Professional Documents
Culture Documents
Purpose
The primary purpose of the schedule is to establish the T/A duration and sequence of activities. The schedule
supports the T/A with data to:
identify critical activities
guide the work in the field during execution
allow the execution team to make timely decisions
feed planned and earned labour units or worklist or Jobcard (JC) - DFL (Direct Field Labour) to the reporting
system, i.e. including foreman, hands on tools and first line of supervision (planned/earned)
identify areas of difficulty
assist with job package quality control
generate progress reports
historical database with ‘as-built’ information
Purpose & Scope
Key Area
Overall T/A
The schedule should be fully integrated. That is, it should include all work to be executed pre, during, and post the
T/A including maintenance, project scope and operational maintenance. The scope of T/A Schedule supports
phases 4 to 7 of the Perform Turnarounds process as shown in Figure below:
Purpose & Scope Key Work Process Interfaces Q&A
Critical Path
Purpose & Scope Key Work Process Interfaces Q&A
Observation:
The level 2 may be split into subsystems (if any).
A good practice is to split the level 2 into the T/A phases (Shutdown,
Decommissioning, Execution and Pre-commissioning, Commissioning
and Start-up).
Activity coding will often be used to create the schedule structure,
providing a lot of flexibility to then ‘slice and dice’ the schedule for
analysis.
Schedule Structure
Schedule Level
Level 1: High level schedule (typically in days) for the entire T/A window. Level of detail only shows Pre- SD/Decon – Mechanical
Window – SU for the shutdown - Post. This is an overview typical for business planning/top management.
Level 2: High level schedule (typically in days) for the entire T/A window. Level of detail only shows Pre - SD/Decon –
Mechanical Window – SU - Post by Area or Unit. Standard for Operations planning.
Level 3: High level schedule (typically in days) for the entire T/A window. Level of detail shows Pre- SD/Decon – Mechanical
Window – SU - Post by Area/Unit by Equipment Type.
Level 4: Detailed schedule (in hours), activity based, with detailed durations per activity for the direct crafts in the field. Standard
for worklist/JC activity assignment on P6
Level 5: Very detailed schedule (in hours), activity based, with detailed durations per activity for the direct crafts in the field and
for supporting crafts (safety, supervision, etc.). Typical for the entire critical path.
Purpose & Scope Key Work Process Interfaces Q&A
Level 1: High Level Milestone Level 2: Execution Level Level 3: Planner Milestone
RFSD – unit level Milestone Start Piping Work
RFSU – unit level All Relief Valves and Controls Valves Finish Exchanger Work
removed
T/A finish – unit level Near-critical path Mechanical Complete Finish Insulation Work
etc
Build Schedule
Working Calendar
Activity calendars are an important piece of the schedule quality and integrity. Ensuring calendar alignment with
the execution team strategy is key to providing accurate and insightful data to the DFL. Here is an example of
typical T/A calendars:
Pre-Shutdown 5 x 10 x 1 / 6 x 10 x 1
Non-Critical Path T/A 6 x 10 x 2
day/week x hour/shift x shift/day
Critical Path T/A 7 x 10 x 2
Post-Shutdown 5 x 10 x 1 / 6 x 10 x 1
Build Schedule
Define the Activity on P6
Job Card (JC): a card which contain everything that the team on the ground needs to complete the task. It includes
descriptions of specific tasks, the related drawings, labour, equipment, materials, and time.
Benefit:
Quantify the T/A task to be reported out in T/A report or dashboard
Scrutinize and mapping activities based on disciplines or role
Define scope of responsibilities
Detail and summary manpower, time, material requirement
Easier to manage and integrate information from planner point of view (produce dashboard etc)
JC will be assigned as the activity on P6 T/A Schedule (JC1, JC2, JC-PIPING-1, JC-ELE-3, etc)
COMPANY Project xyz
XYZ
Build Schedule
Define Schedule Logic
Soft vs Hard Logic: Hard logic is logic that is required for sequencing the work. For example, we cannot pull the tube bundle
before removing the exchanger head. Soft logic is logic that is not really necessary for the execution of the work. Soft logic may
be used to reflect a preference in work sequencing.
Two defining factors that can drive the T/A critical path:
Time based (more common for onshore T/As where the longest path/sequence of work will be the driver).
Resource based (more common for offshore T/As where resource constraints may be the determining factor of how
much work can be executed and therefore be the critical path driver).
Purpose & Scope Key Work Process Interfaces Q&A
Sample of schedule
quality check with
PRA
Optimise Schedule
Improve Work Schedule
Leverage experience and know-how to improve the schedule and productivity. Here are some examples:
Workfront available in case of early finishes (look-ahead report).
