You are on page 1of 11

LEGEND: A CRITICAL PATH

DUMMY B C D E F G H I J K M
L N O P Q RS T U V

BAR CHART AND S-CURVE


0 SEPTEMBER, 2016 OCTOBER, 2016 NOVEMBER, 2016 DECEMBER, 2016 JANUARY, 2017 FEBRUARY, 2017 MARCH, 2017
REL WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17 WEEK 18 WEEK 19 WEEK 20 WEEK 21 WEEK 22 WEEK 23 WEEK 24 WEEK 25 WEEK 26
SCOPE OF WORKS QTY AMOUNT
WT. 15-23 24-30 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2 3-9 10-16 17-23 24-30 31-6 7-13 14-20 21-27 28-3 4-10 11-17 18-24 25-3 4-10 11-13

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120

121

122

123

124

125

126

127

128

129

130

131

132

133

134

135

136

137

138

139

140

141

142

143

144

145

146

147

148

149

150

151

152

153

154

155

156

157

158

159

160

161

162

163

164

165

166

167

168

169

170

171

172

173

174

175

176

177

178

179

180
10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99
1

9
Mobilization 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
100.00
0
100
100.00
99.65
Demobilization 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
98.42
I. Construction of 2 Barrel (3m x 3m) Box Culvert (RCBC) along Valencia-Guinoyoran-Lake Apo Road 97.20
0 0 0 0
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 095.980 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SPL-1 Project Billboard 2.00 unit 6,588.00 0.050%
ACTUAL

Construction of Detour PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


SPL-2 60.00 L.m. 145,168.20 1.109%
Road ACTUAL
91.53
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
103 Structure Excavation 186.07 cu.m. 80,540.40 0.615% 90
ACTUAL
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
104 Embankment 27.00 cu.m. 16,107.93 0.123%
ACTUAL 86.88
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 85.63
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
506 Stone Masonry 20.95 cu.m. 92,464.29 0.707%
ACTUAL

Aggregate Sub-Base PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
200 1.00 cu.m. 1,804.29 0.014%
Coarse ACTUAL

PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ### ### ### ### ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
201 Aggregate Base Course 1.00 cu.m. 1,804.29 0.014% 80
ACTUAL 79.20

Portland Cement PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 0 0 0 0 0 0 0 0
311 1.20 cu.m. 11,096.34 0.085%
Concrete Pavement ACTUAL

Reinforcing Steel PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


428,481.45 3.274%
(Cutting & Bending) ACTUAL
404 Reinforcing Steel 8620.49 kgs.
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
(Fabrication & 428,481.46 3.274%
ACTUAL 71.44
Installation)
Structural Concrete (Forms PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 70
635,027.24 4.853%
Fabrication & Installation) ACTUAL
405 163.12 cu.m.
Structural Concrete PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
952,540.87 7.279%
(Concrete Pouring) ACTUAL
65.35
Sub-Total 2,800,104.76 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

II. Upgrading of Kidanggin Bailey Bridge Plus Rehabilitation of Provincial Road 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SPL-1 Project Billboard 2.00 unit 6,588.00 0.050%
ACTUAL 60.89
60
Finishing of Bridge PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2,135,122.01 16.316%
Materials ACTUAL
408 7 panels
Installation of Bridge PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0
56.62 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2,135,122.01 16.316%
Materials ACTUAL

Removal of Deteriorated PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


SPL-2 3840.00 bd.ft. 54,912.00 0.420%
Structural Members ACTUAL

Chipping of Existing PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


51.36
SPL-3 2.00 units 23,185.28 0.177%
Backwall ACTUAL
50
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SPL-4 Painting 7 panels 21,886.83 0.167%
ACTUAL
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SPL-5 Approach Railings 2.00 units 118,980.52 0.909%
ACTUAL 44.99
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
105 (1) Sub-grade Preparation 7500.00 cu.m. 933,750.00 7.136%
ACTUAL

PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
200 Aggregate Sub-Base Course1125.00 cu.m. 2,028,735.00 15.503%
ACTUAL 40
39.41
Sub-Total 7,458,281.65 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

III. Construction of Box Curvert Double Barrel (2.40m x 2.40m) Box Culvert (RCBC) at Dalaposan Creek along Guinoyoran-Lake Apo Road 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SPL-1 Project Billboard 1.00 unit 3,294.00 0.025%
ACTUAL

Structural Concrete (Forms PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 032.980 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


