Professional Documents
Culture Documents
Civil Engineers
Geotechnical Engineering 163
April 2010 Issue GE2
Pages 65–81
doi: 10.1680/geng.2010.163.2.65
Paper 800011
Received 12/02/2008
Accepted 08/07/2009
Nguyen Tien Dung Sung Gyo Chung Sung Ryul Kim
Keywords: foundations/design PhD student, School of Civil Professor, School of Civil Assistant Professor, School of
methods & aids/piles & piling Engineering, Dong-A Engineering, Dong-A Civil Engineering, Dong-A
University, Busan, Korea University, Busan, Korea University, Busan, Korea
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 65
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
approaches to sophisticated non-linear finite-element (FE) consider the effects of pile cap stiffness in the application of
analyses. They may roughly be categorised as follows the above methods, since they were originally proposed based
on the basis of perfectly flexible or rigid footings. Some well-
(a) the empirical or semi-empirical approach (e.g. Meyerhof, documented case studies are then back-analysed in order to
1976; Vesic, 1977) examine the applicability of the proposed methods. Through
(b) the equivalent raft or pier approach, which was initially the various comparisons, the key factors that affect settlement
proposed by Terzaghi and Peck (1967) and then later are discussed, and finally preferred methods are recommended
improved (e.g. Fellenius, 1991; Poulos, 1993) for practical design.
(c) the interaction factor approach (e.g. Poulos and Davis,
1980; Randolph and Wroth, 1979)
2. METHODS FOR THE EQUIVALENT RAFT
(d ) the numerical analysis approach (e.g. Chow, 1986).
APPROACH
66 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Reference Formula Parameters
pbld
Meyerhof SRaft ¼ p ¼ equivalent net pressure applied to equivalent raft; Id ¼ influence factor for
(1976)* 2q c embedment; b ¼ width of pile group; qc ¼ average cone tip resistance in influence zone
Lp of b; Es ¼ 2qc ¼ average elastic modulus in influence zone.
Id ¼ 1 > 0:5
8B
X
n
˜ pi
2:1 method* SRaft ¼ FD hi ˜pi , h i and Esi ¼ effective stress increment based on 2:1 assumption, thickness and
i¼1
E si elastic modulus of ith sublayer respectively; n ¼ number of sublayers; FD ¼ embedment
correction factor (Fox, 1948).
X
n
I zi h i
Schmertmann S Raft ¼ C1 C2 p C1 ¼ embedment correction factor; C2 ¼ creep correction factor; Iz i , h i and Es i ¼
et al. (1978)* i¼1
E si vertical strain influence factor, thickness and elastic modulus of ith sublayer respectively;
p ¼ net pressure at equivalent raft; n ¼ number of sublayers.
X
n
(Qd þ Qns i )h i
Fellenius (1991) Sed ¼ Qd ¼ average dead load applied to a pile; Qnsi , h i , Api and Epi ¼ drag load, P
length, cross-
i¼1
Api E pi sectional area, and elastic modulus of ith segment of the pile respectively; ni1 hi ¼
SRaft ¼ f (˜ p, E s ) depth from pile head to equivalent raft (neutral plane position); ˜p and Es ¼ effective
stress increment and elastic modulus of soil layers below neutral plane respectively.
QG Leq
Poulos (1993) Se ¼ FD ¼ embedment correction factor (Fox, 1948); p ¼ equivalent net pressure applied to
Aeq E eq equivalent raft; Izi , h i and E si ¼ vertical strain influence factor, thickness and elastic
Xn modulus of ith sublayer respectively; QG ¼ total dead load applied to group; Leq , Aeq
I zi
SRaft ¼ FD p hi and Eeq ¼ length, cross-sectional area and elastic modulus of equivalent free standing
i¼1
E si column respectively.
Conceptually, the settlement computation for pile foundations Horikoshi and Randolph (1997) reviewed various existing
based on the equivalent raft is not significantly different from proposals for raft/soil stiffness ratio and then proposed a new
that for shallow foundations. It is thus probable that the raft– expression. As well as considering the effect of Poisson’s ratio,
soil stiffness approach applied for shallow foundations can be the new expression takes into account the effect of the raft
extended to the equivalent raft concept to approximately take aspect ratio (b/a) and produces the same raft/soil stiffness ratio
into account the effect of pile cap stiffness with the following for both square and circular rafts that have the same area. Thus
assumptions. the new expression would be most reasonable for estimating
the raft/soil stiffness ratio. However, it was suggested without
(a) Piles are distributed fairly uniformly throughout the cap the provision of graphical charts that present the settlement
and have equal lengths, so that the stiffness of pile–soil influence factor as a function of the raft/soil stiffness ratio, as
equivalent material under the cap is relatively the same for is required for practical use. In this study, therefore, the
each soil layer. following two separate definitions for the raft/soil stiffness
(b) For simplicity, no degrees of freedom between piles and ratio for circular and rectangular rafts are adopted.
cap are considered, and the contact between the cap and
the pile–soil equivalent material below the cap is For circular rafts, Clancy (1993) examined the effect of r on
frictionless. the differential settlement of rafts and confirmed that the raft/
(c) Soil layers are horizontally homogeneous within the soil stiffness ratio should be more rationally given in the form
foundation area.
3
(d ) As the stiffness of piles is actually much larger than that of Er 1 2s tr
the soils, the deformation shape of the pile cap, which is 1 K rs,C ¼
Es 1 2r r
simply placed at the equivalent footing level, is considered
to be similar to that of the soil plane at the pile tips.
where r is the radius of the raft, and the other parameters are
In summary, these assumptions imply that the equivalent the same as those given below for Equation 2. Pile caps in this
footing as well as the pile tip plane is subjected to the same study are simply modelled as the rafts in Equations 1 and 2.
deformation shape of the pile cap.
