# Key Item MZP's Comments on Rev. 0 ABE Action MZP's Comments on Rev. 1 ABE Action for Rev. 1
for Rev. 0
Contractor shall ensure that all designated activity codes within his schedule There are 80 of 2779(approx. 3%) cost loaded activities without "BOQ" code assigned to
6b Activity Code Assignment Done Done
are assigned appropriately. Refer to Attachment 1- them. Refer to Attachment 6B
Monthly distribution provided by Contractor in his submittal differs from his programme.
Likewise, 435 of 3212 (approx. 14%) task dependent construction activities do not have
Not Satisfied. Contractor shall ensure that Programme is properly resource
Resource Loading (S-Curve & loaded and levelled to establish adequate resource distribution. Monthly assigned resources. It is important to highlight that impact of these exclusions could vary
11 Done from considarable to significant especially affecting S-curves, histograms, earned value Done
Histogram) Distribution (Histogram) & Overall Profile (S-Curve) shall be attached alongside
reporting & payment. Therefore, the Contractor is strongly advised to adequately
Contractor's submittal
resource load with unique resource names & IDs (& resource level where necessary) all
required construction activities.
Refer to Attachments 14A, 14B & 17 - Contractor shall refrain from using
14 Logic excessively stacked logic in his programme & excessive use of open-ended & Done Subject to resolutions on Item 10 of this checklist Done
open loop activities (SS / FF dependencies).
Contractor shall provide justification for lags used within his programme (Refer to
15 Lags Not Satisfied. Refer to Attachment 15 - Done Done.
Attachment 15)
450 of 3212 (approx. 15%) task dependent " Construction" activities do not have
assigned cost. It is important to highlight that the impact of these exclusions could vary
from considerable to significant especially affecting S-curves, histograms, earned value
19 Cost Loading (S-Curve & Histogram) Not Satisfied. Contractor's cost loading is to match attached BOQ Summary Done Done
reporting, cashflow & payment. Therefore, the Contractor is strongly advised to
adequately cost-load (& resource level where necessary) all required construction
activities.
Not Satisfied. Contractor shall provide narrative with his programme detailing
but not limited to execution approach, interfaces with subcontracts,
20 Overall Execution Plan (Narrative) stakeholders, external dependencies etc.The contractor shall attach logistic Done Subject to resolutions on Item 10 of this checklist Done
plan alongside the program narrative describing in details how construction
works shall be executed.
Compliance Sheet
# Key Item MZP's Comments on Rev. 1 ABE Action for Rev. 1 MZP's Comments on Rev. 2 ABE Action for Rev. 2
Not Satisfied. -
Assigned activity code must be unique to project -
There are 80 of 2779(approx. 3%) cost loaded activities without "BOQ" code assigned to
6b Activity Code Assignment Done Some codes such BOQ Division & Work Type are wrongly assigned Done.
them. Refer to Attachment 6B
at the activity level as mentioned in previous revisions(Refer to
Attachments 6A & 6B)
Not satisfied. Assigned costs at activity level do not match with BOQ
450 of 3212 (approx. 15%) task dependent " Construction" activities do not have
Division (as previously mentioned & highlighted in Item 6B of this
assigned cost. It is important to highlight that the impact of these exclusions could vary
Checklist). Refer to Attachment 6B & Cost Distribution Comparison -
from considerable to significant especially affecting S-curves, histograms, earned value
19 Cost Loading (S-Curve & Histogram) Done Rev 2 N.B. Contractor shall ensure the Done. ( Refer Attachment)
reporting, cashflow & payment. Therefore, the Contractor is strongly advised to
following: -Assigned Activity Code (related to
adequately cost-load (& resource level where necessary) all required construction
Cost) complies with activities described under each & respective
activities.
BOQ Divisions