Professional Documents
Culture Documents
At
DURATION OF WORKS
Strict monitoring of health and safety will be carried out throughout the works,
with toolbox talks being given regarding key areas of work.
A general inspection of the site will take place each morning prior to work
commencing, to spot and assess any new hazards that may have arisen
subsequent to the initial risk assessments.
All persons will undertake a site safety induction when first arriving on site
and, subject to having an adequate method statement and risk assessment
and all necessary PPE they will be allowed to commence work.
Continual health and safety monitoring will take place throughout the working
day to ensure the works are carried out safely and in line with the method
statement and risk assessment.
A strict no smoking rule is to be enforced. Smoking is only to take place in
designated safe areas, appointed by site manager, outside the site.
At all times during the works good levels of communication should be upheld,
with daily safety meetings to agree work areas and any additional control
measures to be implemented.
Details of isolation
All services will be identified and made safe as is necessary prior to working
in excavations through the permit to dig.
Services will be disconnected and re-connected by trained professionals
before works take place in their proximity.
A fire and first aid point and emergency muster point will be set up on site.
Adequate trained personnel will be on site at all times to deal with any fire or
first aid incidents.
Included in the site file is a map detailing the route to the nearest hospital
accident and emergency department
All personnel will be briefed on the emergency procedures during their safety
induction.
EQUIPMENT USED
Equipment:
Heras & pedestrian fencing
Welfare & storage units
Pumps
Underground Storage Tanks
Interceptor
Fuel pipe work and associated equipment
Drainage and duct pipe work
360 degree tracked excavator
Welfare cabins
Tipper wagons
Skip wagons
Dumper
Bomag roller
Kerbs
Various hand tools
PPE:
Hard Hat
High visibility jackets/vests
Eye protection (Appropriate for the task)
Gloves (Appropriate for the task)
Oil and chemical resistant reinforced toe safety footwear
Coveralls (Appropriate to the job)
SET UP SITE
Employees MUST wear the appropriate PPE at all times (A minimum of hard hat, hi-
vis vest / jacket and protective boots). No shorts and vests.
Issue a ‘good neighbour’ letter to all nearby properties, informing them of the
works and giving contact details for any queries or potential issues they may
have.
The area is to be cordoned off with 2.5m high Heras fencing, with debris
netting erected along the perimeter.
Pedestrian fencing is to be used to make a safe walking route around the
cabin area and the site entrance.
Conspicuous safety signs will be mounted with site rules and details of
protective equipment needed. Deep excavation signs should be displayed
around appropriate dig areas.
Site welfare & storage units are to be placed, being hi-ab lifted off lorries
ensuring ground is stable, safe system of work is followed and units are level.
Set up welfare facilities to CDM 2007 standards.
Parking is restricted to only 2 vehicles on site; all other vehicles are to park on
the adjacent Client property, accessed via the private lane, and enter site
through the secure pedestrian gate.
Section off an area within the site for deliveries, none are to take place on the
highway. Keep a clear traffic route and plan delivery times to avoid any
congestion – no traffic is ever to queue on the highway.
Create a safe storage area for all materials and equipment, fence off and
clearly designate.
Section off an area on the site for storage of skips; separate waste for
disposal to recycling facilities where possible.
Ensure all tools that have the potential to create dust are damped down at
source – via an on-board water supply.
Adequate access/egress must be provided across the site.
A minimum of 2 certified ABC category dry powder fire extinguishers, with an
adequate fully stocked first aid kit and eye wash station made readily
available for use at designated points, and an emergency muster point must
be established.
Arrange a clean area to wash wheels of exiting vehicles if required, this will be
via the water supply on site.
Fence erection
During the demolition dust will be damped down via hosepipe and site muck will be
controlled by leaving in hard standing areas (as long as possible) for vehicle
movement on and off site.
All waste will be recycled where possible, via licensed facilities. Disposal to landfill
will be used as a last resort.
All clean concrete on site will be re-used as backfill. A crusher will be contracted in,
with driver, to achieve this.
MAKING SAFE
Uplift fuel
Pumps
THE SITE IS NOW GAS FREE – until all tanks are removed this must be confirmed
at the start of each daily shift
DEMOLITION
Canopy
Position the excavator behind the canopy direction of fall – to the side of the
canopy as fall direction is to be away from the existing shop
Anchor the canopy with the excavator bucket at the top of the fascia, where a
support is fixed. Don’t put any pressure on the structure, just anchor it
NB before commencing any hot cutting complete a hot works permit and
ensure the area is clear of flammable debris and confirmed as gas free.
Cut the legs with the gas cutting gear ready for dropping: 3 sides at the
bottom, leaving the side to bend in the direction of fall; 3 sides at the top,
leaving the opposite side to that left at the bottom so that the structure folds in
on itself
NB. The distance between the top and bottom cuts will be the distance the
canopy travels when pushed over, these should be equal on all legs.
