Professional Documents
Culture Documents
Metal-deck corrosion:
Three case studies
A combination of factors was found to have contributed to major,
unpredictable patterns of deck corrosion
The roofing industry has exhibited Project No. 1 over an area used to charge batteries
a growing concern in recent months for lift trucks. The rusting was ex-
regarding corrosion of metal decks. The discovery of corrosion of the plained as being related to battery acid
Several recent articles in Professional metal deck was initially made on the fumes, a theory later invalidated. Origi-
Roofing ¹ and NRCA Bulletin 15-91 ² roof of Project No. 1 in 1985, about nally, both occurrences were rational-
have discussed a growing concern in three years after construction, when ized as localized anomalies and not a
the roofing community regarding corro- several new penetrations were cut in source of major concern.
sion of metal decks. During the last two the asphalt built-up roof (BUR). This
years the author's roof consulting firm exposed moderate-to-severe corrosion In 1989, six years after construction,
has investigated three projects that of the deck. This corrosion was initially pieces of decking began falling to the
have experienced severe, premature thought to be dormant and isolated to production floor in various areas of the
corrosion of metal roof decking. Two of active leaks. plant. There were numerous leaks doc-
the decks were primed but not painted, Two years later a small area of cor- umented in the plant with no logical
and one was galvanized (ASTM A 446 roded deck was replaced after rust was pattern. Maintenance personnel also
steel with hot dipped galvanized coat- observed on the bottom of the deck discovered several rather odd "sink
ing conforming to ASTM A 525, G-60).
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 1 of 10
TABLE A
Parameter Project No. 1 Project No. 2 Project No. 3
Project location Northwest South Carolina Coastal South Carolina Southeast Michigan
Insulation Type One layer phenolic One layer phenolic 1 layer wood fiber
2 layers phenolic
Number of layers 1 1 3
Deck Gauge 22 22 20
holes" on the roof. The owner was nearly every board joint appeared as a nolic insulation, which has been deter-
concerned and requested an investiga- white line indicating voids at insulation mined to be 23.4 percent (at 90 percent
tion by the author to determine what board joints. The same lines were visi- relative humidity and 68E F)³.
was happening to the roof system, ble on the roof on a frosty morning.
particularly the decking. Dry insulation extracted fromsome
Test cuts and cores confirmed the of the areas we had interpreted to be
The author's first task was to deter- observations of the IR survey. Areas of dry were found to contain as little as
mine the extent and severity of the phenolic insulation interpreted to be 1.6 percent MCBW.
corrosion. An infrared (IR) roof mois- wet were very wet. Moisture Content
ture survey indicated at least 6,000 By Weight (MCBW) was measured up The roof membrane had numerous
square feet 2, or 11 percent of the roof, to 1,025 percent. Most wet material was deficiencies, which had resulted in
had wet insulation with varying de- found to contain about 250 percent more than 100 documented leaks since
grees of moisture. The author also ob- MCBW. Compare these values with the occupancy. The author also found
served on an IR camera screen that equilibrium moisture content for phe- evidence from the test cuts that the
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 2 of 10
joints in the phenolic foam had been
butted, or up to ¼ inches wide, at the
time of construction. They were now
up to 1½ inches wide with an average
width of 1 inch. *[W E ESTIMATED THE
TOTAL CUMULATIVE AREA WHERE THERE
IS NO INSULATION DUE TO OPEN BOARD
JOINTS WAS 2,465 FT 2. THIS MEANT
THAT ABOUT 5% OF THE INSULATED
ROOF AREA WAS NOT INSULATED!]*
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 3 of 10
tion of the underside of the deck and Project No. 2
test-cut data, the author projected that Phenolic insulation with a fiber-
13 percent of the roof deck would have On September 22, 1989, South glass facer was in contact with the
to be removed and replaced. Further, Carolina was visited by a very unpleas- deck. In many locations, the facer had
the author estimated that about 30 ant Hurricane Hugo. The roof on this become firmly adhered to the corroded
percent of the deck would be lightly to project, which is located near the coast, deck. When the insulation was
moderately corroded and would require was exposed to some of Hugo's higher removed, the deck came up with it in
field coating. winds. The ballasted EPDM roof bil- strips the width of the flange. The as-
lowed and was ripped in several places. sociation of the fiberglass as a reactant
The physical condition of the insu- The owner arranged for emergency in the corrosion process has not been
lation and the extent of corrosion, how- repairs soon after the hurricane. During fully investigated, but is currently not
ever, led the author to recommend a final repairs three months later, exten- felt by the author to be significant.