For rectangular rafts, the comprehensive solution proposed by
From the above-mentioned assumptions, the settlement of a Fraser and Wardle (1976) is applied in this study, in which the
piled foundation with reinforced cap can be solved raft/soil stiffness ratio is given as
approximately by using the raft/soil stiffness ratio approach
3
adopted for shallow foundations. The extension is not 4 E r 1 2s tr
conceptually applicable for complex foundations that involve 2 K rs,FW ¼
3 E s 1 2r b
significant differences in pile lengths, pile cap thicknesses, and
horizontal variation of soil layers. For these cases, rigorous
analyses are needed to predict the settlement. where Er is the elastic modulus of the raft and Es is the
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 67
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
equivalent elastic modulus of the soil layers below the 1·6
equivalent raft (which can approximately be taken as the IA
1·4
weighted average in an influence zone of b below the
where I is the settlement influence factor, which is a function The raft/soil stiffness ratio (Krs ) in Equation 5 was adopted by
of raft thickness and raft dimensions for the ideal case being Mayne and Poulos (1999) without considering the Poisson’s
discussed. Fraser and Wardle (1976) suggested several typical ratio of either raft or soil materials (i.e. excluding the term
charts for rectangular rafts in which the factor I can be (1 2s )=(1 v2r ) in Equation 1). However, because the
determined based on the raft/soil stiffness ratio. Among the difference in magnitude between the Poisson’s ratios and their
charts, two typical cases (a ¼ b and a ¼ 2b) are reproduced as second order in the equation is insignificant, their effect is also
shown in Figures 1 and 2. Based on the charts, a correction insignificant in practice. Thus the raft/soil stiffness ratio given
factor for raft stiffness, f, can generally be defined as in Equation 1 can approximately be used in association with
Equation 5.
6 SRaft,corr ¼ f A SRaft
where I and Iflexible are settlement influence factors at the given
Krs,FW and for fully flexible rafts (Krs,FW , 0.001) respectively.
The methods were basically proposed for estimating settlement
only at the centre point (except the Fellenius (1991) method,
1·2 which is implemented in association with the Unisettle
IA
program). If settlement at some particular points (e.g. middle
1·0
Settlement influence factor, I
0
10⫺4 10⫺3 10⫺2 10⫺1 100 101 102 where IA and IAB are the settlement influence factor at A and
Krs,FW the differential settlement influence factor between A and B
respectively.
Figure 1. Settlement influence factor of a square raft
The above expressions for the stiffness correction were
68 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
basically described for the methods developed based on the
1 ó9v0 þ ˜ó9v
flexible footing concept. For the method developed based on 9 å¼ ln
m ó9v0
rigid footings (Schmertmann et al., 1978), the correction
procedures are essentially the same as those described above.
However, the denominators in Equations 4 and 7 must be where m is the modulus number (¼ M 0 =ó9v0 ). The constrained
replaced by the settlement influence factor for rigid modulus (M0 ) in this case can be obtained from available field
foundations, Irigid . tests.
Finally, the total settlement at a given point (e.g. at point A) of In the Unisettle program, the stress increment and settlement at
the pile group is then given by any particular point below the equivalent footing level are
determined based on the Boussinesq or Westergaard stress
8 SG ¼ Se þ f A SRaft distribution theories (hereafter referred to as Fellenius (1991)-B,
and Fellenius (1991)-W, respectively), in association with the
Janbu (1963) tangent modulus concept. In this study, the
2.3. Equivalent raft level elastic modulus and Poisson’s ratio of concrete material are
Much of the success of the equivalent raft approach depends generally taken as 25 GPa and 0.2 respectively.
upon the selection of the representative depth of the raft and
the angle of load spread (Poulos, 2006). In practical design, 3. COMPARISON OF SETTLEMENT FOR CASE
several proposals have been made for determining the level of STUDIES
the equivalent raft, of which the approach proposed by
Tomlinson (1986) appears to be a convenient and useful 3.1. Methodology of analysis
approximation. In Tomlinson’s approach, the level of the In order to verify the applicability of the methods provided in
equivalent raft varies from 2/3Lp to Lp when soil profiles are Table 1, six well-documented case studies were selected and
purely cohesive, when pile toes are located in a sand layer back-analysed in this study. These include different types of
underlain by a clay layer, or when pile toes are located on hard structure, such as high-rise buildings, chimneys and silos, with
stratum such as a gravel or rock basement. Practical soil various foundation types: flexible footings (in the first two
profiles are not usually ideal, unlike the proposal profiles, but cases), rigid footings (in the next two cases) and semi-rigid
they are layered with a significant difference in footings (in the last two cases).
compressibility.
As discussed by Randolph (1994), the accuracy of the
In this study, the equivalent raft level is considered to be located equivalent raft approach relates to the aspect ratio of the
:
at the neutral plane (NP) at which the relative settlement group, R ¼ (ns/Lp )0 5 . The aspect ratio of each pile group is
between the pile and the soil is zero (i.e. the level where examined in this study to confirm whether the equivalent raft
negative skin friction changes to positive skin friction). The NP or the equivalent pier is more suitable. The calculated aspect
implementation has been incorporated in the Unified Design ratios from the case studies are given in Table 2, in which savg
concept (Fellenius, 2004). Coincidentally, all the case studies in is the average spacing between piles in the group, with a
this paper are associated with base-expanded (Franki) piled simplification that p
theffiffiffiffiffipiles
pffiffiffi
are installed in square nets of
foundations in which pile toe resistance is predominant over savg 3 savg (savg ¼ ab=( n 1)). It is shown from Table 2
bearing capacity. Thus, by analysing load transfer curves, it was that the lowest aspect ratio (R ¼ 3.04 from case 3) is still at the
found that the neutral planes for the cases are located at the pile lower bound for the equivalent raft. Thus all pile groups in this
toe level, with the exception of the case of Borsetto et al. (1991). study will be treated as equivalent rafts.
