This was designed on plant controllers (MNB 1000). We have commissioned and tested
successfully.
Additional Scope
After successful implementation and execution of initial scope, client placed new demand
which included the automation of Entire Plant Room which added
To implement new scope, we have added more plant controllers (MNB 1000) and an
Automation server.
Configuration of universal communication protocol (UCP) card of each Chiller with their
respective baud rate and unique network ID.
The carrier team has given us ON/OFF authority. We have hooked up all chillers through
BacNet MSTP of Automation server
Initially the programming script was written in Automation server according to designed
sequence of operations and binded with respect to BacNet values
Problems Encountered
The problems encountered during the implementation and execution stage are:
Date: 2nd August, 2018
Team Members:
1. Kashif Hussain
2. Kashif Ali
3. Zohair Hussain
4. Pervez Karim
5. Talha Sheikh
6. Faisal Dawood
7. Usman Iqbal
Date: 2nd August, 2018