Cut the leg attached to the shop diagonally down to the fall direction so that it
will slide free as the canopy falls
Make sure all people and materials are cleared from under the canopy and its
direction of fall
Post watchers to signal a clear footpath and surrounding area before the drop
Release the excavator bucket from its anchor point and push at the front of
the fascia in a slow controlled manner
The canopy will drop forwards, with the top falling back flat on itself, still
attached to the legs, preventing it from travelling
Demolish the canopy structure on the ground using the excavator, gas gear
and hand tools. Use the excavator wherever possible, only resort to hand
methods when machine methods aren’t possible
Ensure the steel is separated and disposed of in bins to a licensed recycling
plant.
The site manager will advise as to specific techniques for demolition if any
difficult situations are encountered and this safe working procedure cannot be
followed.
Check that there has been a suitable asbestos survey carried out and that any
materials have been removed prior to commencement
Strip out materials from the buildings and dispose of in separate skips, taking
out only what it is safe to do so. Keep a clean and tidy site.
o Remove heavy items by mechanical means – excavator or suitable
equipment
o Minimise the risk of any trip hazards by correct storing of materials. Out
of the way, and stacked properly and stable
o Strip out materials from building for disposal in skips using hand tools
(be sure to wear protective gloves when handling waste as it may
contain sharps)
o Warn others inside the building when you are pulling apart or
demolishing structures, keep good levels of communication at all times
with regards to work areas and work tasks
o Keep a check at all times on levels of dust and fumes and any others
that may cause nuisance to the public, take all practicable measures to
reduce these
o Don’t block up routes with discarded debris, maintain emergency
escape pathways at all times
o Dust masks will need to be worn at times when levels of dust are likely
to be high
o Survey all areas before removing waste; there is always a possibility of
sharps being contained in waste piles that may cause injury. Use a
shovel to bin waste into bags for disposal in the skips provided
o If any hypodermic needles are found the local council environmental
health must be contacted for their removal
o Assess each situation as you come to it during the stripping out, ask
advice if you are unsure how structures will be affected
o When removing suspended ceilings take down the tiles before pulling
down the bracings. Make sure you can see what is above and can
plan accordingly when pulling down
Where there is steel in the structure the machine should be able to de-link and
bend over supports for cutting off at ground level with the gas gear if
necessary.
Any hot cutting to be done must be done only when any flammable debris has
been cleared from the area.
Clear back the building floor leaving no obtrusions that may be hazardous to
trespassers, make sure the whole area is flat and debris free and any holes,
pits or trenches have been filled in.
Match the remaining level with the level of the rest of the site, eliminating as is
possible slip, trip and fall hazards.
Separate materials and dispose of in skips and wagons through a recognised
hauler to a registered waste transfer station.
Tank removal
A suitable barrier of at least 950mm is to be erected around the dig area, to prevent
risk of fall.
CONSTRUCTION WORKS
Before commencing any excavating, survey the area for existing, unknown drainage
and services. If any are encountered make safe or divert as is applicable.
Ensure that the method statements and risk assessments are present and approved
for all sub contractors prior to their works commencing.
Using wooden pegs spaced approximately every 1.5m, set the levels to the
depth of the base required (200mm). Place a 50mm dry lean concrete blinding
to the base of the pit
Lay the tank anchor straps flat on the pit base, spacing evenly and align with
the plastic corners which are positioned to the diameter of the tank avoiding
placing a strap where the manhole on the tank will be
Place the grade plate spacers on the blinding at 1.5m intervals. Lay the
reinforcing onto the spacers and the tank straps
Secure the eyes of the straps to the sides of the pit using twine strung across
the pit ensuring that the ends of the straps rise vertically from the plastic
corners
Ensuring the ramp is suitable for mixer access, back the mixer down to the
base, pour the tank base and hand tamp to finish level with the top of the
pegs or use the machine to lay concrete from above
Fully line the tank hole with a geo-textile filter fabric with minimum 300mm
lapped edges
Cover the bottom of the base with a 150mm pea shingle bed raked level
The tank hole is now ready for the tank installation.
Inspection Point 1
Inspection Point 2
Check level of top of base will produce correct tank lid level.
Check correct and sufficient placement of reinforcement.
Check correct grade of concrete poured.
Check correct positioning of holding down straps.
TANK INSTALLATION
A mobile crane is to be set up on a suitable hard standing area no closer than 4
metres from the edge of the excavation (as detailed on the lift plan issued under the
contract lift). If no suitable CBR test is present the area will be laid with type 2,
compacted and rolled to finish.
Inspection point 3
Set out for the bases and excavate down to level with the 360.
