Kuwait Oil Company (K.S.C.

)
Support Services Group (S&EK)
Project Management Team-II (S&EK)
Minutes of Meeting
Meeting Number: 73 Meeting Type: Progress Review Meeting
Date: Sunday, 05 Feb 2023
th
Contract No: 15052373
M/s Al-Ghanim International General
Time of Meeting: 13.00 – 14:45 Hours Contractor:
Trading Co. W.L.L.
Location: Contractor’s Site Office Recorded By: A Rahman
Attendees:
Distribution:
COMPANY COMPANY
TLPM-II (S&EK)
Name Designation Phone All KOC Attendees – by DIMS
File: Contract No. 15052373
Yousef Al Othman Senior Engineer 55161686
Fahad Al Azmi Lead Construction Engineer 60006754
Othman Al Jasmi Construction Engr –UD 96660065 Copy by fax :
Hassan Behbehani Snr Supervisor Construction 66816661 Contractor: M/s. Al-Ghanim International
Rajab Ali Engineer Design - Mechanical 22874 General Trading & Contracting Co. W.L.L.
Anwarul Haque Engineer Design – Instrumentation 21819
Javed Ahmed Engineer Design - Civil 21817
Jamil Hussain Ahmad Engineer Design - HVAC 21857
Mohanty Pravanjan Engineer Design – Electrical 21874
A Rahman Engineer- Planning 21605

CONTRACTOR: M/s Al-Ghanim Int’l.

Name Designation Phone

Amr Gad Project Manager 94977198


Vijay Chander Lead Engineer 97282470
N. Rajesh Planning Engineer 69030488
Shyam Krishna HSE Engineer 96006076

CONTRACT NO. 15052373


CONSTRUCTION OF REMOTE HEADER MANIFOLDS AND ASSOCIATED WORKS
IN SOUTH AND EAST KUWAIT AREAS
(Contractor: M/s Al-Ghanim Int’l. Gen. Trdg. &Contg. Co.)

Sr. ITEM DESCRIPTION Action By / Date


Page 1 of 11
No.

INTRODUCTION:

Lead Construction Engineer welcomed all the attendees and informed that the
agenda of this progress review meeting is to discuss the bottlenecks and technical
issues related to 1st Year and 2nd Year RHMs to achieve the remaining 6 Nos. RHMs
within the Revised Contract Completion Date i.e. 09th July 2023. Info.

Furthermore the Senior Engineer highlighted the following:

1. All 6 Nos. of RHMs (1st and 2nd Year) are in advanced stage of Construction
and shall be tracked closely to achieve the targets.

PROJECT STATUS
Lead Construction Engineer informed the Contractor to present the status for the 1st Info.
and 2 nd
Year RHMs and advised that any pending issues related to design and
Construction shall be highlighted.

The Contractor presented the 1st and 2nd Year RHMs the project progress as on 05 th
Feb 2023.
DESIGN WORKS STATUS - 1ST YEAR RHMs

A ENGNIEERING DELIVERABLES STATUS:


TYPE OF TOTAL NO. OF APPROVED BALANCE % Info.
1. DOCUMENTS DOCUMENTS TO BE COMPLETE
APPROVED

1. DESIGN 430 430 0 100 %


DOCUMENTS Info.
DRAWINGS 489 489 0 100 %

The Contractor confirmed that no documents related to vendor engineering are


pending for approval related 1st Year RHMs

2.

DESIGN WORKS STATUS - 2nd YEAR RHMs


ENGNIEERING DELIVERABLES STATUS: Info.
TYPE OF TOTAL NO. OF APPROVED BALANCE %
DOCUMENTS DOCUMENTS TO BE COMPLETE

Page 2 of 11
B APPROVED
1. DESIGN 320 310 10 96.87 %
DOCUMENTS
DRAWINGS 347 305 42 87.89 % Info.

VENDOR DELIVERABLES STATUS:


TYPE OF TOTAL NO. OF APPROVED BALANCE %
DOCUMENTS DOCUMENTS TO BE COMPLETE
APPROVED Company
2.
DESIGN 320 481 416 86.48 %
DOCUMENTS
DRAWINGS 245 194 51 79.18 %

Company
The Contractor has provided 35 Nos -drawing and document’s transmittal list which
submitted to respective discipline engineer for approval. Lead Engineer informed
that most of drawing approval under routing process.
3.

