Professional Documents
Culture Documents
Approved by the
American National
Standards Institute
August 21, 2013
IIAR 7
Metric Policy
The IIAR metric policy for ANSI standards, bulletins and all IIAR publications is to use the common
engineering “inch-pound” (IP) unit system as the primary unit of measure, and the International System of
Units (SI), as defined in United States National Institute of Standards and Technology Special Publication
330 “The International System of Units,” for secondary units.
Normative/Informative Elements
This standard includes both Normative (required) and Informative (advisory) language. The bodies of the
standard and labeled appendices are Normative. The forward, notes, and any appendices labeled Informative are
non-mandatory. Informative material shall never be regarded as a requirement.
Notice
The information contained in this Standard has been obtained from sources believed to be reliable. However,
it should not be assumed that all acceptable methods or procedures are contained in this document, or that
additional measures may not be required under certain circumstances or conditions. The Standards Committee
and Consensus Body that approved the Standard were balanced to assure that individuals from competent and
concerned interests have had an opportunity to participate. The proposed Standard was made available for review
and comment for additional input from industry, academia, regulatory agencies and others.
The IIAR makes no warranty or representation and assumes no liability or responsibility in connection with the
use of any information contained in this document. Use of and reference to this document by private industry,
government agencies and others is intended to be voluntary and not binding unless and until its use is mandated
by authorities having jurisdiction.
The IIAR does not “approve” or “endorse” any products, services or methods. This document should not be used
or referenced in any way which would imply such approval or endorsement.
Note that the various codes and regulations referenced in this document may be amended from time to time and it
should be assumed that the versions referenced herein are the versions of such codes and regulations in effect at
the time of the publication of this Standard.
The IIAR uses its best efforts to promulgate Standards for the benefit of the public in light of available
information and accepted industry practices. However, the IIAR does not guarantee, certify, or assume the safety
or performance of any products, components or systems tested, installed, or operated in accordance with IIAR’s
Standards or that any tests conducted under its Standards will be nonhazardous or free from risk.
This Standard is subject to periodic review. Up-to-date information about the status of the Standard may be
received by contacting IIAR.
Copyright
This document may not, in whole or in part, be reproduced, copied or disseminated, entered into or stored in a
computer database or retrieval system, or otherwise utilized without the prior written consent of the IIAR.
FOREWORD (Informative)
The purpose of this standard is to define the minimum requirements for developing operating procedures for
closed-circuit ammonia mechanical refrigerating systems. The document reflects the consensus reached by
ammonia refrigeration industry representatives on how to develop operating procedures.
Since this document defines the minimum requirements for operating procedures it may not be sufficient to
meet other standards and/or regulations that are applicable to each specific refrigerating system. Additional
requirements may be necessary to comply with these standards and/or regulations. The International Institute of
Ammonia Refrigeration’s (IIAR’s) Process Safety Management Guidelines for Ammonia Refrigeration and the
IIAR’s Risk Management Program Guidelines for Ammonia Refrigeration address the additional requirements
needed to meet United States regulations. Note that this standard does not constitute a comprehensive detailed
technical design manual and should not be used as such.
This is a new Standard intended to replace the operations information contained in IIAR Bulletin #110,
Guidelines for Start-Up, Inspection, and Maintenance of Ammonia Mechanical Refrigerating Systems, and
to supplement existing refrigeration standards and publications issued by other organizations such as ASHRAE,
ASME and ANSI.
At the time of publication of this standard, the IIAR Standards Committee had the following members:
Robert J. Czarnecki, Chair — Campbell Soup Company
Don Faust, Vice Chair — Gartner Refrigeration & Mfg., Inc.
Eric Brown — ALTA Refrigeration, Inc.
Dennis R. Carroll — Johnson Controls
Trevor Hegg — EVAPCO, Inc.
Eric Johnston — ConAgra Foods
Gregory P. Klidonas — GEA Refrigeration North America, Inc.
Thomas A. Leighty — Refrigeration Systems Company
Brian Marriott — Marriott & Associates
Rich Merrill — Retired, EVAPCO, Inc.
Ron Worley — Nestlé USA
Dave Schaefer — Bassett Mechanical
Joseph Pillis – Johnson Controls
Peter Jordan – MBD Risk Management Services, Inc.
The task group working on this standard had the following members at the time of publication:
Robert Czarnecki — Campbell Soup Company
Peter Jordan — MBD Risk Management Services, Inc.
James Marrella — United States Cold Storage, Inc.
Godan Nambudiripad — Retired, General Mills
John Landis — Pepperidge Farm, Inc.
Jack Piho — Piho Engineering
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. i
TABLE OF CONTENTS
SECTION 1: PURPOSE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
SECTION 2: SCOPE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
SECTION 3: DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
SECTION 4: REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
SECTION 6: EQUIPMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
6.2 Compressors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
6.3 Condensers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6.4 Evaporators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. iii
SECTION 7: SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
SECTION 8: TASKS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
SECTION 9: (INFORMATIVE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
SOURCES OF REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
APPENDIX A (INFORMATIVE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
APPENDIX C (INFORMATIVE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
APPENDIX D (INFORMATIVE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
iv Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
SECTION 1
PURPOSE
1.1 The purpose of this standard is to define the a. Easy to Understand and Follow
minimum requirements for developing operating b. Safe
procedures for closed-circuit ammonia mechanical c. Effective
refrigerating systems. These operating procedures d. Reliable
shall be developed with the following primary goals e. Meeting Applicable Regulatory Requirements
in mind:
SECTION 2
SCOPE
2.1 This document presupposes that the persons 2.3 This document does not address the
who use it have a working knowledge of the commissioning of ammonia refrigerating systems
functionality of their ammonia refrigerating system(s) or system components. Refer to IIAR5 Start-up
and basic ammonia refrigerating practices and and Commissioning of Closed-Circuit Ammonia
principles. This standard is intended for those who Mechanical Refrigerating Systems for the criteria
develop, define, and/or review operating procedures and procedures to start-up and commission
for ammonia refrigerating systems. systems or system components.
SECTION 3
DEFINITIONS
For other definitions refer to IIAR 2 Equipment, public; and/or components of the refrigerating system;
Design, and Installation of Closed-Circuit Ammonia and/or product.
