KATHMANDU-TERAI MADESH FAST TRACK(EXPRESSWAY) ROAD PROJECT
Contract No:KTFT/NCB/WORKS/2074/2075-4
Chainage: 19+435 - 20+080 Km
Name of Project :Kathmandu-Terai/Madhesh Fast Track( Expressway) Road Project Submission Date: 2075-03-17
Contract No: KTFT/NCB/WORKS/2074/2075-4 Period from: 2074-11-10 to 2075-03-15
Contrtactor : Gajurmukhi-Motidan J.V. Employer/Consultant: Nepali Army
Unit: Ls
Item No. Insurance of the works, plants and materials also including other property, personal injury or death of contractor employee,
A1.01 employer's employee and other people.
1 #REF! 1.00
Provisional Payment for this IPC (100 % of Total quantity of this IPC) 1.00
Chainage
SN. Description of Works Unit Quantity Remarks
From To
1 Earth works 21+120 21+180 m3 5,682.35
2 Gabion works m3 412.00
3 Geotextile Sqm 240.00
4 Backfill behind Gabion wall m3 153.00
Description of work: S.N. (A),Earthwork in excavation including setting out, removal of tree roots and stumps, clearance of site along the aligment, disposal/stock piling of extra
material lead upto 1 Km lead all complete as per DOR specification (905)
Classificiation Quantity Remarks
Cut Area Total
Chainage Length (m) Average Area(m2)
(m2) Volume(m3) SR BMS HR SR BMS HR
S. Chainage Breadth/
Description Nos. Length (m) Area (m2) Quantity (sqm) Remarks
No. From To Height (m)
Drg. No.-
1 Gabion Ret. Wall 21+120 21+180
01
60.00 4.00 240.00 240.00
Remarks
Cut Area Total
Chainage Length (m) Average Area(m2)
(m2) Volume(m3)