You are on page 1of 2

UNIVERSITI KUALA LUMPUR

MALAYSIAN INSTITUTE OF
CHEMICAL & BIOENGINEERING
TECHNOLOGY

DIPLOMA IN CHEMICAL ENGINEERING TECHNOLOGY

TEST 2
JANUARY SEMESTER 2020
( SET 1 )

COURSE CODE : CPD 20302

COURSE TITLE : PROCESS CONTROL

TIME / DURATION : 1 HOUR

INSTRUCTIONS TO CANDIDATES

1. Please read the instruction given CAREFULLY.

2. Answers ALL questions in this question booklet.

Name: MOHD KHAIRUL FATHY BIN M.ASRAR


ID: 55102118037

THIS QUESTION BOOKLET CONSISTS OF 2 PRINTED PAGES INCLUDING THIS PAGE.

ATTENTION: DO NOT OPEN THIS BOOKLET UNTIL PERMISSION IS GIVEN TO DO SO.


CONFIDENTIAL CPD 20302

TOTAL MARKS: 20

1.
a.) State TWO (2) classifications of general Process Control method/approach.

-manual control
-automatic control
( 2 Marks )

b.). Based from your answer in (i.), describe briefly for each answer.

- manual control: process is controlled by the process operator and the process conditions
and controls is adjusted directly.

- automatic control: process is controlled through continuous controller (P,PI,PID) to


control the measurements and conditions of the process.
( 4 Marks )

2.
a.). State ALL methods under Control Strategy

- on-off system, feedback system, feedforward system, ratio control system, cascade
control system, inferential control system, selective/override control system, adaptive
control system.
( 8 Marks )

b.). Based from your answer in (a.), explain briefly THREE (3) methods.
( 6 Marks )
- feedback system: closed loop control system. Feedback are used to make decisions on
changes to the control signal that runs the plant.

- Feedforward system: open loop control system. Measures the important disturbance
in advance and take action before the process is disturbed.

- Ratio control system: maintain the ratio of two PV at a specified value. Disturbance
variable and manipulated variable. Formula: R= u/d.