Professional Documents
Culture Documents
Damascus, Syria
(WALL CLADDING)
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 1 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
PART 1 – GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 DEFINITIONS
A. For the purpose of this Specification the definitions given by the British Standards,
as appropriate, shall apply.
B. Related work
1. Carefully examine all of the Contract Documents for requirements, which affect the
work of this section.
2. Where materials used in this section (e.g. concrete and reinforcement) have been
specified elsewhere in this specification document, the relevant clauses shall apply
to this section.
C. Silence of Specification
1. The apparent silence of the Specification, Drawings or other Contract Documents
as to any or the omission from them of a detailed description concerning any point,
shall be regarded as meaning that only the best general practice is to be used.
2. Materials that have not been individually specified, shall as a minimum standard, be
in accordance with the relevant British standard where applicable.
1.4 SUBMITTALS
A. Shop Drawings
1. The Contractor shall produce large scale shop drawings reflecting fabrication
and installation of all wall cladding work to include plans and details showing exact
size, shape, profile, curvature, jointing, finish and the installation method and
submit to the Consultant for comments.
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 2 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
B. Product Data
1. Submit manufacturer's product data, installation instructions, use limitations
and recommendations. Provide certifications stating that materials comply with
requirements.
C. Samples
1. Submit representative samples of each element that is to be used in the finished work,
showing the full range of colour and finish variations expected. Provide at least four (4)
un-mounted units to locations agreed with the Consultant for comment.
2. Provide wrapped, packaged and labeled extra material consisting of three (3) pieces of
each type, size and configuration of kerb and paving materials used on the project.
Deliver to the location designated by the Consultant.
3. The samples provided must also meet the technical aspects of the specification.
4. Any materials which do not comply with the specification, are not approved or are not to
the satisfaction of the Consultant may be rejected and the Contractor shall replace them
at his own cost, with acceptable items.
D. Closeout Submittals
1. The Contractor shall maintain one set of Contract Drawings for the sole purpose of
recording “As-Built” conditions of the wall cladding works as a whole. All changes,
previously approved, and all completed work shall be recorded on these drawings.
2. The As-Built drawings shall be supplied to the Consultant for approval prior to the issue of
the Completion Certificate.
3. On approval of the as-built drawings the Contractor shall forward the following for the
Consultants retention:
(i)Three complete sets of As-Built drawings properly folded and provided in the plastic
folders as part of the Operations and Maintenance Manuals.
C. Qualified Installer
1. The Installer shall be trained and licensed by the supplier or manufacturer in the use the
materials and equipment to be used in the work
D. Mock-ups
1. Before beginning primary work of this section, provide mock-ups of representative
installations at locations acceptable to Consultant and obtain Consultant's approval.
2. Protect and maintain acceptable mock-ups throughout the work of this section to serve as
criteria for acceptance of this work.
3. Mock ups are to be constructed as standalone project samples and should not be
included as part of the finished work. For walls, fences and balustrades a minimum
section of 2.0m shall be constructed or if the wall, fence or balustrade is in bays a
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 3 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
E. Source
1. All materials shall be the product of one supplier as specified and shall comply with the
relevant British Standards.
2. Contractor to submit for Consultants review and comments, information on the supplier of
all materials furnishing used on the project.
A. Weather
1. Perform work only when existing and forecasted weather conditions are within the limits
established by International Masonry All-Weather Council Guide Specification and
the mortar admixture manufacturer.
C. Substrates
1. Proceed with work only when substrate construction work is complete.
D. Site Investigation/Dimensions
1. The Contractor shall be responsible for ensuring all horizontal site dimensions and levels
are taken and recorded on shop drawings before starting fabrication of any ‘special’ stone
material.
1.8 WARRANTY
1.9 MAINTENANCE
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 4 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
actual materials used in the work, including stone, paving materials, sealants and other
major components.
