To Date ………………….
The Project Chief,
Office of Project Chief,
Kathmandu-Terai/Madhesh Fast Track (Express Way) Road Project (KTFT)
Nepal Army Headquarter, Bhadrakali
Dear Sir,
As per contract agreement dated 17 Jan, 2019(2075/10/03), it is mentioned that completion of
total work within 2076/02/15 and the revised completion date for the whole work is 2076/08/08. Due to
various hindrances beyond our control we could not complete of the total works within given completion
date and request you to provide extension of time for 365 days. The major Causes of delay in project are
briefly as follow:
1. We haven’t got site clear till date for the package KTFT/NCB/WORKS/2075/2076- 04 (19+440 to
20+080) to initiate the work.
3. Due to change in centerline of the road re-design of RE wall takes time which delays the project.
4. Due to change in design of RE Wall time to time we cannot rely on one design to start the construction
work which delays the project.
GAJURMUKHI/MAHALAXMI/FEWA JV
Head Office :Samakhushi, Kathmandu Tel: 01-43625715Email:sakcham.nirman@gmail.com
Hence, we request you kindly to grand extension of time as per our aforementioned valid and genuine
delay causing event. Co operations are required please instruct us. Please find below mentioned
documents attached with this letter.
Sincerely Your’s
………………………….
Contractor’s Representative
Gajurmukhi – Mahalaxmi-Fewa J/V