Professional Documents
Culture Documents
the cement slurry. Bottomhole circulating software to evaluate and optimize the densities of all
temperature (BHCT) was estimated to be 0°C. components to be pumped during the cement job. Every
• Presence of weak zones with formation fracture attempt was made to keep the cement densities as high as
gradient as low as 16.4 KPa/m from 550 – 700 m possible, thus positively contributing to the development of
depth, thus presenting a potential for lost circulation compressive strength but because of the presence of weak
during drilling and cementing operations. formations with low fracture gradients it was decided to pump
• Presence of active aquifers in the interval from 600 – the spacer and slurries respectively with the following
800 m. densities:
• Gas migration potential during the initial setting of • Weighted spacer specially designed to go easily into
the cement slurry for the production casing. turbulent flow (WSTF), mixed at 1350 kg/m.3 The
WSTF may be used in aqueous or non-aqueous
All above factors work synergistically together and they fluids.
are producing a complex environment for performing • 245-mm casing: 1470 kg/m3 for the lead and 1890
cementing operations; therefore, to help develop a properly kg/m3 for the tail slurry.
engineered job design, several meetings among involved • 168 mm casing: 1470 kg/m3 for the lead and 1800
parties were conducted well ahead of time with the aim to kg/m3 for the tail slurry.
address challenges, working parameters, and necessary
requirements for achieving the ultimate goal of long-lasting While the engineering team was working on job modeling
wellbore isolation. This investigative approach was of utmost and finalizing the work requirements, the laboratory team was
significance; especially since the service company personnel preparing for testing slurries at low temperatures. In that
had limited expertise of the work area and associated respect, one high-pressure, high-temperature (HPHT)
downhole conditions. consistometer was retrofitted with a cooling unit, thus
Slurry design is affected by many factors, including brand allowing testing at –5°C. At the same time, the atmospheric
and kind of cement, well depth, temperature, drilling fluid consistometer was modified and a refrigerator was installed in
parameters, desired pumping time, slurry density, fluid-loss the lab to allow the cubes to be tested after they had been
control, and strength development. An attempt was made to resting in a cool environment. All materials and additives were
develop a cementing system that could be used for both casing tested and QA/QC evaluated when received.
strings with minimal modifications thus standardizing the Russian-made PST-1-50 (comparable to API Class “C”)
delivery process while minimizing the impact caused by high, early-strength cement for low-temperature applications
logistics involved with working in a remote area. was the product of choice for engineering and designing all
While preliminarily developing the cement blend a special slurries.
emphasis was made on using a combination of additives that After extensive testing was performed we were able to
would act synergistically together to produce slurries that obtain slurries for the 245-mm casing designed with as little as
would adequately respond to the many challenges already 10% gypsum by weight of cement (BWOC) in lead slurries
present in these wells, while keeping the procedure as simple and respectively with only 1% gypsum (BWOC) mixed in the
as possible because of the adverse Arctic working conditions. tail cement.
After analyzing the actual design of the cements used it To compensate for the reduced amount of gypsum it was
was observed that most all slurries contained a fairly high proposed and agreed to use sodium chloride (NaCl) up to 10%
percentage of a gypsum cement blend (40% BWOC) which by weight of water (BWOW) in the mixing water. The idea
was used primarily to decrease the thickening time, increase behind this addition was to reduce the freezing point of the
viscosity and initiate early strength development. Although it slurry and water (Fig. 2) while at the same time accelerating
is a logical additive of choice to be used in permafrost the setting of cement and increasing its final strength. This
conditions to help deal with the low temperature issue, we approach imposed somewhat a logistical challenge since large
agreed in our discussions with the technical institute to deviate volumes of sodium chloride would require pre-mixing in the
slightly from this rule and to use a significantly lower amount mixing water tank. This difficulty was communicated to the
of gypsum in the design of the lead slurries coming in contact customer and it was ultimately resolved by the drilling
with the permafrost zones. contractor who supplied a centrifugal pump, thus allowing the
In our discussions we were of the opinion that a high recirculation of the mixing water in the water tank until the
content of gypsum could potentially cause the set cement to be sodium chloride was completely dissolved. This operation was
brittle; therefore, making it prone to cracking due to a lack of undertaken a few hours before the cementing operation and
flexibility once the wells are put into production and are was performed by the drilling and cementing crews working
exposed to various pressure and temperature cycles. We together thus minimizing the need to wait a long time before
wanted also to eliminate the eventual potential of gypsum starting the cementing operation itself.
dissolution from the cement composition over time during the Large washouts were expected, especially throughout the
producing cycle of the well which can be caused as a result of permafrost zone (during the cementing of the 245-mm casing
the presence of subsurface active acquifers located below the in particular). To provide efficient mud displacement, the
permafrost zone. proposed spacer system was designed to achieve a 500-m
Once the direction to proceed with the slurry design was separation between mud and the cement. This was achieved
agreed, simulation modeling was conducted using proprietary by pumping 6.4 m3 of water containing a water-wetting
SPE100816 3
surfactant and followed by 4.77 m3 of weighted WSTF mixed overall drilling operation took less time to reach the final
at 1350 kg/m3. To prevent the freezing of water as well as to casing point the noticed volume of returned cement to surface
simplify the logistics sodium chloride (10% BWOW) was also was significantly greater.
added in the mixing water and was therefore part of the WSTF Pipe centralization was also given due attention and as a
system itself. result a pipe standoff of 70% was recommended and
To obtain a lead slurry with relatively low densities for the implemented in the field. A combination of bowspring and
245-mm casing strings the combination of Gilsonite and rigid centralizers for production casings was used to achieve
Bentonite was used. The main purpose of using such a recipe the desired pipe standoff, thus resulting in a more equal
was to alleviate the anticipated problem associated with distribution of forces exerted by the cement slurry as it flowed
potential lost circulation while producing a slurry with a low up the annulus while minimizing the potential of the slurry
density at the same time. Gilsonite, being an asphaltite, is a following the path of least resistance.
