Professional Documents
Culture Documents
Class Test 2018-19: Mechanical Engineering
Class Test 2018-19: Mechanical Engineering
Delhi | Noida | Bhopal | Hyderabad | Jaipur | Lucknow | Indore | Pune | Bhubaneswar | Kolkata | Patna
Web: www.madeeasy.in | E-mail: info@madeeasy.in | Ph: 011-45124612
Answer Key
Detailed Explanations
3. (c)
Standard deviation of critical path a → e is
= 16 + 5 + 7 + 8 = 36 = 6
4. (c)
At the optimal point, annual holding cost is equal to annual ordering cost
Annual inventory cost = Annual holding cost + Annual ordering cost
= 2 × Annual holding cost
Annual holding cost
⇒ = 0.5
Annual inventory cost
5. (c)
2DC0
Optimum value of Q (Q*) = Ch
Optimum number of orders placed per year,
D DCh
N = Q * = 2C
0
www.madeeasy.in © Copyright :
8 Mechanical Engineering
Σ ti = 10 + 9 + 7 + 9 + 8 = 43
∑ti 43
Balance delay = 1 − = 1− = 0.14 = 14%
n × tc 5 × 10
11. (a)
According to Johnson rule, the correct order will be
0 6 13 21 33 47 56 66
E-F-B-A-D-C-G
Milling
66
Utilisation of milling M/C = × 100 = 92.95% Drilling
71
64 6 20 29 41 51 59 65 71
Utilisation of drilling M/C = × 100 = 90.14%
71
12. (b)
3
5
2
F, 4
A, 3 D, 4
10
10 E, 4 14
0 4 5
1 14
0
C, 5
B, 5 G, 6
3
5
5
Z = 5x1 + 4x2 6
1=
–x
x1 + 2x2 ≤ 6 4
+4
– x1 + x2 ≤ 1
x 2=
3
x2= 2
24
x2 ≤ 2 2
x1 +
x1, x2 ≥ 0 1 2x
2 =
6
Solving the above problem, we get
x1
x1 = 3, x2 = 1.5 1 2 3 4 5 6
14. (d)
It is evident from the net evaluations of the optimum table that the net evaluation corresponding to non-
basic variable y1 is zero. This is an indication that an alternative basic solution exits. Thus we can bring y1
in to basis in place of y3 or y5. The resulting new basic feasible solution will also be an optimum one.
15. (b)
Maximum station time (Ts ) max = 10 minutes
i
Smoothness index (S.I.)
2
( )
n
= ∑ Tsi max − Tsi = (10 − 7)2 + (10 − 9)2 + (10 − 7)2 + (10 − 10)2 + (10 − 9)2 + (10 − 6)2
i =1
(S.I.) = 6
www.madeeasy.in © Copyright :
CT-2018 | ME • Industrial Engineering 9
16. (d)
Using the shortest processing time (SPT) rule, sequencing of jobs is
1 3 2 4
IF 18
Now, FF – = 0 − − = 1
TF 18
20. (b)
12 10 10 8 4 2 2 0 3 1 0 0
14
12 15 11 3
1 4 0
2 0 2 0
6 10 16 4 = 2 6 12 0 = 1 5 10 0
8 10 9 7 1 3 2 0 0 2 0 0
Min time required =10 + 12 + 4 + 8 = 34.
22. (c)
S1 S2 S3
Step (I): Subtract the minimum entry in each column from all the entries on that column.
Step (II): Substract minimum entry in each row of job opportunity cost matrix from all the entries of that row.
0 0 0
0 15 5
0 10 20
Step (III): Draw minimum number of horizontal and vertical lines to cover all zeros. This can be done in 2
lines, which is one less than the number of rows (which is 3.) Thus the solution is yet not fixed. Hence go to
step IV.
c
d
15 5
10 20
www.madeeasy.in © Copyright :
10 Mechanical Engineering
Step (IV): From the uncovered entries, the minimum is 5. Thus substract 5 from all the entries, which are
uncovered. Add 5 at junction of lines. We get the following matrix now, as the revised opportunity cost
matrix.
S1 S2 S3
P 5 0 0
Q 0 10 0
R 0 5 15
Thus final assignment is
Item Supplies Cost
P S2 120
Q S3 140
R S1 125
The minimum cost = 120 + 140 + 125
= Rs. 385
23. (b)
P − d
Qmax = Q
P Q
d
P = 1000 per month
d = 500 per month
Max. inventory level
Q = 1000
d)
–
1000 − 500 (P
Qmax = 1000 = 500
1000
tp (T – tp )
Derivation:
T
Q = P ⋅ tp = T × d
Qmax = (P – d)tp
tp = Q/P
P − d
Qmax = Q
P
24. (c)
s1 = 100/unit v1 = 60/unit
F 1000000
BP1 = = = 25000
s − v 100 − 60
s2 = ?
V2 = 60 + 10% of 60 = Rs. 66
F2 = 1000000 + 5% of 1000000 = 1050000
1050000
BP2 =
s2 − v 2
It is given in the problem that BP is constant.
BP1 = BP2
1050000
s2 – v2 =
25000
s2 = v2 + 42
s2 = 66 + 42 = 108
∴ % change in s = 8%
www.madeeasy.in © Copyright :
CT-2018 | ME • Industrial Engineering 11
25. (c)
At first we convert it in equivalent two machine problem:
Job J1 = M1 + M2 J2 = M2 + M3
A 18 14
B 8 10
C 10 9
D 9 8
Now apply Johnson’s algorithm for 2 machine, we can easily find the sequence.
Johnson’s
Johnson’ s Rule:
• If the minimum is on the J1(M1 + M2) machine process is first.
• If the minimum is on the J2(M2 + M1) machine process it last.
26. (c)
11
12
6
7
4
8 8
3 13
2 4 13
7 20
1 2 5 8
5 6 20
0 5 2
7 2
0 5 4 3
14
11
18
11
29. (b)
To earn the profit of Rs.400
Number of articles to be sold
F 2000
BEP = = = 500 units
s−v 9−5
Margin of safety
www.madeeasy.in © Copyright :
12 Mechanical Engineering
30. (b)
Given D = 50000; S = ` 550; C = (0.40) (P); p = 650; d = 350
The EOQ is computed for each unit price
2DS P
Q* =
C p−d
= ` 994107.28
www.madeeasy.in © Copyright :