GOVERNMENT OF NEPAL

MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU-TERAI MADESH FAST TRACK(EXPRESSWAY) ROAD PROJECT
Contract No:KTFT/NCB/WORKS/2074/2075-4
Chainage: 19+435 - 20+080 Km

Name of Project :Kathmandu-Terai/Madhesh Fast Track( Expressway) Road Project Submission Date: 2075-03-17
Contract No: KTFT/NCB/WORKS/2074/2075-4 Period from: 2074-11-10 to 2075-03-15
Contrtactor : Gajurmukhi-Motidan J.V. Employer/Consultant: Nepali Army

Interim Payment Cerificate No. 01

Quantity Summary Sheet

Unit: Ls
Item No. Insurance of the works, plants and materials also including other property, personal injury or death of contractor employee,
A1.01 employer's employee and other people.

S.No. Description From To Quantity Remarks

1 #REF! 1.00

Total Quantity Upto date IPC 1.00

Quantity Payment upto Previous IPC 0.00

Total Quantity in this IPC 1.00

Provisional Payment for this IPC (100 % of Total quantity of this IPC) 1.00

…………………………… ……………………………. ………………………………..


Submitted by Checked by Verified by
Contractor Representative
GOVERNMENT OF NEPAL
MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU - TERAI MADESH FAST TRACK(EXPRESSWAY) ROAD PROJECT
Contract No: KTFT/NCB/WORKS/2075/2076-05
21+120 to 21+180
Summary Sheet

Chainage
SN. Description of Works Unit Quantity Remarks
From To
1 Earth works 21+120 21+180 m3 5,682.35
2 Gabion works m3 412.00
3 Geotextile Sqm 240.00
4 Backfill behind Gabion wall m3 153.00

Submitted By: Checked By: Verified By:


Name of Project :Kathmandu-Terai/Madhesh Fast Track( Expressway) Road Project
Contract No:KTFT/NCB/WORKS/2075/2076-5
Contrtactor :Apex Bkoi J.V. Employer/Consultant: Nepal Army
Quantity Calculation Sheet

Description of work: S.N. (A),Earthwork in excavation including setting out, removal of tree roots and stumps, clearance of site along the aligment, disposal/stock piling of extra
material lead upto 1 Km lead all complete as per DOR specification (905)
Classificiation Quantity Remarks
Cut Area Total
Chainage Length (m) Average Area(m2)
(m2) Volume(m3) SR BMS HR SR BMS HR

21+120.00 10.00 660.87 0 0 95.00% 5.00%


21+130.00 10.00 184.04 422.46 4224.55 95.00% 5.00% 4013.32 211.23 0.00
21+140.00 10.00 18.55 101.29 1012.95 95.00% 5.00% 962.30 50.65 0.00
21+150.00 10.00 13.68 16.11 161.14 95.00% 5.00% 153.08 8.06 0.00
21+160.00 10.00 7.28 10.48 104.78 95.00% 5.00% 99.54 5.24 0.00
21+170.00 10.00 7.46 7.37 73.70 95.00% 5.00% 70.01 3.68 0.00
21+180.00 10.00 13.59 10.53 105.25 95.00% 5.00% 99.99 5.26 0.00
Sub Total Quantity from Chainage 21+130 to 21+180 5,682.35 5,398.23 284.12 -

........................... ............................. ..............................


GOVERNMENT OF NEPAL
MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU - TERAI MADESH FAST TRACK(EXPRESSWAY) ROAD PROJECT
Contract No: KTFT/NCB/WORKS/2075/2076-05
21+120 to 21+180
Measurement Sheet of Gabion

Chainage Length Breadth Height Quantity


S.N. Description No. Location (m) (m) Remarks
From To (m) (Cum)

1 Gabion Ret. Wall 21+120.00 21+180.00 RHS Drg. No.-01

60.00 1.00 1.50 1.00 90.00


Bottom layer
18.00 3.00 1.00 1.00 54.00

3.00 2.00 1.00 1.00 6.00

59.00 1.00 2.00 1.00 118.00


1st Layer
60.00 1.00 1.50 1.00 90.00
2nd Layer
18.00 3.00 1.00 1.00 54.00
Top layer
3.00 2.00 1.00 1.00 6.00

Sub - Total 412.00

Submitted By: Checked By: Verified By:


GOVERNMENT OF NEPAL
MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU - TERAI MADESH FAST TRACK(EXPRESSWAY) ROAD PROJECT
Contract No: KTFT/NCB/WORKS/2075/2076-05
21+120 to 21+180
Measurement Sheet of Gabion

S. Chainage Breadth/
Description Nos. Length (m) Area (m2) Quantity (sqm) Remarks
No. From To Height (m)
Drg. No.-
1 Gabion Ret. Wall 21+120 21+180
01
60.00 4.00 240.00 240.00

Sub - Total 240.00

Submitted By: Checked By: Verified By:


Name of Project :Kathmandu-Terai/Madhesh Fast Track( Expressway) Road Project
Contract No:KTFT/NCB/WORKS/2075/2076-5
Contrtactor :Apex Bkoi J.V.
Quantity Calculation Sheet
Backfill Material

Remarks
Cut Area Total
Chainage Length (m) Average Area(m2)
(m2) Volume(m3)

21+120.00 10.00 2.55 0


21+130.00 10.00 2.55 2.55 25.50
21+140.00 10.00 2.55 2.55 25.50
21+150.00 10.00 2.55 2.55 25.50
21+160.00 10.00 2.55 2.55 25.50
21+170.00 10.00 2.55 2.55 25.50
21+180.00 10.00 2.55 2.55 25.50
Sub Total Quantity from Chainage 21+130 to 21+180 153.00