Lead Construction Engineer enquired about the pending Work order to be issued for
2nd Year RHMs. The Contractor informed that total 98 work order need to be issue
by company. Lead Construction Engineer confirmed that the issuance of work order
4. will be expedited.

CONSTRUCTION / PRECOMMISSIONING AND COMMISSIONING


Info.
WORKS STATUS - 1ST YEAR RHMs

C
The Contractor presented the pending construction works for GC-03 R1 & GC-19
R1 as below:

S.NO WORK DESCRIPTION % COMPLETE


1.
GC-03 R1
1. Installation & Testing of Earthing & Lightning
98%
Materials
2. Glanding & Termination of Electrical
98%
Equipments
3. Installation & Testing of Panels inside
95%
Buildings
4. Installation & Testing of DG & Associated
95%
Items
5. Installation & Testing of HVAC Package 95%
6. Installation & Testing of UPS & Batteries 95%
Page 3 of 11
7. Installation & Testing of DB's 95%
8. Installation & Testing of Light Poles 95%
9. Installation & Testing of Light Fixtures 95%
10. Installation & Testing of Solar System 95%
11. Installation & Testing of Electrical Cables 95%
12. Installation of Cable Trays & Supports 93%
13. Installation of Lighting inside Containerized
80%
Building
14. Installation & Testing of Panels inside Building 95%
15. Installation & Testing of Panels inside GC's 95%
16. Installation & Testing of Instrument Cable 95%
17. Calibration , Installation & Testing of Field
95%
Instruments
18. Calibration , Installation & Testing of Fire &
95%
Gas Instruments
19. Installation & Testing of Junction Box 95%
20. Glanding & Termination of Instrument Items 95%
21. Installation of Cable Trays & Supports 95%
22. Installation & System Modification of
80%
ESD/DCS/ F& G /H2S at GC's
23. Installation & Testing of FACP inside Building 0% Contractor
GC-19 R1

1. Installation & Testing of Solar system 90%


2. Installation of E SCADA 60%
3. Installation & Testing of DG & Associated
95%
Items
4. Installation & Testing of FACP inside Building 90%

Lead Construction Engineer enquired about all pending SAT schedule for GC-03 &
19, the Contractor informed tentative dates are as follows:

Info.

GC-03R1
Systems SAT Start Date End Date
2.
Electrical
LV Switchgear 12th Feb 2023 16th Feb 2023
MOV DB & Lighting DB 20th Feb 2023 22th Feb 2023
HVAC 12th Feb 2023 13th Feb 2023
Page 4 of 11
AC UPS 13th Feb 2023 16th Feb 2023
DG 01st Mar 2023 5th Mar 2023
Instrumentation
PLC 28st Feb 2023 4th Mar 2023
MOV Master Station 08th Mar 2023 11th Mar 2023
FACP 15th Mar 2023 19th Mar 2023

ESD 03rd Week of April 2023


FGS 26th Mar 2023
H2S 27th Mar 2023
DCS 28th Mar 2023
Loop Check 28th Mar 2023 10th April 2023
Info.
GC-04 R2
Systems SAT Start Date End Date
ESCADA 20th Feb 2023 23rd Feb 2023

GC-19 R1 Contractor

Systems SAT Start Date End Date


FACP Yet to Confirm Yet to Confirm
MPFM Yet to Confirm Yet to Confirm
Contractor
ESCADA Yet to Confirm Yet to Confirm
SOLAR Yet to Confirm Yet to Confirm
DG 21st Feb 2023 23rd Feb 2023
Contractor
Diesel Transfer Pump Yet to Confirm Yet to Confirm

Lead Construction Engineer informed that SAT date which are start in 1 st week of Contractor
Ramadan need to shift before start of Ramadan.

Lead Construction Engineer enquired about PSSR recommendations and pending


Punch list for 1st year RHM.
Contractor has provided update upon all pending PSSR recommendations and open
Punch list details as follows.

GC No A & B Category C category Total Pending

Page 5 of 11
3. GC-04 2 39 41 Info.
GC-07 0 85 85
GC-11 3 149 152
GC-19 0 85 85

Senior Engineer informed to check pending GC-11 Punch list with maintenance and
close the pending punches, and further he added to prepare SAT report by tomorrow
for GC-03, GC-07 & GC-11 and submit comments.

