holes left by removal of form-ties,
cone-bolts, she bolt holes, narrow slits for critical repairs or for repairs expected to be
exposed to severe service conditions. Dry pack shall neither be used for shallow
depressions where lateral restraint cannot be obtained nor for filling behind steel
reinforcement.
INJECTION TUBES
WITHDRAWN AS GROUT
RISES
WALL FORMWORK WITH
RAKING SUPPORTS
FOUNDATION
REINORCEMENT
OVERLOW VENT
GAP GRADED
AGGREGATE INLET FOR GROUTING
STEP-1 STEP-2
GAP GRADED AGGREGATE WASHED,FREE OF FINES FORMS ARE FITTED WITH PIPES AND NIPPLES
AND BOND-INHIBITING MATERIALS ARE PLACED IN AND VALVES FOR PLACEMENT OF GROUT.
CAVITY.
OVERLOW VENT
PUMP
STEP-3
FLOWABLE GROUT IS MIXED AND PUMPED INTO STEP-4
FORAMED CAVITY, FILLING SPACE BETWEEN AGGREGATE. FORMS ARE REMOVED AND SURFACE IS FINISHED
6
there are optimum amounts of fillers and admixtures to produce the best pumpability or
consistency. Proper proportioning for the structural grout mix components is necessary to get
the required strength and durability of the finished pre-placed aggregate concrete. Trial mix
design is necessary for each job.
In underwater repair, injection of grout at the bottom of the PAC displaces water, leaving a
homogenous mass of concrete with minimum of paste wash out. In such applications, addition
of anti wash admixtures minimizes the paste wash out. For underwater PAC, the quality of
underwater should also be tested to determine its influence on PAC over a period of time for
taking appropriate corrective action.
6.6.4 Shotcrete
Shotcrete is defined as pneumatically applied concrete or mortar placed directly on to a
surface. The shotcrete shall be placed by either the dry mix or wet mix process.
The dry mix process (Fig 6.5) shall consist of
l Thoroughly mixing the dry materials,
l Feeding of these materials into mechanical feeder or gun,
l Carrying the materials by compressed air through a hose to a special nozzle,
l Introducing water at nozzle point and intimately mixing it with other ingredients
at the nozzle;
l Jetting the mixture from the nozzle at high velocity on to the surface to receive
the shotcrete.
Central Designs Organisation VI-7
HANDBOOK ON REPAIRS & REHABILITATION OF RCC BUILDINGS
PUMP
NOZZLE
WATER
MIXED MATERIAL IS
PLACED INTO PUMP
NOZZLE
SIDE PLATES
GLUE LINE
by fire, chemical break down, rusting or simply bad workmanship. Since epoxy is prone to
premature debonding, use of mechanical anchorage along with epoxy bonding is considered
more reliable.
Since the steel plates are unobtrusive, with this technique original sizes of the structural members
are not increased significantly. This method is preferred where enlargement of the members
is going to affect the headroom, existing windows, doors and other fixtures.
design the strengthening in this manner, but detailing must be right to ensure transfer of load to
the new jacket, if the old concrete fails. It is however, necessary to ensure perfect bond also
between the old and new concrete by providing shear keys and effective bond coat with the
use of epoxy or polymer modified cement slurry giving strength not less than that of new
concrete.
Plate bonding and RC jacketing are the common methods of strengthening RCC structures
(detail procedure and stages given in Fig 6.8). The cost difference between the two methods
is not significant. A choice has to be made between the two methods based on actual needs
and the suitability of each method with respect to the structural /architectural and other details
of buildings.
ADDED LONGITUDINAL
REINFORCEMENT
CONCRETE
SEALING WITH
6 RESIN MIX
C.C. JACKETTING
TOPMOST STOREY
4 C4
IMPORTANT
1 FOR PROPPING/SUPPORTING ANY COLUMN AT TOP,LOWEST
OR INTERMEDIATE STOREYS, PROPS SHALL BE PROVIDED AT
ALL STOREYS BELOW ALL BEAMS MEETING AT COLUMN.