365,718.07 2.795%
Fabrication & Installation) ACTUAL
405 7163.02 kgs.
Structural Concrete PLAN 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
365,718.08 2.795% 30
(Concrete Pouring) ACTUAL 29.54

Reinforcing Steel PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


285,346.06 2.726%
(Cutting & Bending) ACTUAL
404 Reinforcing Steel 73.84 cu.m.
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
(Fabrication & 428,019.10 2.726% 24.63
ACTUAL 24.21
Installation)
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SPL-2 Cofferdamming 1400.00 sacks 69,216.00 0.529%
ACTUAL

PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20.32 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 20
105 Sub-grade Preparation 240.00 cu.m. 29,880.00 0.228%
ACTUAL 18.80

Portland Cement PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 17.40


0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
311 60.00 cu.m. 561,222.00 4.289% 17.11
Concrete Pavement ACTUAL 16.32

PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
506 Stone Masonry 27.22 cu.m. 116,189.11 0.888%
ACTUAL
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
103 Structure Excavation 75.39 cu.m. 40,270.32 0.308% 11.78
ACTUAL
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10
Construction of Detour
SPL-2 300.00 L.m. 178,230.00 1.362%
Road ACTUAL

PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 06.90 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
104 Embankment 379.53 cu.m. 161,080.12 1.231%
ACTUAL

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4.75
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Aggregate Sub-Base PLAN
200 60.00 cu.m. 111,550.80 0.852%
Coarse ACTUAL
2.60
PLAN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
201 Aggregate Base Course 60.00 cu.m. 111,550.80 0.852% 1.44
ACTUAL
0.00
- 0.00
- 0.19
0.00 0.00 0.00 0.00 0
Sub-Total 2,827,284.46 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTAL PHP 13,085,670.87 100% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.02 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

WEEKLY 0.000% 0.186% 1.258% 1.153% 2.150% 2.150% 4.880% 5.334% 7.514% 8.356% 6.432% 5.578% 6.366% 5.264% 4.272% 4.454% 6.093% 7.762% 6.427% 5.903% 4.442% 1.225% 1.225% 1.225% 0.350% 0.000%
PLANNED
Cumulative 0.000% 0.186% 1.444% 2.597% 4.748% 6.898% 11.778% 17.112% 24.626% 32.983% 39.415% 44.992% 51.359% 56.623% 60.895% 65.349% 71.442% 79.204% 85.631% 91.533% 95.976% 97.200% 98.425% 99.650% 100.000% 100.000%
PHYSICAL WEEKLY 0.000% 0.000% 0.000% 0.000% 0.000% 16.316% 1.080% 1.405% 1.520% 3.890% 5.328% 0.136%
ACTUAL
ACCOMPLISHMENT. (%) Cumulative 0.000% 0.000% 0.000% 0.000% 0.000% 16.316% 17.396% 18.802% 20.322% 24.212% 29.540% 29.676%
WEEKLY 0.000% -0.186% -1.258% -1.153% -2.150% 14.166% -3.800% -3.929% -5.994% -4.466% -1.104% -5.442%
SLIPPAGE
Cumulative 0.000% -0.186% -1.444% -2.597% -4.748% 9.418% 5.619% 1.690% -4.304% -8.771% -9.874% -15.316%
Periodic - 24,304.88 164,644.16 150,919.16 281,398.37 281,398.37 638,521.15 698,041.61 983,295.08 1,093,489.11 841,646.75 729,890.57 833,084.46 688,811.27 559,052.38 582,848.48 797,341.55 1,015,696.73 840,978.15 772,402.55 581,307.99 160,249.14 160,249.14 160,249.14 45,785.47 -
EQUIVALENT COST (PHP)
Cumulative - 24,304.88 188,949.04 339,868.20 621,266.57 902,664.94 1,541,186.08 2,239,227.69 3,222,522.77 4,316,011.87 5,157,658.62 5,887,549.19 6,720,633.65 7,409,444.92 7,968,497.30 8,551,345.78 9,348,687.34 10,364,384.07 11,205,362.22 11,977,764.77 12,559,072.76 12,719,321.89 12,879,571.03 13,039,885.40 13,085,670.87 13,085,670.87
MONTH 1 MONTH 2 MONTH 3 MONTH 4 MONTH 5 MONTH 6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
0.00% 0.19% 1.44% 2.60% 4.75% 6.90% 11.78% 17.11% 24.63% 32.98% 39.41% 44.99% 51.36% 56.62% 60.89% 65.35% 71.44% 79.20% 85.63% 91.53% 95.98% 97.20% 98.42% 99.65% 100.00% 100.00%

Republic of the Philippines Name of Project: Prepared by: Reviewed by: Approved: Contents: SHEET NO.