Senior Engineer informed need to shift light pole foundation for MOV-DB for
minimum 3 meter instead of 8-10 meter at site.
4.

Senior Engineer informed that need to cross check all transmitter are reading the
scale within the existing F&G coverage sensor for new line connection or not, or
5. any medication needed for F&G coverage and further.

CONSTRUCTION / PRECOMMISSIONING AND COMMISSIONING


WORKS STATUS – 2nd YEAR RHMs
6.

The Contractor presented the pending construction works for 2 nd Year RHMs as
below:

D
S.NO WORK DESCRIPTION % COMPLETE
1. Design & Construction of Light Pole
99%
Foundation
2. Design & Construction of MPFM Foundation 98%
1. 3. Design & Construction of Diesel line
80%
Foundation
4. Electrical Equipment & Support Foundation
75%
and Structural Works
5. Design & Construction of JB's, Instrument
75%
Foundation & Structural Works
6. Design & Construction of Pipe Support
74%
Foundation at Receiver & Tie -in area
7. Design & Construction of Platform & Valve
74%
Support Foundation -Tie-in area
8. Design & Construction of DB Foundation 30%
9. Design & Construction of Air Volume Tank
5%
Foundation
10. Installation of MPFM Skid 99%
11. Fabrication, Installation of Piping
95%
Interconnection t RHM Area
Page 6 of 11
12. Fabrication, Installation of Piping from
90%
Receiver To Tie-in
13. Fabrication, Installation of Piping for Diesel
38%
Distribution Line
14. Fabrication, Installation of Piping for Potable
6%
Water Line
15. Fabrication , Installation of Instrument Air Line 0%
16. Installation of Diesel Transfer Pump 0%
17. Installation of Eyewash & Safety Shower 0%
18. Installation of Diesel Tank 0%
19. Installation of Jib Crane 0%
20. Installation of Light Poles 72%
21. Installation of Electrical Cables 85%
22. Installation of Earthing & Lightning Materials 2% Info.
23. Glanding & Termination of Electrical
48%
Equipments
24. Installation of Cable Trays & Supports 41%
25. Installation of HVAC Package 40%
26. Installation of CP System for 20" Trunkline 20%
27. Installation of Panels inside Buildings 20%
28. Installation of DB's 8%
29. Installation of Light Fixtures 0%
30. Installation of UPS and Batteries 0%
31. Installation of DG and Associated items 0%
32. Installation of Lighting for Building 0%
33. Installation of Instrument Cable 44%
34. Installation & System Modification of ESD at
36%
Control Room
35. Installation of Junction Box 30%
36. Fabrication & Installation of Stanchions and
30%
Supports
37. Installation of Cable Trays & Supports 26%
38. Glanding & Termination of Instrument Items 22%
39. Installation & Testing of FOC Cable 19%
40. Installation of Field Instruments 0%
41. Installation of Fire & Gas Instruments 26%
42. Installation of Instrument Panels inside
0%
Building
43. Installation of FACP inside Building 0%
44. Installation of Instrument Cabinets (Remote I/O
0%
& FOCs) inside GC's
45. Installation & System Modification of DCS at
0%
Control Room

Page 7 of 11
46. Installation & System Modification of F& G at
0%
Control Room
47. Installation & System Modification of H2S at
0%
Control Room

Lead Construction Engineer enquired about all pending SAT schedule for 2 nd Year
RHMs, the Contractor informed tentative dates are as follows:

GC-03 R2:
2.
Systems SAT Start Date End Date
Electrical
LV Switchgear 09th April 2023 13th April 2023
MOV DB & Lighting DB 15th April 2023 17th April 2023
HVAC 21st April 2023 22nd April 2023
AC UPS 01st May 2023 04th May 2023
DG Yet to Confirm Yet to Confirm
Instrumentation
PLC 14th May 2023 17th May 2023
MOV Master Station 20th May 2023 23rd May 2023
FACP 28th May 2023 31st May 2023
ESD 03rd June 2023 04th June 2023
FGS 05th June 2023
H2S 06th June 2023
DCS 06th June 2023
Loop Check 08th June 2023 16th June 2023