The NP location of a particular pile group is sketched, together
with the vertical cross-section of the group. 3.2. Case 1: DeJong and Harris (1971)
DeJong and Harris (1971) reported the measured and back-
2.4. Consolidation settlement and other conditions analysed settlements of two multi-storey buildings in
The consolidation settlement of sandwiched clay layers under Edmonton, Alberta, Canada. A 27-floor apartment and office
the NP can contribute a significant amount to the total building was supported by a total of 239 Franki (base-
settlement of the pile group, especially when the clays are in expanded) piles. As shown in Figure 3, the total area of the
high compressibility. In this study, consolidation settlement of building was approximately 37.5 m 3 66 m (b 3 a), consisting
clay layers (cases 3, 4, and 5)
is taken into account for
methods that use stress or
strain distribution under the Case Reference a: m b: m n (pile) savg : m Lp : m R
equivalent raft (i.e. the last
four methods listed in 1 DeJong and Harris (1971) 60.4 17.4 179 2.62 4.9 9.8
Table 1). If the consolidation 2 Koerner and Partos (1974) 33.5 24.3 132 2.72 7.6 6.9
parameters of the clays (Cc , 3 Hooper and Wood (1977) 27.6 16.5 48 3.60 18.6 3.0
4 Borsetto et al. (1991) 26.9 26.9 281 1.71 25.0 4.4
e0 ) are not available from
5 Goossens and Van Impe (1991) 85.1 34.3 697 2.13 13.4 10.5
laboratory test, then 6 Tejchman et al. (2001) 51.0 17.5 264 1.96 13.5 6.2
consolidation settlement is
evaluated by using the Table 2. Aspect ratio of pile groups
equation
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 69
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Soil profile Soil properties Piles and foundation plan
0
Silty clay
NP 4·9 m
5
Unit: kN-m
17·4 m
37·5 m
15 qc 143 180 240
Depth: m
N ⫽ 106 (b/ft) 6
7 8 9 10
Es ⫽1000*(N1)60
20 ⫽ 100 MPa 4
3 2 1
5
Dense sand N ⬎ 110 (b/ft)
25
and gravel Es ⫽1000*(N1)60
⫽ 100 MPa
30 60·4 m
66·0 m
Bedrock
Pile cap Franki expanded-base pile Settlement plug Approximate boundary
35
10
founded by 179 piles, mostly consisting of small footings of
8
four piles, which were distributed quite regularly over the area.
6
Franki piles 50–60 cm in diameter were installed to a depth of
4
4.9 m in the overconsolidated clay till layer. The final dead
2
load under operating condition was approximately 258.1 MN
0
over the central area. The soil profile and properties are shown
0 500 1000 1500 2000
in Figure 3. Time: day
0
Group 3 Group 9
The construction of the building was started in August 1964 Group 5 Group 10
and was completed in January 1966 (approximately 500 days). 10 Group 8 Group 11
Settlement monitoring commenced at around 100 days after Group 12
Settlement: mm
70 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Method Case 1: DeJong and Harris (1971) Case 2: Koerner and Partos (1974)
Se Sed ¼ 1 mm, Sm ¼ 33.0 mm, FD ¼ 0.95, Se Sed ¼ 1.8 mm, Sm ¼ 85.0 mm, FD ¼ 0.94,
fA ¼ 1.25* fA ¼ 1.28*
modulus was obtained from the soil that had been consolidated pile caps. The total dead load of the building was estimated as
by the accumulated dead weight of the building during the 107 MN under operating conditions.
construction period of around 500 days, whereas the SPT result
was obtained from the natural soil. In addition, the embedment The installation of piles was completed during the winter of
effect of the equivalent footings was not taken into account in 1967–1968. The construction of the pile caps, floor slab and
the DeJong and Harris (1971) back-analysis that led to superstructure commenced in February 1968, and the
increasing of the modulus. construction of the superstructure was completed in August
1969 (after 630 days). Settlements of the building were
3.3. Case 2: Koerner and Partos (1974) monitored at the six locations shown in Figure 5, at the
Koerner and Partos (1974) reported settlement monitoring of a commencement of the construction of the superstructure. The
19-floor concrete building supported by cast-in-situ base- monitoring period continued for more than 24 months, when
expanded piles that were placed in a medium dense sand layer. there was no further sign of settlement occurring at any of the
As shown in Figure 5, the foundation plan was approximately points.
24.3 m 3 33.5 m, with a total of 132 cast-in-place piles. The
cased piles were 410 mm in diameter and 7.6 m long, with an The results from the SPT were used as the main data to
expanded base diameter of about 760 mm. There were determine deformation characteristics of the soils. As shown in
generally two different grouping types for the pile caps in the Figure 5, the corrected (N1 )60 values were then used to obtain
central and the remaining areas. There were no basement the elastic modulus of the sand layers, while referring to
floors, and the structural floor slab was placed directly on the AASHTO (1996) and FHWA (2002) when the SPT numbers were
Navg
Soil profile N Es (MPa) Piles and foundation plan
(N1)60
0
4 9·5
Fine sand 6·00
15 15·0 0·41 m
7·6 m
1 2 3 4 5 6 7 8 9
Organic clay 3
5 3·00
4 A
NP
20 0·76 m
10 B
Poorly graded 22 11·82
21·5
fine sand 700*(N1)60
23 16·9 C
15
24·3 m
21
Depth: m
F
25 120
130 48·73
Poorly graded
140 69·6 700*(N1)60
fine sand G
30
Column 33·5 m
Bearing stratum Pile cap Franki expanded-base pile Settlement benchmark Approximate boundary
35
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 71
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
larger than 50. In this case, the total area of the foundation is extremely large settlement of the pile group. For the second
modelled as a single and flexible footing. method, application of the equation SG ¼ Q G RG I 1 =LEs ,
originally proposed by Morgan and Poulos (1968) for pile
Point E-6 is approximately taken as the central point of the groups up to 5 3 5, was then extended to the foundation of
footing because no measured data were available at the centre 132 piles (group 11.5 3 11.5). The extension provided a
of the building. Figure 6 shows the settlement measured at the settlement of 81 mm for the group, which compared
monitoring columns against time as well as the calculated favourably with the measured data provided in Figure 6.
results from the proposed methods (provided in Table 3). It Finally, Skempton’s (1952) empirical equation SG =S1 ¼
appears that the Poulos (1993) and Fellenius (1991)-W methods (4b þ 9)2 =(b þ 12)2 was applied, where the settlement of a
agree well with the monitored value. single pile, S1 , was obtained from the static loading test.
