Professional Documents
Culture Documents
ABSTRACT: The Panama Canal Authority (ACP) has undertaken a comprehensive assessment of nat-
ural and chronic risks to improve planning and to optimize its engineering safeguards. The risk assess-
ment program began with an all-inclusive risk register. The register lists somewhat more than 500
items divided among the many categories of facilities constituting the Canal (dams, locks, cuts, gates,
power stations, water plants, and others) and among the various hazards facing the Canal (seismic, hy-
drologic, meteorological, operational). Scientific and operations data for the Canal have been compiled
to characterize risk, while modern reliability models have been developed to translate those data into
actionable assessments of reliability and consequence. Risks were categorized as catastrophic, signifi-
cant, or moderate. The first set has been engineered in detail; the others have been approached opera-
tionally. The resulting probabilities and consequences are tracked in acceptable risk charts in FN for-
mat better to understand where risk remediation is called for. This comprehensive risk assessment is al-
lowing ACP to reduce risk while meaningly keeping costs under control.
The Panama Canal, commissioned in 1914, is the risk analysis. This included expanding the ex-
one of the world’s iconic engineering projects. isting risk register for natural risks and building
The Canal provides passage to 18,000 vessels a an inventory of existing ACP infrastructure. This
year, and carries more than five percent of inter- inventory includes, but is not limited to, dams,
national maritime trade. In the early 1900’s, the spillways, locks, navigation channels, power
Panama site, unlike Nicaragua, was thought free plants, water intakes, communications systems,
of natural hazards and was favored in part be- bridges, and other significant structures (Figure
cause of this. History has changed that appraisal 1). Phase I also included a failure and effects
and it is now understood that seismic, hydro- analysis (FMEA). This work was undertaken by
logic, and meteorological hazards do affect the the Engineering Division of La Autoridad del
Canal. In addition to natural hazards, an engi- Canal de Panamá (ACP).
neered system of this scope must also grapple Phase II focused on engineering and sys-
with chronic risks due to aging and maintenance. tems reliability. This involved assessing annual
probabilities associated with natural hazards af-
1. PROJECT PHASES fecting the Canal, and the corresponding fragili-
Beginning in 2011, a systematic risk analysis ties of the infrastructure. Life cycle analyses
was undertaken to assess the state of natural risks were performed of maintenance repair and re-
facing the Canal. The project was divided into place strategies.
phases: Phase I focused on developing a basis for
1
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
2
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
that were not deserving of special attention but To make cross comparisons more reliable,
could be managed as part of normal operations semi-quantitative scales were developed for haz-
(green). ard probability (Table 1) and for consequence
A qualitative risk assessment was used to (Table 2). An attempt was made to anchor these
rank order the structures and components within semi-quantitative scales to events and outcomes
the portfolio. Development of qualitative risk as- that were intuitively familiar to ACP’s subject
sessment protocol required a number of working matter experts. In this qualitative phase, the
sessions to develop categories of hazards and an probabilities and costs in the risk register were
inventory of critical infrastructure in the ACP based on the judgment of the SME’s
portfolio. ACP utilized its own subject matter
experts (SMEs) in multidisciplinary teams to as- Table 1. Semi-quantitative scale of probability
sess likelihoods and consequence and the parti-
DESCRIPTION
PROBABILITY
COMPARISON
tion and ordering of the risk register. Small
land-‐
1
Very
likely
P>0.1
slide,
draft
restrictions
Structure Hazard Magnitude Component Comment Cause Pr Cost Rank
Landslides
Steel7 Debris7 P=0.1
to
2
Likely
without
Structure7 blockage,7 0.01
Madden7
Spillway
Floods PMF Drum7gates and7all7 undermain 4 3 0 controls
castings7 tenance7or7
P=0.01
to
La
Purisima
concrete repair 3
Unlikely
Impact7by7 0.001
2010
Flood
barge7or7 3 4 0
Large
lare7object
4
Very
unlikely
P<0.001
Previously7 earthquake
Conrete7 damaged7
4 4 0
piers form7other7
Concrete7
even
High7water7
Table 2. Semi-quantitative scale of consequence
main7section velocity
2 4 0
VERBAL
DESCRIPTION
EXAMPLE
OF
LOSS
Uplift7
Complete
Loss
of
navi-‐
forces,7
4 2 0 Loss
of
Gatun
or
Mad-‐
overload,7 1
gation
operations
for
cavitation den
Dam.
Overload 4 4 0
more
than
a
year
Impact7by7 More
than
$1b
loss
of
Roadway7
large7 4 4 0 Impede
operations
for
bridge toll
revenue.