total removal of the roof system to the sive corrosion of the primed deck was
deck. It would then be necessary to observed. After 1,710 square feet of The author examined the EPDM
replace seriously deteriorated deck and steel deck had been replaced, with more membrane for evidence of factory defi-
to coat moderately corroded deck with replacement anticipated, the author was ciencies or deficient field seams or
a high-solids epoxy coating system. requested to review the situation and flashings. No serious problems were
After this preparation, a new roof sys- provide recommendations. found that could explain the extent of
tem would be installed. observed corrosion.
The author extracted numerous test
During the demolition the author cuts from the roof to observe the deck- The owner reported that prior to
found the IR and interior survey tech- ing: several were taken in storm-dam- Hugo, he had only one persistent leak
niques assisted in predicting areas of aged wet areas; most were in areas not in the store. There was nothing in the
corrosion in some areas but were of known to have been damaged during history of the roof to indicate that the
little value in most others. Although Hugo. deck was rusting except for some or-
the process gave the author an indica- ange stains observed on the end walls
tion of the problem and assisted in The results were of great concern. immediately after Hugo. Despite the
developing a basic magnitude of the Out of nine test cuts, eight had disappointing results on Project No. 1
extent of the corrosion, it was not as moderate-to-full penetration rusting of with non-destructive testing to locate
dependable as he would have hoped.
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 4 of 10
IR camera and capacitance meter. The observe the installation of the new The author concluded there were
moisture readings from a nuclear gauge roof. A total of 14,900 square feet, or four "sources" of the water that en-
were questionable, because the author 17 percent of the roof deck, was re- tered the system and initiated the
got low readings on all test-cut loca- placed and 52,094 square feet or 60 corrosion. In order of significance they
tions except one where the insulation percent, was coated with epoxy. Prior are:
was found to contain 1,980 percent to coating, the deck was carefully pre-
MCBW. Here the nuclear count was 19, pared. The use of epoxy requires appli- ! Condensation on the bottom of the
which is not a high reading for 2 inches cators who are trained in the proper membrane.
of insulation that was found to be techniques for this type of coating.
soaking wet. ! Condensation near the deck-to-insu-
The demolition daily exposed ran- lation interface.
In other test cuts where rust was dom, and extensive, corrosion of the
observed, the foam was found to con- decking that the author would not have ! Condensation at insulation joints.
tain only 3.8 percent to 11.4 percent known about if the roof system had not
MCBW and nuclear counts were all remo ved. To have followed a course ! Leaks prior to Hugo.
only four. Therefore, for ballasted other than total removal of the roof
EPDM, non-destructive testing was system would have been a very seri- ! Leaks
~ from Hugo damage.
concluded to be of little to no value in ous mistake. Total removal is required
correlating wet insulation to areas of to assure all corroded deck is removed. It was observed by the author that
rusted deck. the corrosion was more severe at damp
During the course of the retrofit, areas compared to very wet areas. The
Visually surveying the bottom side the author made several observations. acidity of the insulation was tested in
of the deck was misleading too, be- different locations using a pH meter,
cause only about 5 percent of the deck The foam was heavily damaged and was found to range from 4.3 pH in
exhibited visible pitting. In these areas, from compression failure. The author the very wet insulation to a highly
the moisture contents were found to be believes most of this occurred during acidic 1.6 pH in the damp insulation.
about 1,980 percent. the placement of the ballast. Obvi- (The pH scale is from 0-14, with 0 being
ously, there was also some damage acidic, 7 being neutral and 14 being
An orange stain was visible at nu- done during the repairs. The insulation caustic.)