Mechanical Refrigerating Systems or IIAR 1
Definitions and Terminology whichever is the later Emergency shutdown procedures: Procedures which
document. describe the deliberate and immediate shutdown of
the system or a component in the system due to an
Emergency operating procedures: Procedures for unplanned critical circumstance.
operating the system under abnormal, unintended,
or time sensitive conditions. These abnormal or Initial start-up procedures: Procedures which
time-sensitive conditions may involve risk to the describe the steps needed to verify the condition
health and welfare of operators, employees, and the of the equipment and the steps to start the system
or a component in the system safely under normal
conditions.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 1
Normal operations procedures: Procedures which abnormal shutdown conditions or a turnaround such
describe the steps needed to verify the condition of the as power failures or emergency shutdowns. Start-up
equipment and the steps to start and run the system following an emergency or major change may require
or a component in the system safely under normal more inspections to verify that valves are in their
conditions. appropriate positions and all equipment is functioning
properly.
Normal shutdown procedures: Procedures which
describe the steps needed to stop the system or Temporary operating procedures: Procedures which
a component in the system safely under normal describe the deliberate and planned operation of a
conditions. piece of equipment at conditions outside of its normal
operating conditions, but within its upper and lower
Start-up procedures following a turnaround, safe operating limits, including any specific steps that
or after an emergency shutdown: Procedures which must be taken so that there are no safety ramifications.
describe the steps needed to verify the condition Typically, temporary operating procedures are of a
of the equipment and the steps to start the system limited duration.
or a component of the system safely following
SECTION 4
REFERENCES
2 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
4.2 Informative References 4.2.1.3 IIAR Ammonia Refrigeration
Management (ARM) Program.
4.2.1 International Institute of Ammonia
Refrigeration (IIAR): 4.2.1.4 IIAR Introduction to Ammonia
Refrigeration.
4.2.1.1 IIAR Bulletin 114, Guidelines for
Identification of Ammonia Refrigeration 4.2.2 Cascade Energy Engineers (with
Piping and System Components, 1991. distribution support from Northwest Food
Processors Association (NWFPA)), Industrial
4.2.1.2 IIAR Process Safety Management Refrigeration Best Practices Guide.
Guidelines for Ammonia Refrigeration, 2nd
Edition. 4.2.3 Refrigerating Engineers & Technicians
Association (RETA), Industrial Refrigeration
Course IV, Plant Operations & Safety.
SECTION 5
DEVELOPING AND MAINTAINING OPERATING
PROCEDURES
Operation procedures shall describe the appropriate Operating procedures shall comply with regulatory
personal protective equipment (PPE) that shall requirements. In the United States all facilities are
be worn when performing work on the ammonia subject to EPA’s General Duty Clause requirements
refrigerating system. The operating procedures shall (Section 112(r)(l) of the Clean Air Act) and to
also indicate when the buddy system shall be practiced the General Duty Clause in section 5(a)(1) of the
when performing work on the system. The IIAR’s Occupational Safety and Health Act (29 U.S.C. §
Introduction to Ammonia Refrigeration contains 654(a)(1)). Additional items shall be included in the
a description of personal protection equipment operating procedures if the ammonia refrigerating
applicable to ammonia. Developers of operating system is covered by OSHA’s Process Safety
procedures shall review IIAR’s Introduction to Management (PSM) Standard (29 CFR 1910.119), the
Ammonia Refrigeration, modify these requirements USEPA’s Risk Management Program (RM Program)
to reflect the work performed on their system, and Regulation (40 CFR Part 68), or state regulations
incorporate the PPE requirements into their operating
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 3
that exceed minimum requirements. Some of these 5.3 Procedures for Non-Routine Tasks
additional items include:
a. System operating limits When non-routine tasks are required which are not
b. Consequences of deviations, steps to take covered by normal operating procedures, facilities
to correct and/or avoid deviations shall develop procedures for these specific tasks
c. Properties of and the hazards associated with during the planning stages for these tasks. Procedures
ammonia for non-routine tasks are permitted to be documented
d. Quality control procedures taken to monitor as temporary operating and/or emergency operating
the ammonia concentration, ammonia procedures.
inventory levels, and the precautions
5.4 Maintaining Operating Procedures
necessary to prevent exposure
e. Description of safety systems and their Each operating procedures shall have a document
functions number, revision number, and/or revision date so
f. Safety and health considerations regarding that changes made to the operating procedure can be
the process clearly tracked. In addition, a table of contents shall be
provided if there are a significant number of distinct
Appendix D contains an example of additional
operating procedures.
information related to regulatory compliance. Consult
IIAR’s Process Safety Management Guidelines for The operators and mechanics shall be able to quickly
Ammonia Refrigeration for additional samples of and easily obtain current operating procedures to
operating procedures which are designed to comply prepare for and perform their assigned job tasks. It
with OSHA’s PSM Standard. is permissible for these procedures to be available as
printed (hard-copy) documents, viewed on computer
5.2 Developing Operating Procedures screens, and/or printed as needed from electronic
Developers of operating procedures shall consider the files. The most current procedures shall be available
following documentation: to ensure that only up-to-date procedures are used to
a. Material safety data sheets perform operations and maintenance tasks.
b. Refrigerating system flow drawings (such Operating procedures shall be reviewed when changes
as block flow diagrams) and/or piping & are made to the ammonia refrigerating system and the
instrument diagrams (P&IDs) operating procedures shall be updated as appropriate.
c. Equipment lists
d. Installation, Operation and Maintenance NOTE: Certain regulations such as OSHA’s
manuals Process Safety Management (PSM) Standard
e. Manufacturer- (or vendor-) provided (29 CFR 1910.119) and the USEPA’s Risk
instruction Management Program (RM Program) Regulation
f. Control system documentation (40 CFR Part 68) require operating procedures
g. Operating parameters to be annually certified current and accurate.
h. Application data
i. Consider direct input of system operators or
mechanics when documenting the procedures
followed to operate the refrigerating system.
4 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
SECTION 6
EQUIPMENT
This section applies to the following compressors 6.2.2.1 The following items shall be
which are applied to closed-circuit ammonia considered (as applicable to the equipment)
refrigerating systems: when documenting procedures for monitoring
a. Rotary vane booster compressors a compressor.
b. Reciprocating booster and high stage a. Verify that the following compressor
compressors parameters are within expected operating
c. Rotary screw booster and high stage limits and troubleshoot as necessary:
compressors i. Discharge pressure and temperature.
d. Centrifugal booster and high stage ii. Suction pressure and temperature.
compressors iii. Oil pressure and temperature.