Consider incentives/penalties
Perfect work packs are essential to eliminate missing parts/tools/services, etc.
Use tools/parts/consumables runners (DFL specifically for tools/equipment/material logistic on site)
Mobile restrooms and toolboxes at strategic locations close to the work sites.
Hot-bolting – insert new bolts and nuts in campaign or pre-T/A so that removal of bolts for flanges/valves/equipment
goes faster.
Warm-bolting and removing half of the bolts from flanges during pre-T/A will make removal of equipment even
quicker.
Competent permit coordinator
Optimise Schedule
Schedule Optimisation Workshop
The objectives of the T/A schedule optimisation workshop are to:
optimise T/A execution in terms of duration and cost for the T/A without impacting safety
review and improve the proposed work methods, safety and quality planning and conduct a risk assessment of
those activities which impose a potential threat to achieving the desired results
provide an external perspective on the execution of the Turnaround (second eye)
produce a clearly defined and mutually agreed action plan.
Optimise Schedule
Schedule Optimisation Workshop
Optimise Schedule
Schedule Baseline (BL)
The Performance Measurement Baseline (PMBL). It is an approved copy of the project schedule that can be used
to analyze project performance and report schedule variances and performance. BL should never be rescheduled,
only updated with changes to labour units. This allows for an accurate comparison of current percent complete
with planned percent complete. This baseline is a component of the S-curve report. It should be assigned as the
‘Project Baseline’ within Primavera.
Purpose & Scope Key Work Process Interfaces Q&A
COMPANY
XYZ T/A Dashboard
(SAMPLE)
Manage Integrated Schedule
Worklist & Job Card (JC)
Worklist or JC Dashboard
Manage Integrated Schedule
P6 Schedule
Backup Slides
Purpose & Scope
Planner in T/A
T/A Planner job desc:
Liaise directly with all focal points to obtain required information for effective plans
Plan and integrate all work scopes into one overall logically linked turnaround plan
Measure progress against milestone plan
Update the pre-turnaround and turnaround schedule and produce progress reports
Prepare performance forecasts and projections
Prepare resource plans (material, equipment, labour)
Basis of Schedule
The deciding factors for how to organise and integrate the basis schedules are:
Align the schedules to the teams. The schedules align to the schedulers who align to the coordinator(s) who align
to key contractor work forces. This is best for schedule ownership.
Check that the schedules are aligned with the operational relationships. A small number of dependencies can be
managed via constraints (simplest, but manual) or schedule to schedule logic ties.
Basis of Schedule
Timeline
The timeline of developing a T/A schedule varies significantly and is driven by the milestone plan. Typical
parameters that influence schedule development include:
time available to plan and schedule
planning and scheduling proficiency
anticipated shutdown period
available craft and expertise
Material/equipment deliveries.
Basis of Schedule
Scheduling Methodology
Planning tools with Critical Path Method (CPM) scheduling and Precedence Diagramming Method (PDM),
(commonly Primavera P6)
An effective schedule is a model of the T/A that includes :
A list of all activities and its duration required to complete the T/A.
The resource requirements by trade for each activity.
The dependencies between activities.
The coding structures and assignments.
All Project, Operations and Maintenance activities that will be executed during the T/A should be integrated into
the schedule. The T/A scheduler should:
Set activities priority
Compress critical path of T/A by fast tracking or crunching/crashing the schedule
Build Schedule
Gather Scope
Create a Schedule and Gather Scope
T/A or Schedule basis document (method of statement, worklist, JC)
CMMS work orders (automatically through interface or by manual input)
Historical schedule from previous events’ library
Project Team’s T/A scope
Contractor work packs (may come in various agreed formats).
Optimise Schedule
Schedule Quality Check & Schedule Risk Analysis (SRA)
Schedule Risk Analysis (SRA): P6 SRA may be considered when the T/A is large or of high complexity
Manage Integrated Schedule
Techniques to Gather the Information to Update the Schedule
A number of techniques can be used to help gather information from the field:
post a schedule on the wall for better visualization, usually in war-room.
organise formal update conference call/meeting at an agreed time to review all jobs running. Typical questions to ask are:
Is the worklist/JC done and accepted? Are you over or under budget?
Has the material come in yet? Are the jobs running as estimated?
Are you ahead or behind schedule? Are any problems looming?
have a scheduler call/meeting with every responsible party to find out status, and enter the data and update the schedule
(before the meeting preferably)
critical path jobs should be physically verified
equipment progress follow-ups.
Manage Integrated Schedule
Typical Day in the Life of a Turnaround Scheduler
Shift T of D Task
10:00 AM Lunch/break