Using b ¼ 24 m and S1 ¼ 5.8 mm, a group settlement SG of
It is interesting to observe the prediction of settlement carried 76 mm was obtained. The last two estimations were slightly
out by Koerner and Partos (1974), in which settlement at the less than the measured maximum values.
centre of the building was estimated using three methods:
classical elastic theory, modified elastic theory, and 3.4. Case 3: Hooper and Wood (1977)
empirical equation. For the first method, the equation Hooper and Wood (1977) reported a comparative study on
s ¼ pbI(1 2 )=E s was adopted for the settlement of a settlement between two almost identical 22-storey buildings
single pile. They concluded that the estimated settlement was that had different foundation types. The two buildings, one
significantly larger than the measured value from the static supported by a raft foundation and the other by cast-in-situ
loading test on a single pile, which would result in an base-expanded piles, were located approximately 50 m apart
and had the same foundation plan of 456 m2 . Figure 7 shows
the foundation plan of the building that was supported by 48
0 cast-in-situ base-expanded piles (under-reamed piles). The pile
Meyerhof Poulos
10 2:1 method Fellenius (1991)-B shaft diameters varied from 762 mm to 910 mm, and the
20
Schmertmann et al. Fellenius (1991)-W diameter of the under-reamed bases varied from 1.2 to 2.0 m.
40 The pile lengths varied from 17.8 m to 19.4 m (an average
E-1
Settlement: mm
50
value of 18.6 m was taken in this study). Between pile caps, the
D-1
thickness of the ground-floor slab varied from 152 mm to
60
A-5 229 mm, and the pile caps themselves were 910 mm thick.
70 F-5
80 D-3
One special element of the project is that in situ concrete walls
90 E-6
Maximum measured settlement were used in the construction of the first two storeys (ground
100
plus mezzanine floors). The remaining superstructure consisted
110 of precast concrete units with in situ stitches. The estimated
0 100 200 300 400 500 600 700
Time: day
gross building weight was 106 MN, equivalent to a uniformly
distributed load of 232 kPa. In order to simplify the settlement
Figure 6. Measured and calculated settlements for case 2 calculation, the total foundation system is modelled as an
equivalent rectangle 16.5 m (456 m2 /27.6 m) wide.
10
13·5 m
M0 ⫽ 6 ⫹ z
15 London Clay 2
(z ⫽ 0⫺17)
A 6
18.6 m
NP
Depth: m
20
D ⫽ 1·2–2·0 m
m ⫽ 84
25
1
Woolwich and Es ⫽ 200·0 MPa
30 8.0 m
Reading beds (constant) 8
6.6 m 7
35
6.6 m 6.4 m
Cast-in-situ concrete wall
Thanet sands
40 Es ⫽ 4000·0 MPa
and chalk Franki expanded-base pile (pile and under-ream illustrations) Settlement benchmark
72 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Figure 7 also shows the soil profile of the case. As reported, the Because the in situ concrete walls of the first two storeys, in
constrained modulus of the 17 m thick London Clay layer combination with pile caps, were adopted as an equivalent
varied linearly with depth, with an approximate relationship concrete raft with a thickness of 4 m (Hooper and Wood, 1977),
M0 ¼ 6 + 1.0z, where z is the depth from the upper boundary the foundation can no longer be considered to be flexible.
of the layer. The clay layer was followed by Woolwich and Using Equation 2 with Er ¼ 25 GPa, Es ¼ 159.2 MPa, r ¼
Reading beds (14 m thick) and Thanet sands with chalk (12 m), 0.20, s ¼ 0.25 and tr ¼ 4 m, a raft/soil stiffness ratio of Krs,FW
with elastic moduli of 200 MPa and 4000 MPa respectively. ¼ 2.90 was obtained for this case. As shown in Figures 1 and
Further details of these two layers were not provided. 2, the raft/soil stiffness ratio is quite close to the lower
boundary of the truly rigid raft, as Krs,FW > 5 (Fraser and
Construction of the building commenced in February 1968 and Wardle, 1976). By interpolating the charts, a correction factor
was completed after almost 2 years, as illustrated in Figure 8. fA ¼ 0.795 was obtained for the methods of flexible
Settlements were measured at the eight points shown in Figure foundations, and fA 1.00 was obtained for the Schmertmann
7, and the monitoring process continued for more than 5 years et al. (1978) method. Because the settlement at point 7 was
(February 1968 to August 1974), at the stage when the similar to that at the centre points, as shown in Figure 6, the
settlement of the building was almost complete. Figure 8 shows consideration of rigidity is reasonable. It appears that the
the average settlement against time monitored at points 2 and predicted settlement obtained from the Poulos (1993) method
6, and those obtained from the FE analysis performed by agrees well with the monitored value.
Hooper and Wood (1977). In addition, the calculated
settlements at point A (the centre of the equivalent footing)
were also plotted (values given in Table 4). 3.5. Case 4: Borsetto et al. (1991)