hydrocarbon in a granular form with its particle sizes ranging On a model well 550 m deep, the distribution of
from 4 to 100-mesh. It not only lowers the slurry weight, but centralizers for the 245-mm casing and their respective
also acts as an effective bridging agent that helps fight placement can be summarized as given in Table 2.
potential lost circulation. Bentonite, on the other hand, was Subsequently on a model well 1465 m deep, the
added to the slurry as an extender and for the purpose of distribution of centralizers for the 168 mm production casing
increasing slurry viscosity, thus reducing free water, helping and their respective placement can be summarized as given in
prevent settling of cement and separation of the Gilsonite in Table 3.
the slurry. Because boreholes were greatly enlarged (especially for
Slurries for the 168-mm production casing were based on the 245-mm casings) and since turbulent flow could not be
the same designing concept as the slurries developed for the achieved, it was recommended to pump the displacement at
245-mm casing strings but with the addition of specialty low rates thus keeping the movement of fluids in the annulus
additives required whenever designing blends for production in the plug-flowing regime. Once there was pressure
casings. Since determined temperatures were BHST = 27°C indication after the top plug was caught the displacement rate
and respectively BHCT = 22°C the amount of gypsum in the was lowered to 0.7 – 0.5 m3/min. We were convinced that this
lead slurry was further reduced to only 8% (BWOC). To pumping approach would provide a better and more consistant
enhance initial strength development and develop gel strength, removal of gelled mud from a greatly enlarged annulus.
a thixotropic additive was included in both the lead and tail Production casing strings were displaced at maximum rates
slurries. Slurries were designed at 1470 kg/m3 for the lead and of 1.1-1.2 m3/min because there was a pressure limitation to be
1800 kg/m3 for the tail. Added to the tail slurry design also considered to avoid breaking down the weak formations
were dispersing, fluid-loss and gas-migration additives, thus situated between 550 and 700 m. Figs. 3 and 4 are charts of
producing a low fluid-loss slurry of 58cc/30 min and reaching actual jobs performed on 245- and 168-mm casings
compressive strength values of 8.5 MPa in 24 hours and 13.2 respectively.
MPa in 48 hours. Since the production 168-mm casings were
deviated, all slurries designed were tested for free water under Conclusions
a 45° angle and had to pass the mark of having zero free water • Ten 245-mm conductor and ten 168-mm production
after 2 hours. casing strings were successfully cemented during the
During the testing phase of all slurries, API standardized evaluation campaign that took place in late 2004 in
procedures2 and recommendations developed for the testing of Zapolyarnoe gas condensate field (Russian Arctic).
cement through permafrost layers were followed as closely as • All 10 wells were successfully brought to production
possible and within laboratory logistical possibilities. Cement and for the evolved time period have not
and additives were refrigerated overnight before testing and demonstrated crossflows nor have they required
ice-cold water was used in the preparation of samples. workover operations thus proving that the formations
Conditioning of samples was performed in the atmospheric isolation is adequate.
consistometer that was located outside the laboratory building • Pre-planning and extensive dialogue with all involved
thus exposing it to the simulation of cold environment. parties (Technical Institute, customer and service
Selected cementing compositions were pumped for 1.5 hours provider) was of utmost importance in having this
on an atmospheric consistometer before pouring into cube project kicked off in the right direction; especially
molds for curing. Poured samples were kept in the refrigerator since this was a new work area for the service
and were ultimately tested for compressive strength provider with limited past job data.
development at 4°C within 24 and 48 hours, respectively. For • Extensive laboratory work was performed in
lack of appropriate temperature control the API-recommended obtaining the desired cement slurries parameters and
testing at –7°C was omitted. characteristics. API Standarization Committee
Since traditionally no caliper logs are available in the area recommendations were implemented while testing the
the recommended slurry volume excesses were based slurries. This required laboratory equipment
predominantly on past area experience. In accordance and in modifications and adaptations for testing in cold
conjunction with the Technical Institute it was decided to plan environments.
the jobs with excess volumes as given in Table 1. • The amount of gypsum loadings in various cement
Returns of cement to surface were observed and generally compositions (BWOC) was significantly reduced
varied between 3 and 7 m3. Noteworthy is that every time the
4 SPE 100816
(from 40 % initially down to 10 % and 8 % On the production 168-mm strings, potential losses
respectively) thus producing a more ductile cement were prevented by simulating the jobs ahead of time
capable of better withstanding the production and lowering the displacement rates to stay below
pressure and temperature cycles. formation fracture pressures.
• Despite a lower amount of gypsum used, the
acceleration of slurries was achieved by using 10% References
sodium chloride (BWOW) for mixing water. This 1. Blount, E.M. and Prueger, N.J.: “The Development of a Well
also helped reduce the freezing point of water and Completion System for Deep Permafrost” paper SPE 3251
prevent the freezing of the slurry while settling. presented at the SPE Southwest Alaska Section Regional
Meeting, 5-7 May, 1971.
Although managing large quantities of NaCl in the
2. “Cement Blends can be tested for Arctic Environments,”
field was not the easiest task, a centrifugal pump was Petroleum Engineer, (February, 1977) 22.
used to help dissolve the salt in the mixing water.
• A combination of Gilsonite and Bentonite was used
to produce a low-density lead slurry while at the same
time preventing potential losses into the weak zones.