merous flute lines at end laps in the did not display any instability prob-
deck and the exterior end walls. This lems; i.e., there was no shrinkage. This finding initially seems contrary
orange stain was found to be rust that There were some areas where perlite to logic, until you consider that the
had been carried to the flutes of the was in contact with the deck adjacent concentration of an acid is diluted as
deck and flowed in the building after to phenolic foam in these locations. In more water is added to it, and thus its
Hugo. The staining was not found to these locations there was no rust under pH is closer to neutral. Therefore,
be a reliable indicator of rusted deck- the perlite but there was severe rust acidity can be affected by the quantity
ing. only inches away under the phenolic. of water present, but perhaps not in
*[ W E ALSO NOTICE LESS CORROSION ways you might expect.
The author saw no option but to UNDER LOCATIONS WHERE TAPERED EDGE
recommend again complete removal of STRIPS WERE INSTALLED OVER THE PHE- PROJECT NO. 3
the roof system to the deck, for two NOLIC FOAM. IN THESE CASES , CORRO-
reasons:We had to visually inspect the SION STARTED AT THE TOE OF THE TA- The author was recently requested
top surface of the deck for rust, and we PERED EDGE STRIP . to consult on a third project that exhib-
were concerned that the continued ited corrosion of the metal deck. This
presence of wet insulation could pose IN ASSESSING THE SOURCE OF THE roof was about four years old and the
potential future corrosion problems. EXTENSIVE CORROSION ON THIS PROJECT deck had a G-60 galvanized coating.
WE AGAIN CONCLUDED THE PHENOLIC The insulation consisted of two layers
During the demolition, there was a FOAM WAS THE CULPRIT . THE BASIC of 1-inch phenolic foam covered by
full-time observer on site to collect EQUATION FOR CORROSION WAS : half-inch wood-fiber board. As shown
samples, to log and map the demol- PHENOLIC FOAM + WATER = in Table C, the membrane was a CSPE
ished areas, to take photographs and to CORROSION ]* mechanically attached system.
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 5 of 10
Leaks were reported soon after half of the board and 33 percent the top flange and was attacking the
occupancy. There were numerous defi- MCBW in the lower half. The top layer base metal. No full-penetration rust
ciencies in the installation of the mem- of the phenolic contained 9.4 percent was observed. *[THE CORROSION OF
brane. The persistence of the leakage MCBW and the bottom layer 6.9 per- THE GALVANIZED COATED DECKING WAS
led to initiating a partial replacement cent MCBW. The author believes this PREDICTED FROM RESEARCH GATHERED
program with the boundaries for re- stratification of moisture is significant, ON PROJECT NO . 1, BUT NOW IT WAS
placement based in large part on the as it indicates moisture accumulation CONFIRMED.]* Although the corrosion
results of an IR survey. As the replace- related to the drive of moisture from an was not as severe as on Project 2 (both
were the same vintage foam) there was
a basis for serious concern.
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 6 of 10
Metal Decks: More than a place to hang your roof
On each of the projects described in the accompanying designed to transfer wind loads (shear loads) through a
article, the metal deck was designed as more than just a diaphragm, the wind load is transferred from the windward
platform for the roof. The deck in such a design serves wall to the roof deck and out to the walls parallel to the
three primary functions: wind direction.
! Supporting vertical dead and live loads. This transfer is accomplished by attaching the deck to the
structural supports (joists or beams) with welds or screws.
! Providing a wind uplift resistance component. If the decking has either rusted away from the fasteners or
has corroded to the point it is no longer a monolithic plate
! Providing resistance to lateral (sideways) wind loads capable of distributing loads (a diaphragm), the structure
striking the building. This is referred to as diaphragm could receive extensive damage or possibly rack or
action. collapse during a wind that is within the structure's design
load, or even less.