1 C1
LOWEST STOREY A
ELEVATION
TUBULAR PIPE/BUILT UP PROP
Fig 6.9 Typical Arrangement For Propping & Supporting a Column to Releive at Form Load
FIBRE WRAP
CONCRETE SECTION
TENSION CRACK
Fig 6.10 Fibre wrap technique for improving load carrying capacity of a column.
METHOD A
BOND COAT OF
SUNEPOXY 368
EXISTING NEW
M20 GRADE CONCRETE
METHOD A
BOND COAT OF
SUNEPOXY 368
EXISTING
6
M20 GRADE CONCRETE
NEW
METHOD A
c. Joints: The joints play crucial for resisting earthquake forces. The joints can be
strengthening by enlargement, jacketing by steel collar and fibre wrap.
l Beams: These can be strengthened for:
a. Flexural Strength: The flexural strength of the beam can be enhanced by
i. Section enlargement in compression,
ii. Additional reinforcement in the tension. Caution shall be exercised to
ensure that section is not over reinforced while providing additional
reinforcement to compensate loss of reinforcement due to corrosion
etc.
iii. The provisioning for enhanced tensile strength if being undertaken,
this should be accompanied with corresponding increase in compression
as well .Due to such increased flexural capacities extra shear capacities
required to ensure ductile behaviour during earthquake shall also
considered for provision.
iv. MS plate bonding
v. High Strength Fibre Fabric Wrap Technique (without section
enlargement)
ORIGINAL SECTION
INCREASED SECTION WITH MICRO CONCRETE/
SHORTCRETE SELF COMPACTION CONCRETE
FIXING OF STRRUP WITH
EPOXY AND QUARTZ SAND
MORTAR AS SPECIFIED
TENSION REINFORCEMENT
TENSION REINFORCEMENT
b. Shear Strength: The shear strength of the beam can be enhanced by any of the
following:
i.Section enlargement
ii.Shear ties anchored in compression zone of beam.
iii.Post tension strap around the section
iv. Diagonally anchored bolts (the holes are drilled perpendicular to the
possible shear cracks)
v. MS Steel plate bonding
vi. Fibre wraps
l Slabs: The performance of the slab can be improved by providing overlays
(in case of negative moment deficiency) or underlay (in case of positive moment
deficiency). The addition of overlay/underlay will also increase the stiffness of
the slabs and control the excessive deflections problems. The slabs are generally
safe in shear and as such no need is likely to occur for shear strengthening except
flat slabs near column capital.
6.7.3 Compressive Strength of Concrete: The concrete strength can be enhanced substantially
by impregnation with specific polymers. The process has already been explained under section
6.5.9
6.7.4 Cracks/Joints: The concrete and masonry are weak in tension. The cracks indicate the
tensile failure of the material. The cause of cracking should be examined in detail and remedial
measures taken accordingly. Inactive (i.e. non-moving) cracks in masonry can be repaired
by stitching. Grouting with non-shrink grouts also repairs these types of cracks. The active
cracks required for accommodating thermal movements shall be repaired by suitably locating
the expansion joints and filling them with flexible materials like poly-sulphides, bituminous
fillers etc.
6.7.5 Masonry: The masonry may be required to be strengthened for resisting earthquake forces
by external pre-stressing, splint and bandage methods. The techniques are explained in IS:
13935-1993
REPAIR STEPS :
REINFORCED CEMENT
CONCRETE 1:2:4
REINFORCEMENT BARS
CRACK
Fig. 6.14(b) Elevation of Brick Masonry Wall Showing Typical Cracks (Vertical or Diagonal)
Appendix 6.1
Structural Repairs to RCC Columns, Beams and Slabs
CASE-I: Crack Repair and Protective Coating for less damaged structural members
like minor/hair cracks or spalling from beams and columns, where
carbonation depth in cover concrete has not reached reinforcement level.