A safe path of hard standing material will be arranged for the passage of the
mixer - Site operatives will be made aware of heavy plant movement.
Area is to be set out as per the Architects site drawings.
Reduce dig and prepare area with excavator as per footing drawings.
Ensure all open trenches / pits are made safe, fence off where necessary and
create an access route if man entry is needed.
Clear safe route to bring mixer wagon onto site.
Back mixer into positions to pour, using a safety man with pre arranged hand
signals for manoeuvring and agreed verbal instruction.
Ensure the operator has the correct PPE before setting the mixer ready to
pour.
Pour concrete into position.
All operatives must wear the appropriate protective gloves as per the concrete
COSHH assessment.
Tamp and screed the surface to bring any air to the top and achieve the
desired finish.
Set in any bolts etc as required
PIPE WORK
PRESSURE TESTING
DRAINAGE / SERVICES
Set out for the drainage and service ducting as per the site drawing.
Excavate the area with excavator to the required depths and falls as per site
drawing. All brown water drainage must flow to the site interceptor before
flowing to mains drainage, with the exception of any wash facilities which
must flow out to mains drainage via a silt trap, detergent waste is never to
flow to the interceptor.
Dependant on ground conditions and trench depths, the site manager will
advise whether or not the sides need battering back and the angle at which to
do so
Line the bottom of the trenches with a 10mm pea shingle base
Lay drainage / service ducts to the required fall levels (as per drawing)
BACKFILLING: When the pipe work has been laid it is to be covered with
150mm of pea shingle
The trench can then be brought up to formation levels with the appropriate
materials all in accordance with drawing and specification
ACO DRAINS
Set out the runs for the new drainage as per the site drawing
Dig down to level with the excavator
Set the channels in place with lean mix concrete – ensure the wagon is
watched safely onto site and has a suitable area of hard standing
Make sure that you use proper lifting techniques when placing the drainage
Step down to the gully and ensure the drainage pipe work is installed
Build up and finish the area and edges as needed
Clean up all materials and tidy up, protecting the drainage as appropriate
whilst concrete dries
If trenches or drains are to be left where they may cause a hazard they should
be appropriately made safe
INTERCEPTOR INSTALLATION
KERBING
Reduce levels for the kerb line in accordance with site layout drawing
All kerbs are to be delivered along the installation line, to eliminate any
manual handling
A grab attached to a machine is to be used to manoeuvre the kerbs into
position. No manual handling to manoeuvre kerbs.
Use the grab to raise the kerb
Manoeuvre the kerb into position and lower into place with the grab
Repeat procedure for all kerbs
Ensure that there is an area of hard standing for concrete mixer to manoeuvre
around the site safely
Move mixer into its positions with the use of a safety man to direct around the
site, and make personnel aware of its trajectory
Fix kerbs into position with the poured concrete mix, wearing the appropriate
gloves for protection. Site manager will advise as to the correct protection to
use.
PUMPS
Set out the area for the pump island as per Architects drawings
Ensure the surround is built up
Fix pump cradles in place, ensuring all ducting is placed correctly.
Pour concrete and finish to standard specified on the drawings.
Install new pumps using forklift truck.
Connect up all lines and electrics (Electrics by outside contractor).
Flush pumps through, system is connected and ready to be commissioned.
PAINTING
Reference all the COSHH information for the products being used and take
the precautions prescribed by the manufacturer
Arrange with the contracts manager the areas to be painted.
If higher access is required then it must be via a working platform or ladders,
used correctly within the work at height regulations.
At the end of each evening tidy the working area and make sure it is safe.
Obtain approval at the end of the works, remove all equipment and make sure
the area is clean and tidy.
All works are detailed in the schedule; further clarification can be given by the
site and contracts manager.
KIOSK CONSTRUCTION
Steel erection, cladding and roofing of the kiosk, M&E, fitting out and electrical
installation is to be done by others - ensure their safety paper work is reviewed and
approved prior to start, that they work safely and that they are an approved
contractor prior to commencement.
Brickwork
ACOUSTIC FENCE
Obtain the safety paper work prior to commencement of the contractor and
ensure they are approved. Monitor for safety during the contract.
Prepare their area and explain the sequence of works.
SURFACE FINISHES
The tarmac and white lining will be conducted by external contractors - ensure their
safety paper work is reviewed and approved prior to start, that they work safely and
that they are an approved contractor prior to commencement.
Should site conditions change the site manager may consider that on safety grounds
the above method statement cannot be adhered to. In this situation all work must
cease and guidance sought from the Contracts Manager
CONTRACTOR DECLARATION
I have read and understood the above method statement and will abide by it.
If at any point during the works conditions arise that are be deemed to be unsafe,
work should stop immediately and the site agent should be informed