GAJURMUKHI/MAHALAXMI/FEWA JV

Head Office :Samakhushi, Kathmandu Tel: 01-­­43625715Email:sakcham.nirman@gmail.com

To Date ………………….
The Project Chief,
Office of Project Chief,
Kathmandu-Terai/Madhesh Fast Track (Express Way) Road Project (KTFT)
Nepal Army Headquarter, Bhadrakali

Sub: Request for EOT (Extension of Time) accordingly.


Contract No: KTFT/NCB/WORKS/2075/2076-04

Dear Sir,
As per contract agreement dated 17 Jan, 2019(2075/10/03), it is mentioned that completion of
total work within 2076/02/15 and the revised completion date for the whole work is 2076/08/08. Due to
various hindrances beyond our control we could not complete of the total works within given completion
date and request you to provide extension of time for 365 days. The major Causes of delay in project are
briefly as follow:

1. We haven’t got site clear till date for the package KTFT/NCB/WORKS/2075/2076- 04 (19+440 to
20+080) to initiate the work.

2. Earthwork cutting of Gajurmukhi-Motidan J/V package no( KTFT/NCB/WORKS/074/075-4) chainage:


19+435 to 20+190 is running, In the same chainage new package no 4 KTFT/NCB/WORKS/075/076 -4
Chainage: 19+440 to 20+080 is awarded to Gajurmukhi Mahalaxmi Fewa J/V. To commence new RE
wall package 4 work, earlier package KTFT/NCB/WORKS/074/075-4 (Gajurmukhi Motidan J/V) must
completed excavation work as well as muck clearance work to start the construction work.

3. Due to change in centerline of the road re-design of RE wall takes time which delays the project.

4. Due to change in design of RE Wall time to time we cannot rely on one design to start the construction
work which delays the project.
GAJURMUKHI/MAHALAXMI/FEWA JV
Head Office :Samakhushi, Kathmandu Tel: 01-­­43625715Email:sakcham.nirman@gmail.com

5. Variation In Tendered and Designed Quantity


There was difference between designed and boq quantity. The first submission of proposed design to
KTFT design section was on the date 2076/4/16 and the second submission was on date 2076/4/26.
The design is still in review process.

Hence, we request you kindly to grand extension of time as per our aforementioned valid and genuine
delay causing event. Co operations are required please instruct us. Please find below mentioned
documents attached with this letter.

1. Letter of site unavailable


2. New centerline

Sincerely Your’s

………………………….
Contractor’s Representative
Gajurmukhi – Mahalaxmi-Fewa J/V