When a steel roof deck is seriously corroded, its capacity
to resist these loads is compromised. The deck may no Note: The assessment of loss of structural integrity
longer be capable of supporting snow loads, the dead should be made by a structural engineer who is knowl-
load of the roof system, foot traffic, etc. The wind resis- edgeable regarding deck corrosion and its effects.
tance for an adhered system and a mechanically attached
system are provide by screwing the insulation or mem- As a critical component of such structures, metal roof
brane to the metal deck. decks are anticipated in the design to serve the life of the
building - which in most cases is 50, 75, or even 100 years.
If, for example, 50 percent of the deck has turned to A building owner may expect to have to replace localized
*[CRUSTED]* rust, the uplift resistance of its attachment to areas of rusted deck when he replaces his roof, but should
joists or beams - and the pull-out resistance of insulation not expect to replace his entire roof deck, or large portions
fasteners - is reduced proportionately to the reduction of of it when doing so.
metal thickness. When wind strikes a building that was
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 7 of 10
erated corrosion indefinitely, the salts OF THE ROOF ON PROJECT NO. 1 WHICH COMPOSITION OF PHENOLIC FOAM (NOT
produced during the initial corrosion WAS EIGHT YEARS OLD AT REPLACEMENT THE FACERS OR AN INCREASE IN THE
process will remain within the corro- AND ON PROJECT NO. 2 WHICH WAS TWO COMPRESSIVE STRENGTH), WE HAVE NO
sion product (rust), rendering its con- YEARS OLD, THE ACTUAL CORROSION ASSURANCE THAT THE PRESENCE OF
ductivity high. Thus, continued high RATE WAS 3.5 TO 14 MILS PER YEAR PHENOLIC FOAM ON A PRIMED OR GAL-
corrosion rates occur in the presence of (0.0295" ÷ 8 YEARS = 3.6 MILS PER YEAR VANIZED DECK WILL NOT CORRODE THE
moisture trapped in the foam and atmo- AND 0.0295" ÷ 2 YEARS = 15 MILS PER DECK.]*
spheric oxygen. The sulfonic acids YEAR ). THIS IS HARDLY AN ACCEPTABLE
released by moisture from the phenolic CONDITION.]* The author believes that his inves-
foam therefore act as both an initiator tigation on these projects has raised
of corrosion and as a catalyst for fur- Recommendations certain points that require further
ther corrosion." study and discussion within the roof-
What can be done to avoid or mini- ing industry.
Regarding the use of galvanized mize deck corrosion under the condi-
decking, Slater's report states: tions described in these case studies? First, more designers and contrac-
The author suggests these as possible tors should be aware that phenolic
"It has been suggested that galva- preventative steps: foam insulation is vapor-permeable
nized decking is more resistant to at- and therefore capable of absorbing
mospheric corrosion and hence more *[! ISOLATE PHENOLIC FOAM FROM water. This has ramifications relative
resistant to the type of attack found on METAL DECK WITH A SEPARATOR to: material storage (that is, stored in a
the (investigated) roof. The corrosion BOARD place with low humidity); possible in-
rate test data clearly indicate that the clusion of a vapor retarder in situa-
galvanizing cannot be relied upon to ! INSTALL A " PERFECT " ROOF THAT tions not normally requiring one; ap-
protect against the sulfonic acid attack. HAS NOT NOR WILL LEAK DURING ITS plication of this insulation during hot,
Furthermore, the sulfonates can be LIFE (NOT A PRACTICAL humid weather, and design consider-
anticipated to catalyze atmospheric EXPECTATION)]* ations due to the additional weight of
corrosion of the galvanized layer which absorbed moisture.
remains after the initial acid attack, in ! Use epoxy coating or equivalent
the same way as for the ungalvanized applied to prime-coated metal The industry also needs a better
steel. *[THUS GALVANIZING IS NOT CON- deck. method to determine the absorption
SIDERED TO BE THE PROTECTIVE COAT - potential of phenolic insulation.
ING OF CHOICE IN THIS APPLICATION.]*" ! Use G-90 galvanize coating, not G- ASTM C1126 is the "Standard Specifi-
*[TESTS WHICH WERE CONDUCTED 60, for longer resistance to corro- cation for Faced or Unfaced Rigid Cel-
AND REPORTED BY A PHENOLIC FOAM sion. lular Phenolic Thermal Insulation."