Appendix A contains sample operating procedures iv. Oil filter pressure drop.
for a high (single) stage compressor. v. Oil level.
b. Verify that shaft seal leakage is within
6.2.1 Compressor initial start-up the allowable limits specified by the
manufacturer.
6.2.1.1 The following items shall be c. Verify that there are no ammonia or
considered (as applicable to the equipment) oil leaks from the compressor beyond
when documenting compressor start-up allowable limits of shaft seal leakage
procedures. specified by the manufacturer.
a. Appropriate conditions (suction and d. Verify that there are no unusual noises
discharge pressure and temperature, or vibrations.
lubrication oil temperature, lubrication oil
level, etc.) to ensure a safe start-up.
b. Corrective actions required if the
conditions are outside of appropriate
limits.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 5
6.2.3 Steps required to operate 6.2.6 Compressor emergency operations
a compressor under temporary operations
6.2.6.1 The following items shall be
6.2.3.1 The following items shall be considered (as applicable to the equipment)
considered (as applicable to the equipment) when documenting procedures for compressor
when documenting procedures for operating emergency operations.
a compressor under temporary operating a. Steps to operate the compressor under
parameters. emergency operations, for example when
a. Steps to consult supervisory personnel to compressor conditions are outside of
establish temporary operating parameters. appropriate limit.
b. Steps to modify the compressor to operate
under the temporary operating parameters. 6.2.7 Compressor start-up following a
c. Procedures to monitor the compressor turnaround, or after an emergency shutdown
while it is operated under temporary
operating conditions. 6.2.7.1 The following items shall be
considered (as applicable to the equipment)
6.2.4 Compressor normal shutdown when documenting procedures for starting
a compressor following a turnaround or
6.2.4.1 The following items shall be following an emergency shut down.
considered (as applicable to the equipment) a. Appropriate practices if the compressor
when documenting compressor shut down will be started following general
procedures. maintenance, emergency shut down or
a. Steps to stop the compressor. after a system modification.
b. Steps to prepare the compressor for b. Appropriate conditions (suction and
stand-by operations or for maintenance discharge pressure and temperature,
operations as appropriate. lubrication oil temperature, lubrication oil
level, etc.) to ensure a safe start-up.
6.2.5 Compressor emergency shutdown c. Corrective actions required if the
conditions are outside of appropriate
6.2.5.1 The following items shall be limits.
considered (as applicable to the equipment) d. Lockout/tagout procedures.
when documenting procedures for shutting e. Location of the compressor electrical
down a compressor in an emergency. disconnect.
a. Specify who is responsible for the f. Position of the compressor isolation and
emergency shutdown of the compressor. service valves.
b. Steps to stop the compressor. g. Status of the lubrication oil cooling
c. Steps to close the compressor isolation system.
valves, turn off power to the compressor, h. Function of the compressor alarm systems.
and apply lockout/tagout devices if it is i. Steps to start the compressor.
safe to do so.
d. Notification of supervisory personnel and/ 6.3 Condensers
or the appropriate authorities.
e. Steps to log the conditions that caused This section applies to the following condensers which
the emergency shutdown. are applied to closed circuit ammonia refrigerating
systems:
a. Air cooled condensers and air cooled
desuperheaters.
6 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
b. Evaporative condensers. iv. Sump heater (if applicable).
c. Horizontal and vertical shell and tube b. Verify that there are no ammonia or water
condensers with closed water passes and leaks from the condenser.
vertical shell and tube condensers with open c. Verify that the water supply to the
water passes. condenser(s) is on and if a sump is used
d. Plate heat exchanger condensers of the plate- the water is at the proper level.
and-shell type, and of the plate-and-frame d. Verify that the level control is properly
type. working.
e. Double-pipe condensers with closed water e. Verify that the water pump shaft seal is
passes. not leaking.
f. Verify that there are no unusual noises or
6.3.1 Condenser initial start-up vibrations.
g. Verify the sump heater is operational.
6.3.1.1 The following items shall be h. Verify good water spray on coils.
considered (as applicable to the equipment) i. Verify tension on fan belts.
when documenting condenser start-up
procedures. 6.3.3 Steps required to operate a condenser
a. Appropriate practices if the condenser will under temporary operations
be started following general maintenance,
emergency shut down or after a system 6.3.3.1 The following items shall be
modification. considered (as applicable to the equipment)
b. Appropriate conditions (pressure, when documenting procedures for operating
temperature, water flow, etc.) to ensure a condenser under temporary operating
safe startup. parameters.
c. Corrective action required if the conditions a. Steps to consult supervisory personnel to
are outside of appropriate limits. establish temporary operating parameters.
d. Lockout/tagout procedures. b. Steps to modify the condenser to operate
e. Location of the condenser electrical under the temporary operating parameters.
disconnect. c. Steps to monitor the condenser while it
f. Position of the condenser isolation and is operated under temporary operating
service valves. conditions.
g. Function of the condenser alarm systems.
h. Steps to start the condenser water flow 6.3.4 Condenser normal shutdown
and fans.
6.3.4.1 The following items shall be
6.3.2 Monitoring a condenser during normal considered (as applicable to the equipment)
operations when documenting condenser shut down
procedures:
6.3.2.1 The following items shall be a. Steps to turn off condenser fans.
considered (as applicable to the equipment) b. Steps to turn off the water pump.
when documenting procedures for monitoring c. Steps to turn off the water supply
a condenser: (if necessary).
a. Verify that the following condenser d. Steps to drain the condenser sump
parameters are within expected operating (if necessary).
limits and troubleshoot as necessary: e. Steps to prepare the condenser for
i. Discharge pressure. stand-by operations or for maintenance
ii. Water treatment limits. operations as appropriate.
iii. Water temperature.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 7
6.3.5 Condenser emergency shutdown a. Appropriate maintenance practices if
this evaporator will be started following
6.3.5.1 The following items shall be general maintenance, emergency shut
considered (as applicable to the equipment) down or after a system modification.
when documenting procedures for shutting b. Appropriate conditions (pressure,
down a condenser in an emergency. temperature, ammonia level, etc.) to
a. Steps to stop vapor flow to the condenser ensure a safe start-up.
by shutting down the appropriate c. Corrective actions required if conditions
compressor(s) and pressure vessels. are outside of appropriate limits.
b. Steps to shut down the water pumps and d. Lockout/tagout procedures.
fans (if appropriate). e. Location of the evaporator electrical
c. Steps to close the condenser isolation disconnect.
valves and apply lockout/tagout devices if f. Position of evaporator isolation and
it is safe to do so. service valves.
d. Notification of supervisory personnel and/ g. Equipment in the refrigerating system
or the appropriate authorities. needed to accommodate this evaporator.
e. Steps to log the conditions that cause the h. Function of the evaporator alarm systems.
emergency shut down. i. Steps to start the evaporator.
j. Status of the process refrigerating load.