Borsetto et al. (1991) reported the measured and computed
settlements of several structures in a power plant complex in
Applied load: MN
0
0·4 year
10 were also modelled as the equivalent material (Es ¼
0·8 year
2100 MPa) used in this study for the free-standing column.
20
5·0 years Whereas the modulus of the sand layer (non-reinforced
30
portion) was adopted as 80 MPa (approximately 7qc ) for the
Figure 8. Measured and calculated settlements for case 3 best-fit FE approach of Fiesta/Edom, it was taken as
33.8 MPa (¼ 3qc ) in this study. Since no reliable data were
Method Case 3: Hooper and Wood (1977) Case 4: Borsetto et al. (1991)
Se ¼ 2.9 mm, Sed ¼ 3.9 mm, Sm ¼ 23 mm, Se ¼ 2.8 mm, Sed ¼ 6.3 mm, Sm ¼ 40 mm,
FD ¼ 0.75, fA ¼ 0.795 FD ¼ 0.75, f 0 ¼ 0.80
Meyerhof (1976) 20.7 16.5 19.4 0.84 66.7 53.3 56.1 1.40
2:1 method 26.5 21.1 24.0 1.04 41.2 33.0 35.8 0.90
Schmertmann et al. (1978) 11.0 11.0 13.9 0.60 27.5 27.5 30.3 0.76
Poulos (1993) 26.4 21.0 23.9 1.04 47.9 38.3 41.1 1.03
Fellenius (1991)-B 36.5 29.0 32.9 1.43 71.3 57.0 63.3 1.58
Fellenius (1991)-W 31.6 25.1 29.0 1.26 55.1 44.1 50.4 1.26
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 73
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
4·25 m
Soil profile 0 5 10 15 20 Es: MPa Foundation plan
0
qc: MPa
5·20
5 Clayey silt (2·5qc)
10
28·0 m
15 11·60
25·0 m
Silt (2·5qc)
20
Depth: m
25
NP
30 33·80
(3·0qc) Footing plan
Sand
35
40 σ⬘: kPa e O
52 0·748
104 0·736 150·0
45
Hard clayey 260 0·703 (Back-analysed) 30·4 m
silt 520 0·675
281 Franki piles
50 1040 0·639
Bearing stratum
available for the hard clayey silt, the modulus of this layer
was therefore taken as 150 MPa, which was adopted for the 200
Applied load: MN
20 FE analyses
the centre of the chimney foundation, the predicted results Measured
from the three FE approaches carried out by Borsetto et al. 30
(1991) (Fiesta/Edom, Edom and Omega), and the calculated
40 Omega
results obtained in this study.
Fiesta/Edom
50 Edom
The 4.25 m thick pile cap in this case is simplified to be an
equivalent circular raft situated at the neutral plane location. 60
Using Equation 1 with Er ¼ 25 GPa, Es ¼ 93.59 MPa, r ¼ 0 500 1000 1500 2000 2500
Time: day
0.20, s ¼ 0.25 and tr ¼ 4.25 m, a raft/soil stiffness ratio of
Krs,C ¼ 5.70 was then obtained. Using Equation 5, a
Figure 10. Measured and calculated settlements for case 4
correction factor at the footing centre fO ¼ 0.80 can be
achieved for the method of flexible foundations and fO ¼
1.00 for the Schmertmann et al. (1978) method. The as 80 MPa, the calculated settlements would be significantly
calculated settlements are provided in Table 4. It appears that underestimated in comparison with the monitored values,
the Poulos (1993) method gives the best agreement with the because the modulus of the sand layer (approximately 7qc )
monitored value. If the modulus of the sand layer was taken was overestimated.
74 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
3.6. Case 5: Goossens and Van Impe (1991) (1991) performed a settlement analysis for the foundation and
In this case, a block of 40 cylindrical reinforced concrete silos, showed that the long-term settlement at point 2A was 190 mm.
each 52 m high and 8 m in diameter, covered a rectangular Thus the settlement was considered as the total settlement.
area 34.3 m by 85.1 m. The silos were built on a 1.2 m thick
foundation slab which was supported by 697 driven cast-in- The foundation system worked as three independent footings in
situ reinforced concrete piles. Because of the very large area, terms of stiffness (because of the expansion joints), but it
the slab was split into three blocks (Figure 11), using expansion behaved as a large combined foundation in terms of stress
joints in order to allow some differential settlement. The pile distribution. In order to calculate the stress increment and
length and diameter were 13.4 m and 0.52 m respectively. The settlement at point 2A, point O2 (centre block 2) is considered
diameter of the expanded base varied, with an average value of as the approximate centre of the total flexible footing (34.3 m
0.8 m. The average pile load under operating conditions was 3 85.1 m). Thereafter, settlement at point 2A is simply
about 1.3 MN. A main tower 75 m high was built 8 m away corrected by considering only the stiffness effect of block 2.
from the short edge of the silo block. Figure 11 shows brief soil Using Equation 2, a raft/soil stiffness ratio of Krs,FW ¼ 0.14 was
property profiles and a foundation plan of the silos. obtained for block 2 (a/b 1), with Es ¼ 14 420 kPa (weighted
average), and similar parameters for the concrete were taken as
Only five settlement monitoring points were able to be set up those for previous cases. Using Equation 7 and Figure 1, two
along the long edge of the block, as shown in Figure 11. The stiffness correction factors of f2A ¼ 0.76 and
monitoring commenced in September 1976 and continued until f2A 1.00 at point 2A were obtained for the methods of
February 1987, when the consolidation settlement had not fully flexible and rigid foundations respectively. The settlements at
ceased. The maximum settlement at point 2A was recorded in point 2A were then calculated, as given in Table 5. Similarly,
February 1987 at about 185 mm. Goossens and Van Impe settlements at points 1 and 2 were also calculated by using the
12·3 1 2 2A 3 4
(2·5qc) Settlement benchmark
5
Main Cast-in-situ concrete pile
34·3 m
34·3 m 2·09 m
Dense sand 32·0
25 (3·0qc)
Settlement
Mo ⫽ 2·5qc joint
MOS 6
8·36 m
Settlement
40 SLT 585 joint
CPT profile MOS 1
Bearing stratum
at MOS 6
Method Case 5: Goossens and Van Impe (1991) Case 6: Tejchman et al. (2001)
Se ¼ 3.2 mm, Sed ¼ 3.9 mm, Sm ¼ 190 mm, Se ¼ 2.0 mm, Sed ¼ 3.7 mm, Sm ¼ 18.0 mm,
FD ¼ 0.92, f2A ¼ 0.76 FD ¼ 0.85, fB ¼ 0.79
Meyerhof (1976) 698.0 530.5 533.7 2.80 62.7 49.5 51.5 2.86
2:1 method 260.0 197.6 200.8 1.06 28.1 22.2 24.2 1.34
Schmertmann et al. (1978) 164.0 164.0 167.2 0.88 18.5 18.1 20.1 1.12
Poulos (1993) 246.3 187.2 190.4 1.00 25.5 20.1 22.1 1.23
Fellenius (1991)-B 327.7 249.1 253.0 1.33 33.3 26.3 30.0 1.67
Fellenius (1991)-W 274.8 208.8 212.7 1.12 27.7 21.8 25.6 1.42
Note: f 2A 1 and f B ¼ 0.98 for Schmertmann et al. (1978) method in cases 5 and 6 respectively.