Seriously
objects long
period
(>1
year)
or
2
compromise
reliability
Figure 2. Example section from the risk register, create
major
direct
or
of
important
compo-‐
showing risks for part of the Madden Dam spillway indirect
economic
cost
nents
section. Each row (specific risk) is characterized by
Impede
operations
for
More
than
$500m
loss
the name of the structure, type of the hazard, magni-
short
period
(<1
year)
of
toll
revenue.
Direct
tude of the hazard, component affected, and cause of 3
or
moderate
direct
or
repair
costs
greater
the adverse outcome. The probability and cost of indirect
economic
cost
than
$500m
each outcome are ranked from one to four, and an More
than
$100m
loss
overall risk ranking based on a risk matrix. Damages
that
affect
of
toll
revenue.
Direct
4
canal
capacity
and
rev-‐
repair
costs
greater
enues
In the qualitative phase of the risk analysis, than
$100m
simple ordinal scales or rankings were assigned Less
than
$100m
loss
of
to probabilities and consequences. That is, the Economic
damages
but
toll
revenue.
Direct
re-‐
probability of the hazard was ordinal-scaled from 5
canal
continues
to
op-‐ pair
costs
Less
than
one to four. The severity of consequence was or- erate
$100m.
No
impact
to
ACP
reputation
dinal-scaled from one to four. This provided a
starting point, but ordinal nature of the scales
3. QUANTITATIVE RISK
made cross comparisons within the register diffi-
The quantitative risk analysis was conducted us-
cult. So a semi-quantitative set of scales was
ing current hazard-vulnerability-consequence
needed.
3
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
methods similar to those adopted in the USACE tug erosion, and time-related deterioration. Mali-
Interagency Performance Evaluation Taskforce cious anthropogenic hazards are those caused by
study following Hurricane Katrina (IPET 2008) purposeful acts typically by agents external to
and the California Delta Risk Management Study the Canal operations. These include acts of ter-
(DRMS) of seismic and hydrological risk to the rorism but may also include acts by aggrieved
California Delta (URS/JBA 2007). personnel. The present study focused on natural
The approach separates the components of and operational hazards. Malicious anthropogen-
risk into three parts: Hazards, the natural or an- ic hazards were the subject of a separate, inde-
thropogenic threats posing potential loads on the pendent study sponsored by the ACP Protection
system; system response, fragility of the engi- Division.
neered system or its components to the loads
posed by the hazards; and consequences, the po-
tential outcomes in financial cost, mortality and
morbidity, environmental impacts, or other fac-
tors caused by adverse performance of the sys-
tem under hazard loads (Figure 3).
AEP Pf AEP
Vulnerabity
Hazard Consequences
(Fragility)
Assets
Figure 4. Seismic hazard curves for the New Atlantic
Figure 3. Hazard-vulnerability-consequence method Locks as PGA vs. AEP. The mean curve shown in
of natural hazard risk analysis, using seismic accel- red, median in green; also shown are the 5%, 15%,
eration (PGA) as an example. AEP=annual exceed- 85%, and 95% fractiles (URS 2008).
ance probability. Adapted from Grossi and Kunreu-
ther (2005). A typical probabilistic seismic hazard curve
is shown in Figure 4. Similar hazard curves were
4. HAZARDS developed for hydrological and meteorological
The hazards to which the Canal is exposed are hazards for each major component of the Canal
divided into three categories: Natural hazards, infrastructure.
operational and maintenance, and malicious an-
thropogenic hazards. Three natural hazards were 5. FRAGILITY
addressed: seismological, hydrological, and me- The performance of individual components was
teorological. A variety of others—hurricane, tsu- summarized in one of two ways: (1) As a fragili-
namis, tornedo, and sedimentation—were re- ty curve expressing the conditional probability of
viewed but none reached the catastrophic level. failure of the structure for various levels of haz-
Operational and maintenance hazards are ard loading, or (2) as a systems response curve
those that arise internal to the operations of the expressing the conditional probability of levels
Canal and those due to aging and maintenance. of an engineering performance indicator (e.g.,
These include navigation incidents, dredging and displacement, deformation, factor of safety).