6.4 Evaporators
6.4.2 Monitoring an evaporator during normal
This section applies to the following evaporators
operations
which are applied to closed circuit ammonia
refrigerating systems: 6.4.2.1 The following items shall be
a. Forced air evaporator coils. considered (as applicable to the equipment)
b. Shell-and-tube evaporators (with refrigerant when documenting procedures for monitoring
in shell or in tubes) at any temperature level an evaporator.
when evaporating refrigerant is used to cool a. Verify that the following evaporator
another fluid. parameters are within expected operating
c. Plate heat exchanger evaporators of the plate- limits and troubleshoot as necessary:
and-shell type and of the plate-and-frame i. Suction pressure.
type. ii. Suction temperature.
d. Tube-in-tube evaporators. iii. Ammonia level (if applicable).
e. Jacketed vessels. iv. Process temperature and flow.
f. Scraped surface heat exchangers. b. Verify that there are no ammonia leaks
g. Falling film heat exchangers. from the evaporator.
h. Specialized heat exchangers. c. Verify that there are no unusual noises or
vibrations.
6.4.1 Evaporator initial start-up
d. Status of the process refrigeration load.
e. Verify there is no unacceptable ice buildup
6.4.1.1 The following items shall be
on evaporator coils.
considered (as applicable to the equipment)
when documenting evaporator start-up
6.4.3 Steps required to operate an evaporator
procedures.
under temporary operations
8 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
6.4.3.1 The following items shall be 6.4.6 Defrosting an evaporator
considered (as applicable to the equipment)
when documenting procedures for operating 6.4.6.1 The following items shall be
an evaporator under temporary operating considered (as applicable to the equipment)
parameters. when documenting procedures to defrost an
a. Steps to consult supervisory personnel to evaporator.
establish temporary operating parameters. a. Defrost method: air, water, hot gas, or
b. Steps to modify the evaporator to operate electric.
under the temporary operating parameters. b. The frequency of the defrost cycles
c. Steps to monitor the evaporator while it c. The method used to initiate a defrost
is operated under temporary operating cycle (for example manually initiated or
conditions. initiated using a timer).
d. Steps to monitor the process while it d. The specific sequence of steps associated
is operated under temporary operating with the defrost cycle.
conditions. e. Controls and instruments associated with
the defrost cycle.
6.4.4 Evaporator normal shutdown f. Pressures during the defrost cycle.
g. Precautions necessary to prevent thermal
6.4.4.1 The following items shall be shock during the defrost cycle.
considered (as applicable to the equipment) h. Process parameters and status.
when documenting evaporator shut down
procedures. 6.5 Pressure Vessels
a. Steps to shut down the evaporator.
b. Steps to shut down the process associated This section applies to pressure vessels which are
with the evaporator. applied for use in closed circuit ammonia refrigerating
c. Steps to prepare the evaporator for systems.
stand-by operations or for maintenance
6.5.1 Pressure vessel initial start-up
operations as appropriate.
6.5.1.1 The following items shall be
6.4.5 Evaporator emergency shutdown
considered (as applicable to the equipment)
6.4.5.1 The following items shall be considered when documenting pressure vessel start-up
(as applicable to the equipment) when procedures.
documenting procedures for shutting down an a. Appropriate practices if the pressure
evaporator in an emergency. vessel will be started following general
a. Steps to shut down the evaporator. maintenance, emergency shut down or
b. Steps to discontinue process operations. after a system modification.
c. Steps to close the evaporator isolation b. Appropriate conditions (pressure, ammonia
valves, turn off power to the evaporator, level, etc.) to ensure a safe start-up.
and apply lockout/tagout devices if it is c. Corrective actions required if the conditions
safe to do so. are outside of appropriate limits.
d. Notification of supervisory personnel and/ d. Lockout/tagout procedures.
or the appropriate authorities. e. Position of all pressure vessel isolation
e. Steps to log the conditions that cause the and service valves.
emergency shut down. f. Function of the pressure vessel alarm
systems.
g. Steps to bring the appropriate equipment
on line.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 9
6.5.2 Monitoring a pressure vessel during d. Steps to prepare the pressure vessel for
normal operations stand-by operations or for maintenance
operations as appropriate.
6.5.2.1 The following items shall be
considered (as applicable to the equipment) 6.5.5 Pressure vessel emergency shutdown
when documenting procedures for monitoring
a pressure vessel. 6.5.5.1 The following items shall be
a. Verify that the following pressure vessel considered (as applicable to the equipment)
parameters are within expected operating when documenting procedures for shutting
limits and troubleshoot as necessary: down a pressure vessel in an emergency.
i. Pressure. a. Steps to minimize the magnitude or
ii. Liquid level. duration of the emergency. The specific
b. Verify that there are no ammonia leaks steps will be dependent on the emergency
from the pressure vessel. situation that is occurring.
b. Steps to close the pressure vessel isolation
6.5.3 Steps required to operating a pressure valves and apply lockout/tagout devices
vessel under temporary operations when it is safe and appropriate to do so.
c. Notification of supervisory personnel and/
6.5.3.1 The following items shall be or the appropriate authorities.
considered (as applicable to the equipment) d. Steps to log conditions that cause the
when documenting procedures for operating emergency shut down.
the pressure vessel under temporary operating
parameters. 6.6 Refrigerant Pumps
a. Steps to consult supervisory personnel to
establish temporary operating parameters. This section applies to mechanical pumps applied for
b. Steps to modify the pressure vessel to use in closed circuit ammonia refrigerating systems.
operate under the temporary operating This section does not apply to transfer procedures
parameters. which are addressed in Section 8.2.
c. Steps to monitor the pressure vessel while
6.6.1 Refrigerant pump initial start-up
it is operated under temporary operating
conditions.