3. Assemble manuals for component parts into single binders and CD’s for each system.
PART 2 – PRODUCTS
2.1 MANUFACTURERS/SUPPLIERS
A. Stone cladding
2.2 MATERIALS
A. General
1. Where materials used in this section have been specified elsewhere in this
document, the relevant clauses shall apply to this section. Materials that have not
been individually specified shall be of first class quality and the minimum standard
acceptable shall be the relevant British Standard where applicable.
B. Stone Tests
1. Historic test data shall be provided upon request. The contractor may hire and
pay an independent testing laboratory to perform tests that will be typical of the
stone specified for the project.
2. All stone supplied shall meet or exceeds the standard ASTM specifications.
C. Finish
1. Finish shall be within the range of samples approved by the Consultant. The
surfaces shall be out of wind, straight and true in all directions.
D. Facing Thickness
1. Stone shall be to the thicknesses as shown on contract drawings.
E. Anchor Provision
1. All stone panels shall be adequately anchored in combination with mortar and
adhesives.
G. Site Storage
The stone shall be stacked on timber or platforms at a minimum of 3” above
ground upon receipt at the building site or storage yard. Care should be taken to
prevent staining during storage. If the stone will be stored for a lengthy period,
then polyethylene or other suitable plastic should be placed between anything
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 5 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
H. Coping Stones
1. Type/Colour: Natural Stone – Colour: to Architect Approval
2. Finish: Honed
3. Size(s): 30mm thick x 250mm wide, with full bullnose to outer edges/both edges
as articulated in drawings
4. Fixing: e mbe dd ed wit h 20 mm ce men t mo rt a r
5. Special requirements: None
I. Copping Stone:
1. Type/Colour: Natural Stone – Colour: to Architect Approval
2. Finish: Sand Blasted
3. Size(s): 50mm thick X350mm Wide with 10mm to full bullnose outer edges
4. Fixing: e mbe dd ed wit h 30 mm ce men t mo rt a r .
5. Special requirements: None
J. Stone Cladding:
1. Type/Colour: Natural Stone – Colour: to Architect Approval
2. Finish: Roughed
3. Size(s): 50-70mm thick Random cutting
4. Fixing: e mbe dd ed by 50 mm ce me nt mo rta r en fo rce d b y 6 mm st ee l
me sh . Joints to be pointed with grouting mortar, colour a n d f a s h i o n to
Architect Approval
5. Special requirements: None
K. Stone Cladding:
1. Type/Colour: Natural Stone – Colour: to Architect Approval
2. Finish: Roughed
3. Size(s): 20mm thick
4. Fixing: emb ed de d b y 2 0 mmth ick ce me n t mo rta r . Joints to be 3mm +/-
1mm and pointed with grouting mortar, colour to match cladding. All To
Engineer’s detail and approval
5. Special requirements: None
L. Step units
Treads:
1. Type/Colour: Natural local stone – Colour: beige
2. Finish: honed.
3. Size(s): 30mm thick x 300 x 1800mm
4. Construction: Laid to cement mortar bed
5. Special requirements: 5X5 chamfered tread nosing with anti slip strips as
indicated in drawings
Risers:
1. Type/Colour: Natural local stone – Colour: beige
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 6 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
2. Finish: honed.
3. Size(s): 20mm thick x 120 x 1800mm
4. Construction: adhered to cement mortar bed .
5. Special requirements: provide groove at the top of tread as shown in drawings
Landings:
1. Type/Colour: Natural local stone – Colour: beige
2. Finish: honed.
3. Size(s): 30mm thick x as indicated in drawings
4. Construction: Laid on cement mortar bed .
5. Special requirements: . Joints to be 3mm +/- 1mm and pointed with grouting
mortar, colour to match paving.
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 7 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
PART 3 – EXECUTION
3.1 EXAMINATION
A. Verification of conditions
1. Examine areas to receive the work and the conditions under which the work would
be performed.