MANUFACTURER STATED THE FOLLOW - This standard refers to ASTM C209,
ING: *[! H A V E THE INSULATION which includes a moisture absorption
MANUFACTURER WARRANT DAM- test. This test does not adequately
"UNDER THE MOST SEVERE POSSIBLE AGE TO DECK FROM CORROSION model the conditions to which a roof
TEST EXPOSURES , I.E. UNPROTECTED FOR "X" YEARS insulation will be exposed. The test
STEEL, ACCELERATED TEST CONDITIONS , measures the percentage water ab-
AND CONTINUOUSLY WET ( PHENOLIC ! USE A ROOF SYSTEM THAT IS EASY sorption increase by volume with a
FOAM) INSULATION, MEASURED CORRO- TO VISUALLY INSPECT FOR PHYSI- two-hour immersion. For one manu-
SION RATES WERE BELOW 2 (1.8) MILS CAL DAMAGE facturer, this was 2.0 percent by
PER YEAR AFTER 200 DAYS ......" volume. With a density of the foam of
! USE STAINLESS STEEL SCREWS 2.7 pounds per cubic foot that is 46
THE THICKNESS OF 22 GAUGE PRIMED percent MCBW. Further, immersion
METAL DECKING IS ABOUT 0.0295" ! CONSIDER USING ANOTHER INSULA- does not model a vapor drive to which
THICK. IF WE CAN EXPECT CORROSION TO TION in-service insulation is exposed. *[THE
REMOVE 2 MILS (0.002") PER YEAR , THE INDUSTRY NEEDS A BETTER TEST.]*
ANTICIPATED DECK LIFE WILL BE ONLY 15 UNLESS THERE HAS BEEN OR WILL
YEARS ! BASED ON OUR OBSERVATIONS BE A MAJOR CHANGE IN THE CHEMICAL *[This leads us then to a second
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 8 of 10
point. The industry must acknowledge try needs to know what the deck MCBW.) NEXT REMOVE THE FOAM
that phenolic foam is not "closed-cell" manufactures can and will provide to FROM THE CONTAINER. PLACE A FEW
relative t o moisture. When the prod- the end user. *[THE STEEL DECK INSTI- SMALL STRIPS OF METAL DECKING IN
uct can absorb 46% in two hours and TUTE RECOMMENDS FIELD PAINTING THE THE SOAK WATER AND MONITOR FOR A
ultimately nearly 2,000% MCBW, it DECK BECAUSE THEY SAY THE FACTORY WEEK OR SO. WE OBSERVED RUST ON
ain't closed-cell! This is important dur- PRIMER IS " AN IMPERMANENT AND THE EXPOSED CUT EDGES OF THE STRIPS
ing the design stage. Structural engi- PROVISIONAL COATING." W OULD IT BE IN ABOUT 48 HOURS. W HEN WE
neers base their designs and size POSSIBLE OR PRACTICAL FOR THE MET - CHECKED THE PH AFTER THE METAL
structural members on the assumption AL DECK SUPPLIER TO FURNISH A PRE- HAD BEEN IN THE SOLUTION FOR A
that the insulation is dry and will re- PAINTED PRODUCT WITH MORE THAN A WEEK, WE FOUND THE PH HAD RISEN
main dry, not that someday itweigh
may 20 " PROVISIONAL COATING"? IF NOT , THEN DUE TO THE CHEMICAL REACTION TAK-
times more than they were told it THE CHOICES ARE: A G-90 GALVANIZED ING PACE IN THE CORROSION PROCESS.
would. Mechanical engineers base COATING; AN ALUMINUM ZINC ALLOY
their heating and cooling loads on dry COATING; A FIELD APPLIED PAINT OR M ORE SOPHISTICATED TESTS CAN
material with a stated "R" value, not a COATING; OR CHANGING TO ANOTHER BE RUN BUT WE HAVE FOUND THESE
depreciated, lower value as a result of DECKING SYSTEM. SIMPLE TESTS ARE QUITE INFORMATIVE.
moisture absorption. These are impor- YOU MAY WANT TO RUN SIMILAR TEST
tant liabilities that must considered.]* WHAT CAN YOU DO? ON OTHER INSULATIONS FOR YOUR
INFORMATION.