6.6.1.1 The following items shall be
considered (as applicable to the equipment)
6.5.4 Pressure vessel normal shutdown
when documenting pump start-up procedures.
6.5.4.1 The following items shall be a. Appropriate practices if the pump will be
considered (as applicable to the equipment) started following general maintenance,
when documenting pressure vessel shut emergency shut down or after a system
down procedures. modification.
a. Steps to stop the flow to the pressure b. Appropriate conditions (suction pressure,
vessel by shutting down the appropriate discharge pressure, etc.) to ensure a safe
equipment such as compressor(s), start-up.
condenser(s), and evaporator(s). c. Corrective actions required if conditions
b. Steps to shut off the liquid make-up are outside of appropriate limits.
system (if necessary). d. Lockout/tagout procedures.
c. Steps to close isolation valves to stop e. Location of the pump electrical
liquid migration (if necessary). disconnect.
f. Position of pump isolation and service
valves.
10 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
g. Function of the pump alarm systems. 6.6.4 Refrigerant pump normal shutdown
h. Steps to start the pump.
i. Process status. 6.6.4.1 The following items shall be
j. Minimum flow. considered (as applicable to the equipment)
k. Hydrostatic relief. when documenting pump shut down
l. Motor cooling. procedures.
a. Steps to stop the pump.
6.6.2 Monitoring a refrigerant pump during b. Steps to prepare the pump for stand-by
normal operations operations or for maintenance operations
as appropriate.
6.6.2.1 The following items shall be c. Steps to secure process operations.
considered (as applicable to the equipment)
when documenting procedures for monitoring 6.6.5 Refrigerant pump emergency shutdown
a pump.
a. Verify that the following pump parameters 6.6.5.1 The following items shall be
are within expected operating limits and considered (as applicable to the equipment)
troubleshoot as necessary: when documenting procedures for shutting
i. Discharge pressure. down a pump in an emergency.
ii. Suction pressure. a. Steps to stop the pump.
b. Verify that there is no leakage from the b. Steps to close the pump isolation valves,
pump seals. turn off power to the pump, and apply
c. Verify that there are no leaks from flanges lockout/tagout devices if it is safe to do so.
or pipe connections. c. Notification of supervisory personnel and/
d. Verify that there are no unusual noises or the appropriate authorities.
or vibrations. d. Steps to log the conditions that caused the
emergency shut down.
6.6.3 Steps required to operating a refrigerant e. Steps to secure process operations.
pump under temporary operations
6.7 Non-Condensable Gas Purger
6.6.3.1 The following items shall be
considered (as applicable to the equipment) This section applies to non-condensable gas purgers
when documenting procedures for operating a applied for use in closed circuit ammonia refrigerating
pump under temporary operating parameters. systems. This section does not apply to manual
a. Steps to consult supervisory personnel to purging of non-condensables from the system which is
establish temporary operating parameters. addressed in Section 8.3.
b. Steps to modify the refrigerant pump to
6.7.1 Non-condensable gas purger initial start-up
operate under the temporary operating
parameters.
6.7.1.1 The following items shall be
c. Steps to monitor the refrigerant pump
considered (as applicable to the equipment)
while it is operated under temporary
when documenting purger start-up procedures.
operating conditions.
a. Appropriate practices if the purger will
be started following general maintenance,
emergency shut down or after a system
modification.
b. Appropriate conditions (foul gas pressure,
purge point timing, etc.) to ensure a safe
system start-up.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 11
c. Corrective actions required if the c. Steps to monitor the purger while it is
conditions are outside of appropriate operated under temporary operating
limits. conditions.
d. Lockout/tagout procedures.
e. Location of the purger electrical 6.7.4 Non-condensable gas purger normal
disconnect. shutdown
f. Position of the purger isolation and service
valves. 6.7.4.1 The following items shall be
g. Function of the purger alarm systems. considered (as applicable to the equipment)
h. Steps to start the water supply to the when documenting purger shut down
purger. procedures.
i. Steps to start the purger. a. Steps to stop the purger.
b. Steps to prepare the purger for stand-by
6.7.2 Monitoring a non-condensable gas purger operations or for maintenance operations
during normal operations as appropriate.
6.7.2.1 The following items shall be 6.7.5 Non-condensable gas purger emergency
considered (as applicable to the equipment) shutdown
when documenting procedures for monitoring
a purger. 6.7.5.1 The following items shall be
a. Verify that the following purger considered (as applicable to the equipment)
parameters are within expected operating when documenting procedures for shutting
limits and troubleshoot as necessary: down a purger in an emergency.
i. Water supply. a. Steps to stop the purger.
ii. Timing and duration of purge points. b. Steps to close the purger isolation valves,
iii. Incoming foul gas pressure at each turn off power to the purger, and apply
incoming line. lockout/tagout devices if it is safe to do so.
iv. Condition of solenoid valve coils. c. Notification of supervisory personnel and/
v. Purge count (if applicable). or the appropriate authorities.
b. Verify that there is no leakage from the d. Steps to log the conditions that caused the
purger. emergency shut down.
c. Check the ammonia concentration in the
area in/around the purger. 6.8 Oil Removal Devices
12 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
6.8.1.1 The following items shall be a. Position of isolation and service drain
considered (as applicable to the equipment) valves.
when documenting procedures to set-up an oil b. Steps to operate auxiliary heating systems
removal device. (if necessary).
a. Appropriate practices if the oil removal c. Sequence of steps used to minimize the
device will be used following general amount of residual ammonia in the oil.
maintenance, emergency shut down or d. Sequence of steps to drain oil from the
after a system modification. system.
b. Appropriate conditions (system pressure, e. Amount of time needed to drain the oil.
device pressure, etc.) to ensure a safe f. Oil removal device pressure.
operation. g. Steps to use auxiliary equipment such as a
c. Corrective actions required if the pump-out system (if necessary).
conditions are outside of appropriate h. Steps to maintain an oil log.
limits. i. Steps to dispose of the oil removed from
d. Lockout/tagout procedures. the system.
e. Need for personal protection equipment.
f. Emergency response procedures. 6.8.3 Steps required to operating an oil
g. Location of safety shower and eyewash removal device under temporary operations
stations.
h. Position of isolation and service drain 6.8.3.1 The following items shall be
valves. considered (as applicable to the equipment)
i. Function of the oil removal device alarm when documenting procedures for operating
systems (as applicable to the equipment). an oil removal device under temporary
j. Type of oil removal device. operating parameters.