2. Identify conditions detrimental to the proper and timely completion of the work.
3. Do not proceed until unsatisfactory conditions have been corrected.
B. Base surfaces
1. Examine surfaces to receive paving materials specified under this section, and
conditions under which they will be installed, with installer present, for compliance
with requirements for installation tolerances and other conditions affecting
performance of the work.
2. Do not proceed with installation until unsatisfactory conditions have been corrected.
3. The installer shall be fully responsible for accepting the condition of such surfaces
prior to initiation of work.
4. Ensure that surfaces to receive paving materials are firm, dry, clean, and free of oily
or greasy films, mortar, soil, and other foreign substances.
3.2 PREPARATION
A. Fabrication
1. Accurately cut all material to shape and dimension in strict accordance with
approved shop drawings.
2. Jointed surfaces shall be cut full and square from the face.
3. All exposed surfaces to be true and out of wind, with edges in a continuous straight
line with adjoining edges.
4. Fabrication tolerances shall be in accordance with reference standards clause 1.2 .
B. General Preparation
1. Clean sub-base to remove dirt, dust, debris and loose particles.
2. Do not use damaged, chipped or defective stone pieces. Cut stone with power saw
to provide clean-cut edges; form patterns indicated.
3. Use full, uncut units to the greatest extent possible.
4. Beginning work means installer accepts substrates and conditions.
3.3 INSTALLATION
A. General
1. Strictly comply with suppliers and manufacturer's instructions and
recommendations, except where more restrictive requirements are specified in this
section.
B. Mortar bedding
1. Install stones in full mortar backing conforming to the requirements below.
(i) Mix and prepare mortar in compliance with mortar/ grout manufacturer's instructions
and recommendations.
(ii) Saturate concrete sub-base with clean water several hours before placing setting
bed.
(iii) Spread and screed setting bed to a uniform thickness required for accurate setting of
stone to achieve a uniform surface. Mix and place only that amount that can be
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 8 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
covered with stone prior to initial set. Cut back, level edge, and remove and discard
mortar that has reached initial set prior to placing stone.
(iv) Wet stones thoroughly before setting. Set stone in pattern approved by the
Consultant. Provide 5mm (coping) and 3mm for feature wall slips dry joints between
stones. Set stones before initial set of mortar bed occurs. Do not set stone on dry
bed. Apply uniform 1.6mm thick slurry bond coat to bed or back of stone with a flat
trowel just prior to placing stones on green or wet setting bed.
(v) Set stones into place with heavy rubber mallet to obtain full contact and adhesion
with setting bed. Do not disturb stones after setting. Remove and relay stones that
must be adjusted. Wall to have appearance of dry stone wall. No mortar to be visible
on front face of wall.
(vi) Expansion and Control Joints: Provide 9.5mm wide sealant filled joints in compliance
with relevant Specification section. Provide sealant filled expansion joints over all
cracks and joints in concrete sub slabs and over all changes in backing materials.
(vii) Prevent disturbance of stone wall during setting or within 24 hours after initial setting
of stones.
B. Maintenance
1. After removal of protective coverings, clean and maintain all stainless steel surfaces
at regular intervals until Practical Completion.
2. All maintenance is to be in accordance with procedures detailed by the wall
cladding supplier’s technical literature and the guarantee.
3. At practical completion, maintenance details must be passed on to the
Consultant to enable the Employer to set up a maintenance contract.
4. Maintenance records should be kept until the end of the guarantee period.
3.5 CLEANING
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 9 of 10
(2b+G+7) 8th Gate Financial District Buildings FD1&FD2
Damascus, Syria
3.6 PROTECTION
B. Sealant
1. Wall surfaces shall be treated with two coats of premium, no-sheen, natural look,
water based penetrating sealer/impregnator, applied in accordance with the
manufacturers printed instructions
DIVISION 02 – LANDSCAPE
SECTION 02 83 00 - Wall cladding Page 10 of 10