In addition, the matter of positive DURING OUR INVESTIGATIONS WE
pressure from an HVAC system billow- HAVE CONDUCTED A SIMPLE TEST TO FOR THOSE WHO HAVE IN -PLACE
ing a single-ply membrane is a situa- MONITOR PHENOLIC FOAM CORROSION PHENOLIC FOAM, IT MAY BE PRUDENT TO
tion that is not receiving adequate PROPERTIES AND MOISTURE ABSORP- DETERMINE IF A PROBLEM CURRENTLY
attention from manufactures, design- TION. YOU MAY WANT TO PERFORM EXISTS AND THEN RECHECK OCCASION-
ers, or contractors. The requirement YOUR OWN TESTS TO SEE WHAT HAP - ALLY. TAKE A FEW EXPLORATORY TEST
for roof pressure relief valves, air re- PENS WHEN A 2" CUBE OF DRY PHENOLIC CUTS AND SEE IF THERE IS A PROBLEM.
tarders or fully adhered systems needs FOAM IS PLACED IN ABOUT 150 ML OF ON OUR PROJECT NO. 1, 35% OF THE
further study and consideration in the DISTILLED WATER . EVERY 24 HOUR PE- DECK HAD TO BE EITHER REPLACED OR
design process. With the exception of RIOD MEASURE THE PH WITH INDICATOR COATED AFTER ONLY EIGHT YEARS. ON
only a few manufacturers, air infiltra- PAPER OR A P H METER . A LSO PROJECT NO. 2, 77% HAD TO BE RE-
tion remains a non-issue. ACCURATELY WEIGH THE SAMPLES . W E PLACED OR COATED AFTER ONLY TWO
FOUND THE PH DROPPED FROM 6.6 TO YEAR S . TIME MAY BE YOUR ENEMY IF
Regardless of the type of insula- 3.3 IN ONLY 48 HOURS. THE MCBW IN- THE DECK IS CORRODING. DAMAGE MAY
tion to be used, there needs to be a CREASED TO OVER 200% IN THE SAME BE MINIMIZED IF CAUGHT EARLY
thorough, industry wide review of TIME PERIOD. (THAT IS FIVE TIMES THE ENOUGH.]*
metal decks and corrosion. The indus- TWO-HOUR IMMERSION VALUE OF 47%
BY THE TIME RUST IS OBSERVED ON THE BOTTOM SIDE OF THE DECK IT IS TOO LATE. THE CORROSION
HAS PROGRESSED TO A POINT OF COMPONENT FAILURE.
* READER NOTE: The text enclosed by asterisks and brackets *[ IN SMALL CAPS ]* was in the author’s original manu-
script, but omitted in the published article by the Editor.
References
1. Professional Roofing: March 1991, NRCA News, Page 63, Tech Transfer, Page 74; April 1991, Tech Transfer, Page 86.
2. "Corrosion Protection For New Steel Roof Decks," NRCA Bulletin 15-91, May 1991.
3. Cash, C. G., "Moisture and Built-Up Roofing," Proceedings of the Second International Symposium on Roofing Tech-
nology, NRCA, 1985, Pages 416-427.
About the Author: Richard P. Canon, a Registered Roof Consultant (RRC) and Professional Engineer (PE), is owner of Canon
Consulting & Engineering Co.,Inc. 1617 John B. White Sr., Blvd., P. O. Box 17007, Spartanburg, SC 29301-0101, (864) 574-6500.
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 9 of 10
ADDITIONAL PHOTOGRAPHS OF MISCELLANEOUS PROJECTS
Figure 5: Project 1, view of wet insulation. Figure 6: Project 1 interior view of corrosion
Professional Roofing (Reprinted with Permission. See Note to Reader at end of Article) August 1992
Compliments of Canon Consulting & Engineering Co., Inc.
Spartanburg, South Carolina
(864) 574-6500 Page 10 of 10