DELAY EVENT - 01

Sl.no Description of delays Start Finish Remarks

ITS Additional works

Activity ID Delay Event Activities Start Finish

RFI submitted for confirmation of additional works shown in


DE 01-10 16-Mar-17 16-Mar-17 Additional work shown in Design NOC
Design NOC

DE 01-20 Received reply to RFI 17-Mar-17 20-Mar-17 Instructing to follow the Design NOC

DE 01-30 Company submitted Notice to Claim 21-Mar-17 29-Mar-17

Engineer's comments:
DE 01-40 Engineer's rejection to Notice to Claim 30-Mar-17 25-Apr-17 1. Submit Cost Proposal / New rate
2. Obtain Construction NOC

Company comments:
1. ITS not indicated in Tender Drawings.
DE 01-50 Company replied to Engineer's rejection letter 25-Apr-17 26-Apr-17 2. Requested to issue approved Contract / Construction Drawings
to analyse exact scope of works.
3. Mentined the Kick-Off Meeting Instruction.

DE 01-60 Awaiting response from Engineer 27-Apr-17 23-May-17

Mentioned that additional resources to be deployed for 360 days to


DE 01-70 Company submitted Interim Particlars 24-May-17 24-May-17 complete the ITS works.
No impact on the final completion date.

Rejection Reasons:
1. All information received during tender stage have been
incorporated in tender drawings.
2. Formal information regarding the existing ITS installations duct
lines etc. were provided with tender drawings anticipating such
proposal/diversion with final Design NOC/Construction NOC
DE 01-80 Engineer's rejection to Claim 24-May-17 25-May-17 and cost implication incorporated under provisional sums.
3. Advised to prepare shop drawings based on the Final Design
NOC and to submit appropriate cost estimate.
4. Engineer's Instruction will be issued after consultation with
Employer.
5. Consultant are in the process of obtaining approval from the
Employer to perform the above work under provisional sums.

Company Reply:
1. ITS Network was not reflected in either Tender / Contract
Drawings.
2. In Consultant Letter 2017 dated 25th Apr 17, Engineer instructed
to take up this additional work.
DE 01-90 Company Replied to Engineer's rejection letter 26-May-17 30-May-17
3. 11 km of duct & 60 Nos of chambers. The resources required is
additional to originally planned resources and not extension of
existing resources.
4. This work constitutes a variation order and therefore cannot be
incorporated in Clause 8.3 Programme.

DE 01-100 Awaiting response from Engineer 31-May-17 26-Jun-17

Company Comments:
1. Based on Design NOC & Advance copy of the Construction
Drawings, Construction NOC is applied, awaiting Construction
DE 01-110 Company submitted Interim Particlars 27-Jun-17 27-Jun-17
NOC.
2.As final construction drawings and construction NOC are not yet
received, the scope of works is not completely clarified.

DE 01-120 Awaiting response from Engineer 28-Jun-17 23-Jul-17

DE 01-130 Company submitted Interim Particlars 24-Jul-17 24-Jul-17 Same Comments as previous Interim Submission.

DE 01-140 Awaiting response from Engineer 25-Jul-17 19-Aug-17

Company Comments:
DE 01-150 Company submitted Interim Particlars 20-Aug-17 20-Aug-17
1. The complete details of ITS works are not entirely clarified.

DE 01-160 Awaiting response from Engineer 21-Aug-17 15-Sep-17

Company Comments:
DE 01-170 Company submitted Interim Particlars 16-Sep-17 16-Sep-17 1. Shop Drawings have been approved for all the ITS works and
Construction NOC have been received partially.

DE 01-180 Awaiting response from Engineer 17-Sep-17 13-Oct-17

Company Comments:
1. Company estimated the quantities for ITS works from the
final construction drawings.
DE 01-190 Company submitted Final Particlars 14-Oct-17 14-Oct-17
2. Based on the quantities, Cl 8.3 Programme is impacted and
impact is 14 days as on 14 Oct 17 and the impacted completion
date of the project is 5 Mar 19.

Engineer's comments:
1.ITS scope had been available to Company in Mid of May 2017
and Company failed to obtain the construction NOC on time.
2. As per Sub Clause 13.3 contractor should not delay any
additional work whilst awating engineer response.
DE 01-200 Engineer's rejection to Claim 15-Oct-17 20-Feb-18 3. Contractor's non-compliance to the requirements stipulated
under sub-clause 8.4 of the conditions of contract and PS 1/31 of
the Particular Specifications.
3. Company have to follow the commitment made during meeting
with Client on 26 Dec 2017 wherein the contractor agreed to
waived back all outstanding claims related to EOT.

Company Comments:
1. We have not made any delay in awaiting responsed from the
Engineer.
2. As per Clause 8.4, Company has shown the delay in the Critical
Path of the Clause 8.3 Programme.
DE 01-210 Company replied to Engineer's rejection letter 21-Feb-18 27-Feb-18 3.We have submitted all the notices, interim particulars and
detailed particulars on time ((within 28 days) but we have not
received the same from Aurecon.
4. In the meeting with Client Company promise to complete the all
major work on time, Except Underpass which will complete within
11 month after traffic diversion.