4
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
The former is used when the modeling leads structural and geotechnical reliability methods of
to a discrete failure vs. no-failure outcome, while the sorts described in Ditlevsen (1996) or
the latter is used when the modeling leads to a Baecher and Christian (2003). Depending on the
gradient of possible severity of the outcome. In system and failure mode, these methods ranged
the former case the consequence of failure is a from simple Monte Carlo simulation to stochas-
fixed although perhaps uncertainty value, while tic finite element method. For example, Figure 5
in the latter case the consequence of failure is a shows Gatun Dam, spillway, and powerhouse.
variable dependent on the level of the perfor- Seismic forces were generated using a design
mance indicator (and possibly also uncertain). spectrum from a seismic report prepared by URS
(2008). For each site, response spectra were de-
veloped with different damping coefficients. Us-
ing Chopra’s simplified method (Tan and Chopra
1996), the lateral earthquake forces were esti-
mated from the earthquake design spectrum
(Figure 6). The effects of lake interaction and
water compressibility, dam-foundation rock in-
teraction, and the absorption of hydrodynamic
pressure waves were considered in the reservoir
bottom sediments and in the underlying founda-
tion rock.
6. EPISTEMIC UNCERTAINTY
Figure 5. Gatun Dam from the above, showing the
A logic tree approach provides a numerical way
spillway at center, Gatun Powerhouse center.
of handling parameter uncertainty and propagat-
ing its effects to uncertainties in (or confidence
bounds on) the output predictions. In the system
simulations, the epistemic uncertainties are gath-
ered into their own uncertainty tree—a so-called
logic tree—ahead of the simulation representing
aleatory uncertainties (Bommer and Scherbaum
2008).
The aleatory simulation is calculated condi-
tional on the value of the epistemic parameters
generated in the logic tree for hazard, fragility,
and consequence. These probabilities scan be
combined to yield probabilities of the end leaves
of the epistemic analysis .
Using the Monte Carlo method, the logic
tree approach decomposes the numerical model-
Figure 6. General forces diagram for Gatun Spill- ing into a two-step, nested process: (1) A simula-
way: (1) monolith, (2) pier, (3) water behind the tion is made of many values, N, of the epistemic
spillway gates, (4) gate, (5) lake, (6) soil in front of
uncertainties leading to a large number of reali-
monolith, (7) rock, (8) downstream, (9) key, (10) up-
lift.
zations, and (2) a set of M iterations of the HVC
model is made for each realization of the epis-
In either of these cases, the corresponding temic uncertainties simulated in step one (Figure
fragility or system response is analyzed using 7).
5
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
Proper9es(&
Parameters Aleatory Simulation
Loads(&(
Engineered(System
Disturbances
Performance
6
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
curve approaches is provided in Bedford and made to separate catastrophic from routine risks
Cooke (2001). at a cost of USD 10m. Similar results were gen-
Two envelopes are sketched in Figure 8. erated for each high-risk entry in the risk regis-
The first is an approximate upper bound for risks ter.
generally agreed to be acceptable for failure of
constructed facilities that threaten the general 8.2. Non-catastrophic risks
public. The second is an approximate upper The “acceptable risk” curve adopted for evaluat-
bound for risks appearing to be marginally ac- ing risk items apply only to catastrophic risks,
ceptable for failure of facilities that give no that is, major failures, not to routine accidents.
threat to the general public. These data are im- “Yellow” and “green” risks in the risk register
precise and incomplete. The envelopes are at are mostly of this latter type. These risks may
most first-order approximations. plot above the acceptable risk line and still be
F$N'Chart'Historical' Total'Cost' FN'Seismic' MC'Total'Cost' satisfactory. From comparison and presentation
1.E+00' purposes, routine risks are plotted in fN space
(i.e., the derivative of FN space) and compared
Annual&Exceedance&Probability&
1.E$02'
1.E$03'
Marginal
Probability, f Lines of
O&M risks Catastrophic risks
constant f*N
1.E$04'
'0.01'' '0.10'' '1.00'' '10.00'' '100.00'' '1,000.00''
Acceptable
Cost&(mUSD)&
Risk Curve
Figure 9. Slope failures in the Gaillard Cut. Dia-
monds are “routine failures” due to rainfall and ero-
sion. Crosses are a Poisson-lognormal approxima- Consequence, N
tion to historical failures. Triangles are the binned- Figure 10. f-N curve of less-than-catastrophic (yel-
approximation. Red squares are calculations of seis- low) risks. The constant f-N curves indicate how
mically induced failure probabilities due to ground much could be reasonably spent annually on reduc-
acceleration. ing the risks. These risk items can reasonably plot
above the “acceptable risk” curve as they are non-
Typical results for slope failures in the Gail- catastrophic.
