Process Engineering Deliverables

· Process Flow Diagrams (PFD), Process Flow Scheme (PFS)

· Piping & Instrument Diagrams (P&ID)

· Line List

· Equipment List

· Process Design Calculations

· Process & Operational Control Description

· Process Data Sheets for Instrumentation

· Process Data Sheets for main Equipment

· Performance Test Procedure

Static Equipment Department- Mechanical

· Mechanical Data Sheet (MDS)

· Equipment Installation Plan

· Equipment fabrication Drawing

· Vendor Drawing for Review

Rotating and Package Equipment Department

· Mechanical Data Sheet (MDS)

· Equipment Specification List

· Vendor Drawing with Detail

· Deliverables from Instrumentation Department

· Instrument Data Sheet

· Instrument Hook-up
· System Block Diagrams

· Control Room and Control Building Layouts

· Instrument Location Drawings

· Instrument Cable Routing

· Instrument Power and Utility Requirements

· Instrument Index

· Relief and Safety Device Index

· Alarm and Trip Schedule

· Data Transfer Cable Tray Layouts

· Air Distribution Diagram

· Instrument Junction Boxes and Panels Block Diagrams

Electrical Department

· Grounding layouts

· Cable Tray Route Layouts

· Plant and Buildings Lighting Layouts

· Substation Sizing and Layout

· Wiring Drawings and Terminal Connections

· Electrical Equipment and Component Data Sheet

· Heat Tracing Panel Schedules

· Load List

· Tray Sizing

· Emergency Power Load Specification

HVAC Department

· Air Handling Unit (AHU) Layout


· Duct Layout

· Cooling/Chilled Water Piping Layout

Civil and Structural Department

· Foundation and Structural Layouts

· Reinforced Concrete Specification

· Steel-work Specification

· Foundation Settlement Data

· Procedures for Earthworks like Excavation and Leveling

· Floor or Wall cut-out section Layout

· Drawing of Platform, Ladders, Stair and Hand-railing

· Road Layouts

Fire Fighting and Safety Department

· Hazards Study Report

· Layout Approval Report

· P & ID for Fire Water Piping

· Fire Fighting Equipment Layout

· Water Storage Tank Data Sheet

· Operating Manuals for Fire Fighting Equipment

· Extinguishing System Design

Deliverables of Piping Department

· Layout

· Overall Site Plot Plan

· Area Mark-up

· Unit Plot Plan

· Zero-Level MTO (Material Take-off)


· Equipment Layout

· General Arrangement (GA) Key Plan

· Piping Layout (GAD)

· Piping Study

· Pipe Support Layout

· Nozzle Orientation Drawing

· Pipe Rack Layout

· 3D Model

· Construction Isometric

· Intermediate MTO

· Vessel Trim Drawing and MTO

· Vendor Drawing Review Report

· Final MTO

· Work Completion Tracking Report

· As-Built Drawing

Material

· Materials Selection Data

· Pipe Thickness Calculation

· Miter Bend and Reinforcement (RF) Pad Calculation

· Pressure & Temperature (PT) Rating Table

· Piping Material Specification (PMS)

· Valve Data Sheet (VDS)

· Special Parts Data Sheet

· Vendor Drawing Review Report

· Corrosion Study Report


· Material Testing Report

· Pressure Test Procedure

Stress

· Stress Critical Line List

· Stress Analysis Specification

· Stress Sketches

· Support Selection List

· CAESAR Analysis Report

· Support Drawing

· Support Span List

· Piping Loop Calculation and Layout

· Different Load Specification Sheet of Supports

· Final Stress Report

Deliverables or Information Provided by Client

Product Concept

Operating Guidelines

Codes and Standards as per Location

Statutory Requirement Details

Metro-logical Data

Users and Uses of Piping Deliverables

Overall Plot Plan

Used by all the departments including clients.

For the Finalization of pipe rack, trenches, and underground facilities (Pipes/Cables).
Zero-Level MTO

Used by the procurement department.

For estimation of cost and bidding.

Intermediate MTO

Used by the procurement department.

For ordering purposes.

Final MTO

Used by the procurement department.

For review purposes.

Unit Plot Plan

Used by all departments.

For finalizing work break-down structure (WBS).

For match line and scope finalization.

Equipment Layout

Piping Department: for preparation of GA key plan and piping lay out.

Civil Department: for equipment foundation location & building layout for designing of
foundation/building.

Electrical Department: for electrical cable/junction box layouts.

Instrument Department: for data transfer cable layouts.

Equipment Department: for preparation of installation plan.

GA Key Plan

Used by the piping department.

For finalization of exact piping layouts, north/east co-ordinates of match lines which are
required for continuation.

Piping Layouts

Piping Department: for preparation of intermediate MTO, construction isometrics, nozzle


orientation, and pipe support layout.
Civil Department: for knowing piping cut-offs.

Electrical Department: for the development of cable layouts of instruments that are
mounted on pipes.

Instrument Department: for the development of cable layouts of instruments that are
mounted on pipes.

Nozzle Orientation

Mechanical Department: for updating MDS (Mechanical Data Sheet) as an input to the
vendor.

Vendor: for equipment fabrication to weld nozzles to equipment.

As-built Drawing

Used by the client.

For record purpose, future review, and modification.