Caution: It may be stated that recommended measures are cosmetic measures.
The distress may continue to take place even after repairs, if the protective coating,
provided as per step no. 7 below, is damaged or ineffective.
Step-1: Measures shall be taken to ensure that no seepage/leakage etc. affects
the RCC columns/beams.
Step-2: The plaster/finishes over the RCC columns/beams shall be removed as
per relevant item in sub head 2 of Chapter 8 and relevant specifications
in Chapter 9. The concrete surface exposed, spalled and loose cover
concrete removed, cracks marked after close examination on the surface
of concrete. Whereas the good surface of concrete shall be hacked and
roughened for receiving the repair as per relevant item in sub heads 4 &
5 of Chapter 8 and relevant specifications in Chapter 9.
Step-3: Wherever loose/spalled cover concrete is removed, it shall be repaired
6
with polymer modified cement mortar, done up in layers as per
nomenclature of items in sub-heads 4 & 5 of Chapter 8 and relevant
specifications in Chapter 9.
Step-4: All cracks in RCC columns/beams wherever noticed shall be sealed by
injection grouting through nipples fixed along the crack line as per
nomenclature of items in sub head 3 of Chapter 8 and relevant
specifications in Chapter 9.
Step-5: Over the prepared surface of RCC columns/beams, 6 mm thick 1:3
cement sand plaster shall be applied with polymer modified cement
ENTRY PORT WITH ONE-WAY NIPPLE CHASE A V-GROOVE ALONG THE CRACKS
FOLLOWED BY WATER-JETTED CLEANING
CL
5 4 3 2 1 6 7 8 9
ALTERNATIVE A
CL
8 6 4 2 1 3 5 7 9
ALTERNATIVE B
SEQUENCE OF INJECTION OPERATION
Step-5: Fix shear key bars of appropriate diameter at specified spacings in both
directions over the surface to be covered with repair materials as per
the nomenclature of items in subhead 2 of Chapter 8 and relevant
specifications in Chapter 9.
Step-6: The rusted reinforcement shall be cleaned of rust and passivated and
applied bond coating as per the nomenclature and of items in subhead 4
of Chapter 8 and relevant specifications in Chapter 9.
Step-7: The prepared concrete surface shall be covered with appropriate mix of
polymer modified cement sand mortar in layers including behind
reinforcement over a bond coat with polymer modified cement slurry
as per the nomenclature of items in subhead 4 & 5 of Chapter 8 and
relevant specifications in Chapter 9. The mortar cover thickness shall
be not less than 15 mm over the reinforcement. The maximum thickness
shall be not more than 30 mm with each layer not exceeding 10 mm.
Fig. 6.16 Typical repair procedure for patch repair and corrosion damaged concrete
Step-8: Water curing shall be carried out for a minimum period of 7 days as per the
nomenclature and of items in subhead 6 of Chapter 8 and relevant
specifications in Chapter 9.
Step-9: Necessary white washing /painting of the surface may be carried out
after the curing period is over and the surface gets dried up.
(ii) Shotcreting: (For repair jobs covering large areas and/ or large magnitude)
Stepwise sequence of methodology to be adopted is given hereunder
Step-1: Step no. 1 to 6 shall be same as in case of no. (i) above.
Step-7: Shotcreting with average thickness of 50 mm shall be done within the
tacking period of epoxy bond coat to be applied over the prepared surface
of concrete.
Step-8: Finishing plaster if necessary, may be provided within 48 hours of
shotcreting without allowing the RCC slab to become dry during the
intervening period.
Step-9: Water curing shall be carried out for a minimum period of 7 days as per
the nomenclature and of items in subhead 6 of Chapter 8 and relevant
specifications in Chapter 9.
