aarvee associates
architects engineers & consultants pvt. Itd,
Letter No.: AA/HW/NHAI/Narmada/1681/17-18/1726
Date: 05" March, 2018
To,
‘The Project Manager,
L&T 3° Narmada Bridge Project site,
Zadeswar Chowkdi, NH-8, Toll Plaza Complex,
Bharuch (Gujarat) ~ 392 011
‘Sub: Six laning of Km 192.00 to Km 198.00 between Vadodara-Surat section of NH-8 including
construction of a new four lane Extra Dosed across river Narmada in the State of Gujarat
‘on EPC mode-Reg: Provisional Certificate - Issued
1. NHAI letter No. NHAI/PIU-Surat(Expressway)/Narmada-7 1/2018/1079, dated 01.03.2018
2. Our Letter No. AA/HW/NHAI/Narmada/1681/17-18/1184, dated 28.11.2017
3. Contractor’ letter no. L&T-HCIC-Narmada-17-01-169, dated 15.09.17
Dear Sir,
AAs per provisions of Clause 12.2 of EPC Agreement, we are pleased to issue the ‘Provisional
Certificate’ for the above Project w.e.. 27.10.2017, along with the jointly signed "Punch List’, Part I
containing works to be completed within 30 days from the effective date of Provisional Certificate,
Part ~ II containing works that could not be completed due to hindrance / resistance from local
public to be completed as and when the front is made available,
We wish you all the best.
With best regards,
For Aatvee Associa
5 JaSwant Kumar ‘a
Authorized Signatory
Encl: As above.
Copy to:
The Chief General Manager (Tech) & RO, NHAI, Gandhinagar
2. The General Manager (Tech), Gujarat, NHAI, New Delhi
3. Project Director, PIU ~ Surat
4, Team Leader, Aarvee Associates in JV with NICE Pvt Ltd.
Hyderabad - 500 089, India
nail: aarvee@aarvee.net; web: www.aarvee.com
74200G2005°1C045491
Ravula Residency, Srin
Tel: +91-40-93737633,48483456; Fox: +9
cn
ar Colony Main‘ix Laning of km. 192.000 to km. 198,000 between Vadodara ~ Surat section of NH-8 including construction of a new four lane Extra Dosed
Bridge across river Nacmada inthe State of Gujarat on Engineering Procurement and Construction (EPC) contract mode
[ - PUNCH UST (as on 27102017)
Chanage
[Sno | Description of work ‘From to Side Remarks
‘Part-|: LIST OF WORKS TO BE COMPLETED WITHIN 30 DAYS OF PROVISIONAL CERTIFICATE
1924000 | 192+800
i MBCB in Median Median | Yet to be started for a a length of 160m
1974660 | 1984540
2 | Garage near Admin building
(Toll Paza)
1 overhead gantry before start of the Project i to
3 Sign Boards org tat
1964447 RHS
| 196+500 RHS
4 Chute drains Sane ane Rectification of damaged portion
197+660, LHS
5 Shoulder Kerb & MBCE ETOH sos.s09 | 196,000 | BHS Work in progress
6 | Pipe and Box Culvert aprons | 194+700 cw
7 | Paver block at toll plaza Toll plaza
x-ll: LIST OF WORKS WHICH COULD NOT BE COMPLETED DUE TO HINDRANCES AND TO BE COMPLETED AS AND WHEN
THE SAME IS MADE AVAILABLE
1 | Guidebundonatside [Riverbank | AL CWPRS report anated
[2 | Boundary fencing [Along the Project Highway |
3 | Eneuyatsipatonchanber | AFiéhembentmes Workin progress test stiles rom cal
4 tensa drain Along the Projet hay
[5 | Footpatneumarain | 1924405 | 1924900 | tHS | Yettobe started objection fom locas)
raoPROVISIONAL CERTIFICATE
We, M/s Aarvee Associates Architects Engineers & Consultants Pvt. Ltd., acting as Authority's
Engineer, under and in accordance with the Agreement dated 25.02.2014 (the
“Agreement’), for “construction of Vadodara - Surat section (Km 192,000 to Km 198.000)
of National Highway No. 8 (the “Project Highway”) on Engineering, Procurement and
‘Construction (EPC) baiss through M/s Larsen & Toubro Limited having its registered office at
L&T House, N.M.Marg, Ballard Estate, Mumbai 400 001, hereby certify that, the Tests in
accordance with Article 12 of the Agreement have been undertaken to determine compliance
of the Project Highway with the provisions of the Agreement and are found to be in order.
Works that are incomplete on account of Time Extension have been specified in the Punch
List appended hereto, and the Contractor has agreed and accepted that it shall complete all
such works in the time and manner set forth in the Agreement. In addition, certain minor
works are incomplete and these are not likely to cause material inconvenience to the Users
of the Project Highway or affect their safety. The Contractor has agreed and accepted that
as a condition of this Provisional Certificate it shall complete such minor works within 30
(thirty) days hereof. These minor works have also been specified in the aforesaid Punch List.
In view of the foregoing, we are satisfied that the Project Highway from Km 192,000 to Km,
198.000 can be safely and reliably placed in service of the Users thereof, and in terms of the
‘Agreement, the Project Highway is hereby provisionally declared fit for entry into operation
wef 27" day of October, 2017.
ACCEPTED, SIGNED, SEALED SIGNED, SEALED AND
‘AND DELIVERED DELIVERED
For and on behalf of For and on behalf of
opRACTER by AUTHORITY'S ENGINEER by
(Signature) (Signature) _
Authorized Signatory
Larsen & Toubro Limited, Authorized Signatory a>
Aarvee Associates Architects En &
Consultants Pvt. Ltd., in JV with Nag
Infrastructure Consulting Engineers Pvt, Ltd.
8-2-5, Ravula Residency,
Srinagar Colony Main Road,
Hyderabad.