a. Steps to consult supervisory personnel to
6.8.2 Operating an oil removal device during establish temporary operating parameters.
normal operations b. Steps to modify the oil removal device
to operate under the temporary operating
6.8.2.1 The following items shall be parameters.
considered (as applicable to the equipment) c. Steps to monitor the oil removal device
when documenting procedures to drain oil while it is operated under temporary
from the system to the oil removal device. operating conditions.
a. Position of isolation and service drain
valves. 6.8.4 Oil removal device normal shutdown
b. Sequence of steps to drain oil from the
system. 6.8.4.1 The following items shall be
c. Amount of time needed to drain the oil. considered (as applicable to the equipment)
d. System pressure. when documenting oil removal device shut
e. Oil removal device pressure. down procedures.
f. Steps to use auxiliary equipment such as a a. Steps to return the device to standby
pump-out system (if necessary). mode.
g. System being drained. b. Position of isolation and service drain
valves.
6.8.2.2 The following items shall be c. Steps to turn off auxiliary equipment such
considered (as applicable to the equipment) as a pump-out system (if necessary).
when documenting procedures to draining oil d. Steps to verify there are no ammonia
from the oil removal device. leaks.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 13
6.8.5 Oil removal device emergency shutdown b. Steps to close the oil removal device
isolation valves, turn off power to the oil
6.8.5.1 The following items shall be removal device, and apply lockout/tagout
considered (as applicable to the equipment) devices if it is safe to do so.
when documenting procedures for shutting c. Notification of supervisory personnel and/
down an oil removal device in an emergency. or the appropriate authorities.
a. Steps to shut down the oil removal device. d. Steps to log the conditions that caused the
emergency shut down.
SECTION 7
SYSTEMS
7.1 This section lists items which shall be b. Refrigerating system configuration.
considered when combining procedures for individual c. The sequence in which they will be operating.
pieces of equipment into operating procedures for the d. If one procedure can be used for all of the
entire refrigerating system. equipment or whether multiple procedures
must be developed for individual pieces of
7.2 When developing operating procedures for equipment.
the entire refrigerating system or for refrigerating
subsystems the following items shall be considered: 7.3 Additional guidelines are contained in the
a. Type and style of equipment used in the attached Informative Appendix B.
refrigerating system.
SECTION 8
TASKS
14 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
d. Facility safe work practices and emergency 8.4 Pump-Out and Line/Equipment Opening
action and response plan procedures Procedures
applicable to the charging procedures.
e. Steps required to charge ammonia to the 8.4.1 The operating procedures for the pump-
system. out and line/equipment opening shall document
f. Steps required to purge the charging system. the following items:
g. Visually inspect hoses fittings, etc. and a. The appropriate personal protective equipment
make sure they are suitable for ammonia (PPE) that shall be worn and indicate when
refrigeration service. the buddy system shall be practiced.
b. The conditions under which pump-out and/or
8.2.3 The operating procedures for transferring line/equipment opening are required.
ammonia within the system shall document the c. Location of the line/equipment that will be
following items: pumped-out and/or opened.
a. The appropriate personal protective equipment d. Facility safe work practices and emergency
(PPE) that shall be worn and indicate when action and response plan procedures
the buddy system shall be practiced. applicable to the line/equipment opening
b. The conditions required for the transfer. procedures.
c. The source and the receiving location for the e. Steps required to pump-out the line/
ammonia. equipment.
d. Steps required to transfer the ammonia. f. Steps required to open the line/equipment.
e. Steps required to terminate the transfer of g. Steps required to place the system back in
ammonia. normal operations.
f. Visually inspect hoses fittings, etc. and
make sure they are suitable for ammonia 8.4.2 Appendix C contains sample line opening
refrigeration service. procedures.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 15
Section 9
Sources of References (Informative)
9.1 American National Standards Institute (ANSI) 9.5 Refrigerating Engineers & Technicians
25 West 43rd Street, 4th Floor Association (RETA)
New York, NY 10036 PO Box 1819
Salinas, CA 93902
9.2 American Society of Heating, Refrigerating
and Air Conditioning Engineers, Inc. 9.6 U.S. Environmental Protection Agency (EPA)
(ASHRAE) Ariel Rios Building
1791 Tullie Circle, N.E. 1200 Pennsylvania Avenue, NW
Atlanta, GA 30329 Washington, DC 20460
16 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
APPENDIX A (INFORMATIVE)
EQUIPMENT SOP SAMPLE — SOP 1:
HIGH (SINGLE) STAGE COMPRESSOR
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 17
A.1.8 Verify the oil level in the compressor using • Suction pressure: Verify the position of the
the two sight glasses. The level should be in the suction valve and adjust settings using the
middle of the top sight glass when the compressor is compressor microprocessor
shut down. The level should be in the middle of the • Discharge pressure: Verify the position of the
bottom sight glass when the compressor is running. discharge valve and verify the operation of the
evaporative condenser
A.1.9 Verify that the compressor coupling • Lubrication oil pressure and temperature,
guard is in place. discharge temperature: Verify the operation
of the lubrication oil pump, the position of the
A.1.10 Remove any locks and tags and turn on oil valves, the oil filter pressure drop and the
power to the compressor. operation of liquid injection system
• Verify that there are no mechanical problems
A.1.11 Use the microprocessor to ensure that the with the compressor.
oil temperature in the oil separator is above 110oF.
If the oil temperature is not above 110oF check the A.2.2 Shutdown the compressor (see task 5) if
oil heater. any of the following conditions occurs:
• Shaft seal leakage is not within the allowable
A.1.12 Press the “Local Start” button on the limits specified by the manufacturer
microprocessor. • Ammonia or oil leaks beyond allowable
limits of shaft seal leakage specified by the
A.1.13 Press the “Automatic” button on the manufacturer
microprocessor. The compressor oil pressure • Unusual noises or vibrations
will begin to increase as the lubrication pump
starts-up. Once the oil pressure has built up, the A.2.3 The compressor log sheet should be filled
compressor will start. out once a ______.
18 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
A.4 Compressor Normal Shutdown A.4.9 Evacuate the residual ammonia from the
compressor, until the pressure gauge located at
The following procedures should be used during the service port of the low pressure suction header
normal (manual) shutdowns of the compressor. reads 0 psig.
