Professional Documents
Culture Documents
in China
Changyu Shao, Chief Eng. of Shanghai Municipal Engineering Design Institute (SMEDI), China, and Zhifang Yang, Prof.-level
Engineer of Shanghai Tongsheng Major Bridge Construction Ltd., China
Introduction 10–20 m, is located at over 130 m thick The numbers of different construc-
loose stratum of the Quaternary Peri- tion elements involved are 5700 piles
The Donghai Bridge is a very impor- od. The current velocity of sea water at driven at open sea using “piling ships”,
tant subsidiary project to the Shanghai the bridge site is generally 2,0–2,5 m/s, 700 bored piles cast-in-situ by off-
Yangshan Deep-water Harbor Proj- and the maximum height of wave in a shore platform, 822 large piers of 300 t
ect. The bridge is the first super long return period of 100 years is 6,19 m. weight each installed by off-shore ope-
bridge crossing open sea in China with The maximum measured wind speed rations, and 670 pieces of box girders
the total length of 32,5 km. It starts at at bridge site is 35,0 m/s. with 1700–2000 t weight each installed
Shanghai Luchao Harbor, and crosses
The bridge site is under great influence by lifting vessels with 2500 t capacity.2
the open sea to the Phase I junction
of such climatic and oceanic conditions The alignment of Donghai Bridge is
of Xiaoyangshan Harbor. The proj-
of an open sea, as wind, wave, current, very long. In addition, there are all
ect is characterized by its large scale,
tide, fog and rain; therefore, the annual kinds of bridge structures with very
the severe environmental conditions,
operable days are 240 days for sub- tight construction schedules. The de-
the high technical difficulties, and the
structures, and 180 days for pier and mand for various construction equip-
short construction duration; therefore,
girder assembly. ments in the area was extensive; the
the design of this bridge brought about
a series of problems which were never number of vessels added up to 200, in-
Bridge Layout cluding the 85 m-tall fully rotating pil-
faced before and required detailed
analysis and study for its solution.1 The bridge is 32,5 km in length, of which ing ships, and two lifting vessels with
The designers worked out the plans about 90% is off-shore as illustrated 2500 t capacity each. Moreover, there
and techniques for safe and efficient in Fig. 1. It includes one main naviga- were also a great number of off-shore
off-shore construction; as a successful tional channel, three auxiliary navi- operation platforms, temporary bridg-
result, the construction of the bridge gational channels, non-navigational es for construction, operational docks,
took merely 40 months from June 2002 spans as well as approach spans for and a 350 000 m2 large scale pre-fabri-
to October 2005. port connection. The general informa- cation site for bridge parts to help push
tion of the bridge is shown in Table 1. through the project.2
Keywords: Donghai Bridge; non-
navigational spans; driven steel pipe; The design of Donghai Bridge adopts
pre-cast pier shaft; pre-fabricated in a traffic speed of 80 km/h and dual
three lanes with typical deck width of
Off-shore Non-navigational
one complete span; cable-stayed bridge;
composite box girder. 31,5 m according to Chinese Express Spans
Way Design Code. The loading of the
Span Arrangement
bridge is designed according to a Chi-
Project Overview nese standard truck lane load (20 t For the design of the non-navigational
standard trucks at 15 m intervals and spans, the bridge designers have taken
Construction Environmental
one special truck with a 55 t axle load) multiple factors into consideration.
Conditions
and checked according to a specialized Numerical analysis indicates that when
The bridge, crossing 26 km of wide container lane load (55 t containers at the span exceeds 50 m, the influence of
open sea with the water depth of 10 m intervals). piers on the tidal current is negligible.
Under this premise, the designers have therefore, considering that easier fabri- strength strands, and the vertical pre-
studied the global effects on this proj- cation, transportation, and installation, stressing adopts 32 mm diameter high
ect by adoption of different spans, the constant depth is adopted for both strength deformed pre-stressing bar.
structural styles, and construction kinds of girders – 3,5 m high for 60 m One piece of 60 m span girder weighs
methods; they conclude that it is most span girders and 4,0 m for 70 m span 1700 t and 70 m span girder 2000 t.
economical to adopt 60 and 70 m span girders. Another important advantage
PC box girders for the superstructure, is that the girders with constant depth The 0,8 m thick cross beam at the end
and 1,5 m diameter steel-pipe piles for can be simply-supported at piers easily, of the side span is pre-fabricated to-
the foundations. The PC box girder and the top plan of piers can provide gether with the girder. As the 1,6 m
is pre-fabricated and installed in one good working place for construction thick cross beam at the middle support
complete span that helps to meet the of the wet joints between the simply- is cast-in-situ with the wet joint later,
construction deadline, decrease off- supported spans at open sea. there is no cross beam pre-fabricated
shore workloads, reduce construction in plant for middle-span girder; there-
risk, and improve project quality. It is The bridge is divided into two separate fore, the measure has to be taken to
a very popular span arrangement that bridge decks transversely. The 60 and enhance torsion stiffness by strength-
six to seven 60 m span or five to six 70 m span girders are single-box struc- ening the end sections of middle-span
70 m span PC box girders form one tures made of high-performance con- girder so as to meet stress requirement
continuous unit. crete with specified strength 32,4 MPa. during girder transportation and in-
The deck is 15,25 m wide and the bot- stallation.