Table 5. Settlements from case 5 (point 2A) and case 6 (mid-edge point)
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 75
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Unisettle program and extending the Poulos (1993) method (see the silo block, the settlement of the silo block was slightly
Appendix 1). tilted to the main tower side following a long period of
consolidation. However, this effect was not considered owing
Figure 12 shows the monitored settlement curves obtained to the simplification of the methods.
from the five points and the calculated settlements at points
1, 2 and 2A. At point 2A, the Poulos (1993) method gives 3.7. Case 6: Tejchman et al. (2001)
the best agreement with the monitored result, whereas the A settlement analysis for a block (17.5 m 3 51.0 m) consisting
2:1 method slightly overestimates it. At points 1 and 2, both of 12 cylindrical reinforced concrete silos was presented by
the extended Poulos (1993) method and the Unisettle Tejchman et al. (2001). The 8.36 m diameter silos were built on
program overestimate the monitored values. It appears in this a 0.5 m thick foundation slab, which was supported by 264
case that the discrepancy between the monitored and driven cast-in-situ reinforced concrete piles. As shown in
calculated settlements was due to the complexity of the split Figure 13, each silo was apparently supported by 22 circularly
foundation. As the construction of the main tower was distributed piles. The pile length and diameter were 13.5 m and
completed about 1 month before the start of construction of 0.508 m respectively. The diameter of the expanded base varied
1 2 2A 3 4
0
20 Meyerhof Poulos
22 Sep 1976
2:1 method Fellenius (1991)-B
40
Schmertmann et al. Fellenius (1991)-W
60
80 30 Oct 1978
Settlement: mm
100
Soil profile 0 10 20 30
0 Piles and foundation plan
qc: MPa Es: MPa
0·5 m
Fill C 11 12 13
2 1·5 m B
4·65 m
2·45 m
m
4 0·508 m
10
4·
Fine sand
13·5 m
6 48·8
8
17·50 m
8·20 m
A
Clay 7 8
10 0·60
44·40
Depth: m
12
69·50
NP
4·65 m
14 D ⫽ 0·6 m
59·20
16 51·80 2
Dense sands 59·2 1 25·50 m 3
18
11 12 13 14 15 16
20 Test pile Silo Settlement benchmark
S-6 S-5 S-4 S-3 S-2 S-1
17·5 m
69·50 No. P3
7 8 9 10
22 S-12 S-11 S-10 S-9 S-8 S-7 Pile cap Vibrex pile
24 1 2 3 4 5 6
CPT No.12
51·0 m
76 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
from one location to another, having an average value of
Meyerhof Poulos
0.62 m. The average pile load under operating conditions was 2:1 method Felenius (1991)-B
about 880 kN. Figure 13 briefly shows the soil properties of the 3·0 Schmertmann et al. Fellenius (1991)-W
site and the foundation plan of the silos, where the qc profile
from CPT was obtained at borehole No. 12 and the elastic 2·5
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 77
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
In contrast to the interaction factor approach, the high-strain given in Appendix 1. Figure 16 shows a comparison between
elastic modulus of soils below the pile toes is generally the ratios of settlements obtained from the Janbu tangent
recommended for the equivalent raft approach (Poulos, 1993). modulus concept and those obtained from the linear strain
This is also supported by these case studies, indicating that the factor concept. The settlement ratios shown in Figure 16 were
monitored settlements are comparable with the predicted calculated with consideration of the stiffness correction factor
settlements estimated using common values of elastic modulus. ( f ). However, the elastic settlements of the pile group (Se or
In the equivalent raft approach, settlement of the foundation is Sed ) were not taken into account owing to the different
caused mainly by the soils below the pile toes, since the calculation approaches.
equivalent material (reinforced zone) is much stiffer than the
original soils. Thus, although the pile spacing and installation As can be seen in the figure, the original Fellenius (1991)-B
methods significantly affect the settlement predicted from the method (s ¼ 0) provides an average ratio of 1.37, yet when a
interaction approach, these factors are relatively insignificant Poisson’s ratio of s ¼ 0.25 is used in the extended Fellenius
in the equivalent raft approach. (1991)-B method, the ratio is only 1.08. If the elastic settlement
of pile groups is taken into account in each method, the ratios
given in Figure 16 would increase slightly to 1.38, 1.07 and
4.3. Settlements of flexible foundations at various points
1.10 respectively. Theoretically, one might expect that the
A comparison of settlements at various points was carried out
extended Fellenius (1991)-B method could give an average
for flexible footings (cases 1 and 2) as shown in Table 6 by
settlement ratio of 1.10 3 1.04 ¼ 1.14 in comparison with the
using the Unisettle program and extending the Poulos (1993)
measured data from the case studies.
method (with the principle provided in Appendix 1). The
extended Poulos (1993) method again shows reasonably
No consistent trend was found for the settlement ratios when
consistent settlement ratios, which resulted in an average ratio
the same Poisson’s ratios were used in the concepts. However,
of 0.96, followed by the average ratio of 1.09 obtained by
it seems that the Janbu tangent modulus concept is either
Fellenius (1991)-W. The Fellenius (1991)-B method consistently
almost similar to, or sometimes slightly overestimates, the
overestimates the settlements, with an average settlement ratio
of 1.36.