6
TIMBER FORM WORK AND
CROSS FRAMING SECOND STAGE
GUNITE / SHORTCRETE
SHUTTER FINISHED SURFACE
(A) BEAM REPAIR (TIMBER FORM WORK REMOVED)
FINISHED GUNITE/
FIRST STAGE SHORTCRETE
GUNITE / SHORTCRETE
SECOND STAGE
GUNITE / SHORTCRETE
a. REMOVE COVER CONCRETE b. FIXED SCREEDS AND SPRAY TWO SIDES c. SPRAY REMAINING SIDES AND
APPLY FLASH COAT TO FULL AREA
(B) COLUMN REPAIR
Appendix 6.2
TREATMENT OF DEPRESSED FLOOR IN TOILETS/KITCHEN
Stepwise sequence of methodology to be adopted is given hereunder
Step-1 Remove all materials /flooring from the sunken floors and expose the drainage
pipes/G.I. water supply lines.
Step-2 Test the G.I. water supply lines less than 6 kg per sq.cm. Water pressure
using the pressure-testing machine with pressure guage, which is readily
available in the market.
Step-3 Test the drainage pipes and other joints for leakages if any, by plugging of
horizontal pipe at tee junction with vertical stack and filling with water upto
the finished floor level for 48 hours. Leakages noticed, if any, shall be attended
to.
Step-4 Provide 40 mm dia G.I.pipe spout and CC flooring with water proofing
compound laid in slope(1:48 minimum) for draining out leaking water, if
any, from the sunken portion in the shaft.
Step-5 Provide 12mm thick cement plaster 1:3(1cement:3 fine sand) mixed with
water proofing compound on the vertical walls of the sunken portion including
providing necessary repair around the drainage spout provided.
6
CEMENT PLASTER
WATER TIGHT JOINT
BRICK WALL
BITUMEN COATING
KHURRA 150 X 150 (MIN.)
"A"
DRAINAGE SPOUT
R.C.C. SLAB R.C.C. BEAM
GRADING CONC. 1:1.5:3
(WITH NEAT CEMENT PUNNING)
STONE AGGREGATE
CEMENT CONC. 1:5:10
FLOORING
DETAIL AT "A"
STEP 2 - GRADING CONCRETE 1:1.5:3 LAID TO SLOPE TOWARDS DRAINING SPOUT WITH FLOATING COAT OF NEAT CEMENT
STEP 3 - PROVIDE AND LAY WATER SUPPLY & DRAINING PIPES & TEST FOR LEAKAGE THE DRAINAGE /SANITARY PIPES
SHALL BE LAID TO SLOPE AND A CLEAR GAP UNDERNEATH THE PIPES SHALL BE MADE AVAILABLE BY PROVIDING SUITABLE
C.C. BLOCKS AT APPROPRIATE LOCATION FOR FREE FLOW (OF LEAKED WATER ,IF ANY ) TOWARDS DRAINAGE SPOUT.
STEP 4 - 18 MM TH. CEMENT PLASTER 1:3 ON VERTICAL FACES MIXED WITH POLYMER MODIFIED WITH WATER PROOFING
COMPOUND AND FLOATING COAT OF POLYMER MODIFIED NEAT CEMENT SLURRY & COATED WITH BITUMEN (2 COATS)
STEP 5 - 150 MM TH. 20 MM SINGLE SIZED STONE AGGRAGATE TO PROVIDE A FILTER MEDIA FOR ANY LEAKING WATER TO
TRAVEL TO DRAIN SPOUT BELOW C.C. 1:5:10 ( 1-CEMENT : 5-COARSE SAND : 10-40 MM & DOWN GRADED STONE AGGREGATE )
NOTE :- 1. WATER PROOFING TREATMENT SHALL BE UNDERTAKEN ONLY WHEN ALL DRAINAGE PIPES / SANITARY PIPES /
DRAINAGE SPOUT ETC. HAVE ALL BEEN LAID AND TESTED.
Fig. 6.18 Typical arrangement for treatment of Depressed Floor of Toilets etc.