lard Cut are shown in Figure 9. The low proba-
bility-high consequence risks to the right-hand 9. CONCLUSIONS
side are associated with large earthquakes on the An orderly Risk Management System (RMS) for
Pedro Miguel and Limon fault system. These are the Panama Canal infrastructure subjected to
catastrophic risk in that many km of slopes may physical hazards has been established over the
slide and the associated cost would be in the past five years, in compliance with the Canal’s
hundreds of millions of USD. 2010 “Integration Program for the Expanded Ca-
To the left-hand side are historical failures nal”.
due to rainfall and channel erosion. These are not The RMS integrates the various existing, but
catastrophic in that they occur nearly every year separate risk mitigation programs at the Panama
and are managed by observation and mainte- Canal, and benefits from the experience of each.
nance as mentioned above. The decision was
7
12th International Conference on Applications of Statistics and Probability in Civil Engineering, ICASP12
Vancouver, Canada, July 12-15, 2015
The RMS has the capability for integrating dif- Seismic Hazard Analysis.” Earthquake Spec-
ferent types of physical risks: catastrophic risks, tra, 24(4), 997–1009.
chronic risks and human risks. This segregation Chopra, A., and Tan, H. (1989). Simplified Earth-
relates to their respective mitigation strategies. quake Analysis of Gated Spillway Monoliths
of Concrete Gravity Dams. Report to
Catastrophic risks are mitigated through analysis,
USACE WES, University of California,
reinforcement, and mitigation before the hazard- Berkeley.
ous event. Chronic risks are mitigated by sys- Ditlevsen, O. (1996). Structural reliability methods.
tematic inspections and maintenance practices. Wiley, Chichester ; New York.
Human risks are managed by strategies imple- Grossi, P., and Kunreuther, H. (2005). Catastrophe
mented by the Canal Protection Division. Modeling: A New Approach to Managing
The risk analysis has demonstrated that the Risk. Springer.
dominant risks facing the Canal concern the HSE. (2001). Reducing Risks, Protecting People –
three large dams retaining Lake Gatun and its HSE’s Decision Making Process. UK Health
water supply (Gatun, Madden, and Miraflores and Safety Executive, London: HMSO.
Dams), and the Gaillard Cut slopes. For each of IPET. (2008). Performance Evaluation of the New
Orleans and Southeast Louisiana Hurricane
these, the hazard of greatest importance is seis-
Protection System, Final Report, v.8 – Engi-
mic. The risk analysis also indicated the need for neering and Operational Risk and Reliability
more advanced and detailed analysis of the struc- Analysis. Interagency Performance Evalua-
tural and geotechnical reliability of these struc- tion Taskforce, Washington, DC.
tures and components. Tan, H., and Chopra, A. (1996). “Dam-Foundation
The RMS enables an objective comparison Rock Interaction Effects in Earthquake Re-
of risks and a systematic comparison of costs and sponse of Arch Dams.” Journal of Structural
potential consequences, to develop a rational Engineering, 122(5), 528–538.
strategy for prioritizing capital investments relat- URS. (2008). ACP Geotechnical Services Contract
ed to risk mitigation. Task Orders 1 and 5: Seismic Design Crite-
The RMS permits continuous upgrading and ria for ACP Critical Structures. Autoridad
del Canal de Panamá, Balboa Heights, Pana-
maintaining so its relevance is maintained as the
ma.
Canal ages and changes. The output from this ef- URS/JBA. (2007). Delta Risk Management Strategy
fort is being directly incorporated into the ACP’s (DRMS) Phase 1 Risk Analysis Report. Pre-
overall Enterprise Risk Management Program. In pared by URS Corporation/Jack R. Benjamin
this way, physical risks are viewed in the same & Associates, Inc. for the California Depart-
light as other types of risks affecting the Organi- ment of Water Resources, Sacraemento.
zation. Whitman, R. V. (1984). “Evaluating the calculated
risk in geotechnical engineering.” Journal of
REFERENCES the Geotechnical Engineering Division,
Alfaro, L. D. (1988). The risk of landslides in Gail- ASCE, 110(2), 145–188.
lard Cut. Autoridad del Canal de Panamá,
Balboa Heights, Panama, 78.
Baecher, G., and Christian, J. (2003). Reliability and
Statistics in Geotechnical Engineering.
Wiley, Chichester, West Sussex, England ;
Hoboken, NJ.
Bedford, T., and Cooke, R. M. (2001). Probabilistic
risk analysis : foundations and methods.
Cambridge University Press, Cambridge,
UK ; New York, NY, USA.
Bommer, J. J., and Scherbaum, F. (2008). “The Use
and Misuse of Logic Trees in Probabilistic