Generally, the average ratios and detailed values given in Table 2·0
6 show a similar trend to those in Figure 15, indicating that
Settlement ratio, SFellenius/SPoulos
78 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
strain factor concept. It is also interesting to note from Figure The original Fellenius (1991)-B method ( ¼ 0) overestimated
16 that when the same Poisson’s ratios are used for the settlements of the structures by approximately 1.4 times the
concepts, the settlement ratios appear to be similar. The monitored values. When a common Poisson’s ratio of soils ¼
similarity of the ratios indicates that the Poisson’s ratio is not a 0.25 and stiffness correction are properly applied, the method
governing factor of the difference between the concepts, but could be reasonably used, since in this study it resulted in an
the effective stress of the soil profiles. average settlement ratio of about 1.14.
4.5. Consideration of pile cap flexibility Based on the comparison with the case studies, it cannot be
Based on previous discussions, the 2:1, Poulos (1993) and recommended that the empirical method of Meyerhof (1976) or
Fellenius (1991) methods are considered to be the most the strain factor method of Schmertmann et al. (1978) be used
reasonable for the settlement calculation of large-scale piled for estimating settlement of very large pile groups founded on
foundations in practice. However, these methods were basically stratified and inhomogeneous soils.
suggested for flexible foundations. A simple comparison is
shown in Table 7, where the settlement ratios from the last four Some researchers have claimed that the low-strain shear
cases in this study are provided. The 2:1 and Poulos (1993) modulus (G0 ) can successfully be employed in the prediction of
methods slightly overestimated settlements for the cases by as settlement by using the interaction approach for pile groups
much as an average ratio of about 1.08 with an approximate designed with a relative high factor of safety. Conversely, it
correction factor ( f ) of 0.78. If stiffness correction factors had was found from this study that the high-strain elastic modulus
not been considered, the two methods would have considerably values commonly suggested for foundations in practice can be
overestimated settlements for the cases, with an average successfully used in the equivalent raft approach.
settlement ratio of 1.38 (¼ 1.08/0.78). The overestimation
would be even more serious for the Fellenius (1991) method if APPENDIX 1. INTEGRATION OF BOUSSINESQ’S
stiffness correction were not considered. STRESS DISTRIBUTION
The following equations are integration stress components at
5. CONCLUSIONS depth z under a corner of a rectangular loaded area with length
Four common methods of the equivalent raft approach and a a 3 width b founded on an infinite elastic half-space (Poulos
semi-empirical method were reviewed, followed by back- and Davis, 1974).
analysis of six well-documented case studies in order to
determine the reliable methods in practical design of larger- Vertical stress component
scale pile groups. The conclusions drawn from the research are
as follows.
ó0 ab 1 1 z
10 óz ¼ arctan þ ab þ
The stiffness of the pile cap and the horizontal stress 2 zC A2 B2 C
increment, as the key factors, significantly affected the
settlement estimation of large-scale pile groups. With the Horizontal stress component in a direction:
extension of stiffness correction techniques for shallow
foundations to pile caps, the Poulos (1993) method, with ¼
0.25, resulted in the best estimation of settlement, which was ó0 ab ab z
11 óa ¼ arctan 2
1.0–1.1 times that of the measured data. The simple 2:1 2 zC A C
method with stiffness correction, even without consideration of
the horizontal stress increment, also gave reasonable
Horizontal stress component in b direction:
estimations of settlement at the centre of foundations, which
were 1.07 times the monitored values.
ó0 ab ab z
Although the effect of pile cap stiffness was conservatively 12 ób ¼ arctan 2
2 zC B C
considered, as were the shallow foundations, the estimated
settlements of the foundations were found to be acceptable. It
may be expected that the simplified assumptions can be where ó0 is uniformly distributed pressure, A2 ¼ a2 + z 2 , B2 ¼
applied for practical design. b2 + z 2 and C2 ¼ a2 + b2 + z 2 .
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 79
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Vertical strain distribution along the depth at the corner of the of the 2nd International Conference on Soil Mechanics and
loaded area is then determined by Hooke’s Law as Foundation Engineering, Rotterdam 1: 129–132.
Fraser RA and Wardle LJ (1976) Numerical analysis of
1 rectangular raft on layered foundations. Géotechnique 26(4):
13 åZ ¼ ½ó z s ðóa þ ó b Þ
Es 613–630.
Goossens D and Van Impe WF (1991) Long term settlement of a
pile group foundation in sand, overlaying a clayey layer.
ACKNOWLEDGEMENTS Proceedings of the 10th European Conference on Soil
This work was supported by the Korea Science and Engineering Mechanics and Foundation Engineering, Florence 1: 425–428.
Foundation (KOSEF) NRL Programme, grant-funded by the Hooper JA and Wood LA (1977) Comparative behaviour of raft
Korean government (MEST) (No. R0A-2008-000-20076-0), and and piled foundations. Proceedings of the 9th International
by Dong-A University, Busan Korea. Conference on Soil Mechanics and Foundation Engineering,
Tokyo, 545–550.
REFERENCES Horikoshi K and Randolph MF (1997) On the definition of raft–
AASHTO (American Association of State Highway and soil stiffness ratio for rectangular raft. Géotechnique 47(5):
Transportation Officials) (1996) Standard Specifications for 1055–1061.
Highway Bridges, 16th edn. AASHTO, Washington, DC. Janbu N (1963) Soil compressibility as determined by
Balasubramaniam AS, Phota-Yanuvat C, Ganeshnanthan R and oedometer and triaxial tests. Proceedings of the 3rd European
Lee KK (1981) Performance of friction piles in Bangkok Conference on Soil Mechanics and Foundation Engineering,
subsoils. Proceedings of the 10th International Conference on Wiesbaden 1: 19–26.
Soil Mechanics and Foundation Engineering, Stockholm, Kim SR, Chung SG and Dung NT (2006) Determination of true
605–610. resistance from load transfer test performed on a PHC pile.
Blessey WE (1976) Pile foundation in the Mississippi River Journal of the Korean Geotechnical Society 22(11): 113–122
deltaic plain. In Analysis and Design of Building Foundations (in Korean).