GC-09 R1:
Systems SAT Start Date End Date
Electrical
LV Switchgear 12th Mar 2023 16th Mar 2023
MOV DB & Lighting DB 21st Mar 2023 23rd Mar 2023
HVAC 28th Mar 2023 29th Mar 2023
AC UPS 15th April 2023 18th April 2023
DG Yet to Confirm Yet to Confirm
Instrumentation
PLC 22nd April 2023 25th April 2023

Page 8 of 11
MOV Master Station 25th April 2023 27th April 2023
FACP 16th April 2023 19th April 2023
ESD 07th May 2023 08th May 2023
FGS 09th May 2023
H2S 11th May 2023
DCS 13th May 2023 14th May 2023
Loop Check 14th May 2023 30th May 2023

GC-09 R2:
Systems SAT Start Date End Date
Electrical
LV Switchgear 23rd Mar 2023 28th Mar 2023
MOV DB & Lighting DB 02nd April 2023 04thApril 2023
HVAC 05th April 2023 06th April 2023
AC UPS 23rd April 2023 27th April 2023
DG Yet to Confirm Yet to Confirm
Instrumentation
PLC 07th May 2023 11th May 2023
MOV Master Station 13th May 2023 15th May 2023
FACP 14th May 2023 17th May 2023
ESD 14th May 2023 16th May 2023
FGS 21st May 2023
H2S 22nd May 2023
DCS 23rd May 2023 25th May 2023
Loop Check 30th May 2023 10th May 2023

GC-10 R1:
Systems SAT Start Date End Date
Electrical
LV Switchgear 28th Feb 2023 06th Mar 2023
MOV DB & Lighting DB 11th Mar 2023 13th Mar 2023
HVAC 25th Mar 2023 26th Mar 2023
AC UPS 04th April 2023 08th April 2023

Page 9 of 11
DG Yet to Confirm Yet to Confirm
Instrumentation
PLC 22nd April 2023 25th April 2023
MOV Master Station 25th April 2023 27th April 2023
FACP 09th April 2023 12th April 2023
ESD 02nd May 2023 03rd May 2023
FGS 04th May 2023
H2S 05th May 2023
DCS 06th May 2023 07th May 2023
Loop Check 08th May 2023 18th May 2023

GC-20 R1:

SAT Start Date End Date

Electrical
LV Switchgear 12th Feb 2023 16th Feb 2023
MOV DB & Lighting DB 20th Feb 2023 22th Feb 2023
HVAC 12th Feb 2023 13th Feb 2023
AC UPS 13th Feb 2023 16th Feb 2023
DG Yet to Confirm Yet to Confirm
Instrumentation
PLC 28st Feb 2023 4th Mar 2023
MOV Master Station 04th June 2023 07th June 2023
FACP 07th June 2023 10th June 2023
ESD 05th May 2023 07th May 2023 & 12th June 2023
FGS 08th June 2023
H2S 09th June 2023
DCS 10th June 2023 14th June 2023
Loop Check 10th June 2023 18th June 2023

Page 10 of 11
CONCLUSION
1. The remaining 6 Nos. of RHMs shall be commissioned with in the revised
contract completion date 9th July 2023.
2. All the pending SAT for 1st Year & 2nd Year RHMs shall be scheduled and
expedited considering the Approved Target dates as per program of Works
3. The Company shall expedite that issuance of pending work orders for 2nd Year
RHMs.
4. All pending design deliverables shall be expedited.
5. SAT punches and PSSR Comments for the 1st Year RHMs (GC-04, 07, 11 &
19) shall be completed in order to handover the RHM Facility.
6. All critical Material of 2nd Year RHMs shall be delivered to achieve the
target dates.
7. As-built drawings for the Completed Work Orders shall be submitted.
Next Meeting Advise:

- The date for next progress review meeting will be intimated. Info
This meeting concluded at 15:00 Hours.

Nothing stated in these minutes of meeting shall serve as or be construed as an instruction from the Company to deviate from or
waive the Contract requirements. Variations to the Contract shall be made only in accordance with the General Conditions of the
Contracts.

FOR COMPANY
Signature :
Name :
Designation :
Date :

FOR CONTRACTOR

Signature :
Name :
Designation :
Date :

Page 11 of 11