Steps A.4.4 to A.4.13 should only be followed if
maintenance is to be performed on the compressor A.4.10 Close the valve on the service port to the
Section A.5 should be used for emergency shutdown low pressure suction header (Valve # ___) and
procedures. monitor the pressure gauge on the service port at
the low pressure suction header for any pressure
A.4.1 Push the “manual unload” button on the increases (above 0 psig).
compressor microprocessor.
A.4.11 After 15 minutes, close the “pump out”
A.4.2 While the compressor unloads, monitor valve on the compressor (Valve # ___). Remove
the compressor temperatures and pressures and the pressure gauge and slowly reopen the “pump
look/listen for any unusual vibrations. out” valve on the compressor to break the vacuum.
A.4.3 Monitor the load percentage until it A.4.12 Open, lock and “tag” the compressor
reaches 0%, then push the “Stop/Reset” button disconnect to lock out power to the compressor.
to stop the compressor.
A.4.13 At this point ammonia should be
A.4.4 Close, “tag”, and lock the manual removed from the compressor and the compressor
valve located in the compressor suction line. should be fully locked out. Follow appropriate line
(Valve # ___). opening procedures to perform maintenance on the
compressor. Wear appropriate personal protective
A.4.5 Close, “tag”, and lock the manual
equipment (PPE) and follow the buddy system.
valve located in the compressor discharge line.
(Valve # ___). A.5 Compressor Emergency Shutdown
A.4.6 Close, “tag”, and lock the manual valves The following procedures should be used by qualified,
located in the compressor liquid injection line. trained personnel to shutdown the compressor during
(Valves # ___ and # ___). an emergency. Use these procedures if there are leaks
on the compressor skid or if there is any mechanical
A.4.7 Connect a hose that is appropriate for damage to the compressor. These procedures are only
ammonia service from the “pump down” valve guidelines to supplement the emergency response
located on the compressor to the service valve procedures. Each emergency situation should be
on the low pressure suction header (Valve # ___). evaluated on a case-by-case basis to determine the
actual emergency response procedures to follow.
A.4.8 Open the service valve (Valve # ___)
on the low pressure suction header and the “pump A.5.1 Practice the buddy system and do not put
down” valve on the compressor (Valve # ___) yourself at risk during any emergency. If an area
allowing the low pressure suction header to cannot be safely entered, leave the area and wait
evacuate residual ammonia from the compressor for assistance before proceeding.
to the refrigeration system.
A.5.2 Verify that the ventilation fans in the
machinery room are operating.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 19
A.5.4 Assemble the appropriate general A.5.9 Close, “tag”, and lock the manual valve
protective equipment. Protective equipment that located in the compressor discharge line. (Valve #
may be required includes: ___ ).
• Goggles;
• Full face shield; A.5.10 Close, “tag”, and lock the manual valves
• Chemical resistant gloves (rated for located in the compressor liquid injection line.
appropriate temperature levels); (Valves # ___ and # __).
• Chemical resistant boots;
• Emergency showers/eye wash stations; A.5.11 Open, lock and “tag” the compressor
• First aid kit; disconnect to lock out power to the compressor.
• Full face gas mask;
• Positive pressure self-contained breathing A.6 Compressor Emergency Operations
apparatus;
The following procedures should be used by qualified,
• Chemical resistant suits (rated for ammonia use);
trained personnel to operate the compressor during an
• 2-way radios; and
emergency, for example when compressor conditions
• Hearing protection (earplugs).
are outside of appropriate limits. Each emergency
situation should be evaluated on a case-by-case basis to
A.5.5 Assemble the appropriate tools. Tools
determine the actual emergency operations to follow.
that may be required include:
• Rescue rope;
A.6.1 Consult the refrigeration supervisor to
• Non-sparking pipe wrench;
determine what adjustments are necessary.
• Ammonia rated purge hose;
• Portable monitoring equipment; A.6.2 Adjust the settings as necessary using the
• Explosion-proof flashlight(s); compressor microprocessor. The manufacturer’s
• Water hose with mist nozzle; and equipment manual should be consulted for
• Portable ventilation fans. the specific procedures necessary to adjust the
settings.
A.5.6 Measure the ammonia concentration
at the door and follow the personal protective A.6.3 Record any setting changes using the
equipment (PPE) requirements in the Emergency computer and/or the log book in the control room.
Response Plan before walking into any room.
No area should be entered if there is a visible A.6.4 Follow the normal operating procedures
ammonia cloud. (see task 2) to monitor the compressor while it is
operated using these settings.
A.5.7 Shut off the compressor by hitting the
“Emergency Stop” button on the microprocessor A.6.5 Shutdown the compressor (see task 5)
control panel. If the button cannot be safely reached if any of the following conditions occurs:
due to the ammonia concentration inside the • Shaft seal leakage is not within the allowable
compressor room, use the “Emergency Stop” button limits specified by the manufacturer
located at the entrance to the compressor room. • Ammonia or oil leaks beyond allowable
limits of shaft seal leakage specified by the
A.5.8 Close, “tag”, and lock the manual manufacturer
valve located in the compressor suction line. • Unusual noises or vibrations
(Valve # ___ ).
20 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
A.7 Compressor Start-Up Following a A.7.2 Follow pre-startup procedures for the
Turnaround or After an Emergency Shutdown compressor as appropriate, for example vacuum
and/or pressure tests. Consult IIAR 5 Start-up
The following procedures should be used during start-
and Commissioning of Closed-Circuit Ammonia
ups of the compressor following turnarounds or after
Mechanical Refrigerating Systems for examples
an emergency shutdown.
of initial start-up procedures when commissioning
new equipment.