(Fang H-Y (ed.)). Envo Publishing, Lehigh Valley, PA, pp. Koerner AM and Partos A (1974) Settlement of building on pile
799–834. foundation in sand. Journal of the Soil Mechanics and
Borsetto M, Barbera G, Colleselli F et al. (1991) Settlement Foundation Division, ASCE 100(3): 265–278.
analysis of main buildings in power plants by means of 2-D Mandolini A (2003) Design of piled raft foundations: practice
and 3-D models. Proceedings of the 10th European and development. Proceedings of the 4th International
Conference on Soil Mechanics and Foundation Engineering, Seminar on Deep Foundations on Bored and Auger Piles,
Florence 1: 323–328. Ghent, 59–79.
Chow YK (1986) Analysis of vertically loaded pile groups. Mandolini A and Viggiani C (1997) Settlement of piled
International Journal for Numerical and Analytical Methods foundations. Géotechnique 47(4): 791–816.
in Geomechanics 10(1): 59–72. Mandolini A, Russo G and Viggiani C (2005) Pile foundation:
Clancy P (1993) Numerical analysis of piled raft foundation. experimental investigations, analysis and design. Proceedings
PhD thesis, University of Western Australia. of the 16th International Conference on Soil Mechanics and
DeJong J (1970) Foundation displacement of multi-storey Foundation Engineering, Osaka 1: 177–213.
structures. PhD thesis, University of Alberta, Edmonton. Mayne PW and Poulos GH (1999) Approximate displacement
DeJong J and Harris MC (1971) Settlement of two multistory influence factors for elastic shallow foundations. Journal of
buildings in Edmonton. Canadian Geotechnical Journal 8(2): Geotechnical and Geoenvironmental Engineering, ASCE
217–235. 125(6): 453–460.
Dung NT, Chung SG, Kim SR and Chung JG (2007) Meyerhof GG (1976) Bearing capacity and settlement of pile
Comparative study between design methods and pile load foundations. Journal of Geotechnical Engineering, ASCE
tests for bearing capacity of driven piles in the Nakdong 102(GT3): 195–228.
River delta. Journal of the Korean Geotechnical Society Morgan JR and Poulos HG (1968) Stability and settlement of
23(3): 61–75. deep foundations. In Soil Mechanics: Selected Topics (Lee IK
Fellenius BH (1991) Pile foundations. In Foundation (ed.)). Butterworths (London), pp. 528–609.
Engineering Handbook, 2nd edn (Fang H-Y (ed.)). Chapman & Poulos HG (1968) Analysis of the settlement of pile groups.
Hall, New York, pp. 511–536. Géotechnique 18(4): 449–471.
Fellenius BH (2004) Unified design of piled foundations with Poulos HG (1993) Settlement prediction for bored pile groups.
emphasis on settlement analysis. In Current Practice and Proceedings of the 2nd Geotechnical Seminar on Deep
Future Trends in Deep Foundations, ASCE GSP No. 125 Foundations on Bored and Auger Piles, Ghent, 103–117.
(DiMaggio JA and Hussein MH (eds)). ASCE, pp. 253–275. Poulos HG (2001) Piled raft foundations: design and
Fellenius BH (2006) Basics of Foundation Design, electronic applications. Géotechnique 51(2): 95–113.
2nd edn. http://ww.fellenius.net/papers.html (Accessed 07/ Poulos HG (2006) Pile group settlement estimation: research to
03/2010). practice. Keynote lecture. In Foundation Analysis and
FHWA (Federal Highway Administration) (2002) FHWA-IF-02- Design: Innovative Methods, GSP No. 153. ASCE, Reston, VA,
034 Geotechnical Engineering Circular No. 5: Evaluation of pp. 1–22.
Soil and Rock Properties. US Department of Transportation, Poulos HG and Davis EH (1974) Elastic Solutions for Soils and
FWHA, Washington, DC. Rock Mechanics. Wiley, New York.
Fox EN (1948) The mean elastic settlement of a uniformly Poulos HG and Davis EH (1980) Pile Foundation Analysis and
loaded area at a depth below the ground surface. Proceedings Design. Wiley, New York.
80 Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al.
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Poulos HG, Carter JP and Small JC (2002) Foundations and strain influence factors diagrams. Journal of the Geotechnical
retaining structures: research and practice. State of the art Engineering Division, ASCE 104(GT8): 1131–1135.
lecture. Proceedings of the 15th International Conference on Skempton AW (1952) Discussion, Proceedings of the 3rd
Soil Mechanics and Foundation Engineering, Istanbul 4: International Conference on Soil Mechanics and Foundation
2527–2606. Engineering, Switzerland, 3, 172.
Randolph MF (1994) Design methods for pile group and piles Tejchman A, Gwizdala K and Dyka I (2001) Analysis of
rafts. Proceedings of the 13th International Conference on settlements of piled foundations. Proceedings of the 15th
Soil Mechanics and Foundation Engineering, New Delhi, International Conference on Soil Mechanics and Foundation
61–82. Engineering, Istanbul 2: 1025–1030.
Randolph MF and Wroth CP (1979) An analysis of the vertical Terzaghi K and Peck RB (1967) Soil Mechanics and Foundation
deformation of pile groups. Géotechnique 29(4): 423–439. Engineering Practice. Wiley, New York.
Resendiz D and Auvinet G (1973) Analysis of pile foundations Tomlinson MJ (1986) Foundation Design and Construction, 5th
in consolidating soil. Proceedings of the 8th International edn. Longman Scientific and Technical, Harlow.
Conference on Soil Mechanics and Foundation Engineering, Vesic AS (1977) Design of Pile Foundations. National
Moscow 3: 211–218. Cooperative Highway Research Program Synthesis of
Schmertmann JH, Hartman JP and Brown PR (1978) Improved Practice No. 42. Transport Research Board, Washington, DC.
Geotechnical Engineering 163 Issue GE2 Settlement of piled foundations using equivalent raft approach Dung et al. 81
Downloaded by [ Purdue Univ Lib TSS] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.