Considering that the tidal current tom slab 7,25 m wide. The cantilever
and the scouring depth increases pro- Sixty and seventy meter box girders
of the top slab extends 4,0 m. The top
gressively from seashore to open sea, are pre-fabricated in one complete
slab is 0,26–0,55 m thick. The web and
and the direction of current is more span at the same pre-fabrication plant.
bottom slab at the centre of the span
variable far from the seashore, the de- All the girders are drawn to the dock
are 0,4 and 0,25 m thick respectively,
signers adopt two different kinds of with sliding method and lifted, and
increasing in thickness at supports ac-
span – 60 and 70 m, especially more of then installed by two different lifting
cording to the stress level. The main
60 m spans than 70 m at areas close to vessels (illustrated in Figs. 2–4).
girder is pre-stressed in all three direc-
the seashore. tions internally; meanwhile, external After a girder is simply-supported at
pre-stressing ducts are reserved for fu- piers, the jacks are used to slightly ad-
Superstructure just the girder into accurate position.
ture use. There are two kinds of longi-
Generally the engineering cost of 60 tudinal pre-stressing specifications, 12 The error must be controlled when
and 70 m span girders with the constant and 17 high strength strands of 15,2 mm the girder is placed. Combined with
depth is only just a little bit more expen- diameter. The transverse pre-stressing the oceanic conditions and the crane
sive than those with the varying depth; adopts three 15,2 mm diameter high performance, the error allowance of
Substructure
Two main pylons are founded on two
pile foundations, each of which is com-
Fig. 13: Composite box girder posed of 38 bored piles of 2,5 m dia-
meter and 110 m length. A pile cap is
28 m wide, 56 m long and 7 m deep.
meter for the connection between the The pylon foundation is designed longi-
steel box structure and the concrete tudinally and transversally according
deck. One type is 450 mm long, set to wave impact and ship impact forces,
at the edge of the top steel flange to respectively.
counteract the transverse bending mo-
ments, and another type is 200 mm The main pylon foundations are con-
long. structed with the assistance of plat-
forms that are designed as the steel-pipe
The main pylons are made from rein- truss structure (illustrated in Fig. 16)
forced concrete with specified strength from the experience of petroleum
of 32,4 MPa. The section above the platform at open sea. A steel coffer-
deck is an inverted “Y” shape. Below Fig. 14: Cantilever construction dam (illustrated in Fig. 17) is adopted
the deck is a box structure with un- for the construction of pile cap. The
even width. In the transversal direction steel cofferdams and the platforms are
of the bridge, the dimensions of the There are 107 segments for the whole
fabricated individually and floated to
upper, middle, and lower part of the bridge, including 96 typical segments,
the site, and then connected to each
pylon are 7, 4,2, and 37–28 m respec- the 8 m long closure segment, eight
other. The pylon foundations are con-
tively, corresponding to a longitudinal 5,0 m long segments near the pylons,
structed in the following sequence:
width of 8 m. and two 6,58 m side span segments
(a) establish guiding piles and steel
(Fig. 15). All the segments are pre-
casings, (b) construct the bored piles,
Steel anchor girders are used for two- fabricated in-factory, except 0,5 m long
(c) cast the bottom sealing concrete,
thirds of the stay cables in the anchor- concrete deck at both ends. These two
(d) cast the concrete of pile caps (illu-
age zone, and rigidly connected to the ends have to be filled with joint con-
strated in Fig. 18).
pylon wall. The other one-third of the crete on-site, as to ensure the quality
cables is anchored directly to the con- of construction. The segments should Since combined structures of steel-
crete pylon wall due to their smaller be fabricated in the following sequ- pipe truss platform and steel coffer-
horizontal component force. ence: (a) fabricate parts of the steel dam provided significant stiffness to
There are a total of 224 stayed cables
that are fabricated with galvanized
parallel wires. Each cable consists of a
maximum of 283 wires or minimum of
121 wires of 7 mm diameter.
The deck segments are fabricated in-
factory and then installed with the can-
tilever method (Fig. 14). The segments
at the top of the auxiliary piers and at
the end of the side spans are floated
and hung by floating cranes. Typical
segments are floated to the site and
then hung and installed by cranes on Fig. 16: Steel-pipe truss
the girder. After the installation of seg-
ment, first the steel structures have to be
connected and then wet joint concrete
between segments has to be cast. There
exists compressive forces applied to the
top concrete deck because of the ten-
sion of stay cables; thus the cables can
be installed and tensioned 1 or 2 days
after casting the joint concrete, and al-
lowing the concrete to reach sufficient
strength to resist the compressive
stresses. It takes approximately 4–5
days to install each segment. Fig. 15: View of main bridge Fig. 17: Steel-pipe truss and steel cofferdam