A.7.1 Determine (and correct if necessary) any
problems before restarting the system following
A.7.3 Follow the compressor initial start-up
an emergency shutdown
procedures (step 1) to start-up the compressor.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 21
APPENDIX B (INFORMATIVE)
DISCUSSION — SYSTEM SOP
22 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
procedure may be written for all compressors e. Procedures for systems with secondary
of the same manufacturer even if the system refrigerants (such as glycol chillers) are
contains multiple compressor models provided typically included with the procedures for the
that the compressors are in similar service evaporators associated with the secondary
(e.g. all high stage compressors). Methods refrigerant.
that can be used to account for the differences f. Separate procedures are typically developed
include: for the carbon dioxide equipment in an
i. Using tables to list the specific valve ammonia/carbon dioxide cascade refrigerating
numbers for each piece of equipment. system.
ii. Providing “Notes” in the procedures
which describe steps needed to operate a B.2.5 System- wide operating procedures
specific piece of equipment. are typically developed for complex systems
iii. Add additional sections to the procedures in addition to the procedures developed for
which contain steps for a specific piece the individual pieces of equipment. Examples
of equipment, for example procedures to of system- wide operating procedures that are
operate a swing compressor. typically developed include:
c. Separate procedures are often developed if a. Start-up procedures following a system- wide
the equipment is not similar (for example outage, for example following a planned
reciprocating compressors vs. screw system shut-down or turnaround.
compressors) or if the equipment is not b. Start-up procedures following a system- wide
in similar service (for example high stage emergency shut-down.
compressors vs. booster compressors). c. Operating procedures during and after a system-
d. Separate procedures are typically developed wide power outage.
if the equipment is located in separate d. Shut-down procedures for a system- wide
refrigerating systems which are not shut-down, for example a planned turnaround.
interconnected. e. Emergency shut-down and operating
procedures for the entire system, for example
B.2.4 The following practices are often following a large ammonia release or a natural
followed when documenting procedures for disaster.
complex systems.
a. Procedures for refrigerant pumps are often B.2.6 System- wide controls may be included
combined with the procedures for the vessel in the procedures developed for the individual
associated with the pump. pieces of equipment or may merit separate
b. Separate procedures are typically not dedicated procedures. Examples of system wide-
written for instrumentation. Instrumentation controls include:
is typically included in the procedure for a. Master hot gas outlet pressure control
the specific piece of equipment associated regulators.
with that instrumentation. For example, a b. Emergency pressure control systems.
pressure vessel procedure would include c. Ammonia detection systems.
instrumentation associated with the pressure d. Ammonia ventilation systems
vessel level control systems. e. Ammonia pressure relief systems.
c. Oil draining procedures are typically included
with the equipment where the oil is drained
from.
d. Pressure vessels associated with evaporators
in flooded systems are often combined with
the evaporators into a single procedure.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 23
APPENDIX C (INFORMATIVE)
SAMPLE LINE OPENING PROCEDURES
C.1.2 Verify that you know the location of C.1.10 After the equipment/line is evacuated,
all valves that would be required to isolate the completely isolate the line by closing, locking,
equipment in the event of a problem. and tagging the valve in the suction line.
24 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
C.1.11 If possible, conduct a pressure test C.1.14 The system is now ready for maintenance
by attaching a pressure gauge and monitoring operations.
the pressure to verify that the pressure is not
increasing above 0 psig. C.1.15 When placing the equipment/line back
in service after maintenance operations, conduct a
C.1.12 Verify that the line is not cold — pressure test the system by opening a valve in the
this will let you know it is evacuated. suction line. Then work backwards, opening the
suction valve(s) first and finally the valve(s) in the
C.1.13 Slowly vent the line/equipment at the supply line.
best place possible so you can isolate it quickly
if necessary. For example, use a vent line where
possible to vent residual ammonia into a container
of water to minimize any ammonia smell.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 25
APPENDIX D (INFORMATIVE)
EXAMPLE OF ADDITIONAL INFORMATION WHICH MAY
BE NEEDED FOR REGULATORY COMPLIANCE
Revision Table
Objective This procedure contains the Technical Operating Specifications (TOS) and Standard
Operating Procedures (SOPs) which describe the operation of the compressor.
Purpose The purpose of the TOS is to provide a description of the compressor defining its
function, operating conditions and limits, consequences of deviations from operating
limits, controls, instrumentation and safety systems. The purpose of the SOP is to
describe the proper steps for startup, operation and shutdown of the compressor.
Department Refrigeration
Operator/ Refrigeration Operator
Responsibility
Equipment Compressor HS-1
Location The compressor is located in the ammonia machinery room
Related documents Anhydrous Ammonia Material Safety Data Sheet (MSDS) [SDS upon adoption
of Global Harmonization System (GHS)]
Lockout/Tagout Procedures
P&ID R-01
Compressor IOM Manual
26 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
Safety and Health Consideration
Hazards and Ammonia is a colorless gas or liquid with an extremely pungent odor. At 0 psig (0 bar
Properties of gage) It is a gas at room temperature and has a boiling point of -28oF (-33oC) and a
Ammonia freezing point of 108oF (-78oC). When ammonia is in its vapor phase, it is lighter than
air and has a vapor density of 0.60 (Air = 1). When ammonia exists as an aerosol, it is
heavier than air (vapor density >1.0).
In case of skin contact: Wash affected skin areas thoroughly with water for at least 15
minutes and seek medical attention if necessary.
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 27
Compressor Technical Operating Specifications (TOS): Function
Vapor from the intercooler provides suction for the high stage compressor. During the compression phase in the
compressor, the temperature of the ammonia vapor rises as the pressure of the ammonia vapor increases. The
high pressure ammonia vapor flows from the compressor via a vapor header to the evaporative condenser where
heat is removed, condensing the vapor into a high pressure liquid.
28 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
Lubrication oil pressure: Higher or lower lube oil pressures Check the lube oil levels to ensure
35 to 45 psig could damage the compressor. there is enough oil and to make sure
that the oil is not foaming (because
there is ammonia in the oil).
Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited. 29
Low lubrication oil temperature Protect the compressor from 70°F
cutout damage due to low lubrication
oil temperature by shutting down
compressor
High lubrication oil temperature Protect the compressor from 160°F
cutout damage due to high lubrication
oil temperature by shutting down
compressor
High discharge temperature cutout Protect the compressor from 200°F
damage due to high discharge
temperature by shutting down
compressor
Ammonia detector in ammonia The detector will provide audible 35 ppm
machinery room and visual alarms in the machinery
room, send an alarm to control
room, and start the machinery room
ventilation system if the setpoint is
reached.
Emergency stop button When the emergency stop button N/A
located at the entrance to the
machinery room is hit:
• The ammonia compressors
will stop.
• The ammonia pumps
will stop.
• The solenoid valves in
the liquid fill lines to
machinery room vessels
will close.
30 Copyright © 2013 International Institute of Ammonia Refrigeration. All Rights Reserved. Reproduction prohibited.
1001 N. Fairfax Street
Suite 503
Alexandria, VA 22314
(703) 312-4200
Fax: (703) 312-0065
www.iiar.org