PROVINCE OF BUKIDNON
PROVINCIAL ENGINEER'S OFFICE
Malaybalay City
KONKRETO AT AYOS NA LANSANGAN AND DAAN TUNGO SA
PANGKALAHATANG KAUNLARAN - PACKAGE III GRACE D. CAÑETE BONIFACIO G. SUAREZ ALBERT D. YULO
UP-DATED BAR CHART AND
CURVE
S-
1of1
Location: Valencia City and Pangantucan, Bukidnon Engineer II Engineer IV Provincial Engineer
100
100.00

90

80

70

60

50

40

30

20

10

1of1
Contract Ref. No. : 2019-102 PROVINCIAL ENGINEER'S OFFICE
STATEMENT OF WORK ACCOMPLISHED
Project Name : Concreting of Jct. (Manolo Fortich) Lingi-on Road NTP Date : October 09, 2019
Location : Manolo Fortich, Bukidnon For the period Ending : July 22, 2020 Completion Date : May 15, 2020
Contractor : JT GAMOLO CONSTRUCTION Progress Report No. : 38 evised Completion Date : October 17, 2020
Source of Fund : CMGP Fund
Length : 4.80 kms
ACCOMPLISHMENT
TOTAL REL.
ITEM DESCRIPTION UNIT UNIT PRICE AMOUNT PREVIOUS THIS PERIOD TO DATE REMARKS
QUANTITY WT.
Quantity Amount % Quantity Amount % Quantity Amount %
PART A. FACILITIES FOR THE ENGINEER
Construction of Combined Field Office,
A.1.1 (1) Laboratory and Living Quarters Building for LS 1.00 366,000.00 366,000.00 0.488% 0.360 131,760.00 0.176% - 0.000% 0.360 131,760.00 0.176% ON-GOING
the Engineer
Provision of Furnitures/Fixtures, Equipment
A.1.1 (11) and Appliances for the Field Office for the LS 1.00 256,200.00 256,200.00 0.342% 1.00 256,200.00 0.342% - 0.000% 1.000 256,200.00 0.342% COMPLETED
Engineer
Provision of Service Vehicle (Air-
A.1.2 (2) conditioned type) for the Engineer on bare months 7.00 61,000.00 427,000.00 0.570% 7.00 427,000.00 0.570% - 0.000% 7.000 427,000.00 0.570% COMPLETED
rental basis
PART B. OTHER GENERAL REQUIREMENTS
B.9 Mobilization and Demobilization LS 1.00 176,900.00 176,900.00 0.236% 0.50 88,450.00 0.118% - 0.000% 0.500 88,450.00 0.118% ON-GOING
B.4 (1) Construction Survey and Staking kms. 4.8000 61,000.00 292,800.00 0.391% 4.80 292,800.00 0.391% - 0.000% 4.800 292,800.00 0.391% COMPLETED
B.7 (1) Occupational Safety and Health Program months 6.50 24,400.00 158,600.00 0.212% 6.50 158,600.00 0.212% - 0.000% 6.500 158,600.00 0.212% COMPLETED
B.5 Project Billboard each 2.00 6,100.00 12,200.00 0.016% 2.00 12,200.00 0.016% - 0.000% 2.000 12,200.00 0.016% COMPLETED
PART C. EARTHWORK -
104 (1) b Embankment from Roadway Excavation cu.m. 4,111.0000 124.17 510,462.87 0.681% 4,111.00 510,462.87 0.681% - 0.000% 4,111.000 510,462.87 0.681% COMPLETED
102 (2) Surplus Common Excavation cu.m. 5,967.000 144.96 864,976.32 1.154% 5,967.00 864,976.32 1.154% - 0.000% 5,967.000 864,976.32 1.154% COMPLETED
105 (1) a Subgrade Preparation sq.m. 40,366.722 24.73 998,269.04 1.332% 38,880.00 961,502.40 1.283% - 0.000% 38,880.000 961,502.40 1.283% ON-GOING
PART D. SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course cu.m. 11,887.270 1,528.34 18,167,790.23 24.235% 11,327.20 17,311,812.85 23.094% - 0.000% 11,327.20 17,311,812.85 23.094% ON-GOING
PART E. SURFACE COURSE
311 (1) d1 Portland Cement Concrete Pavement sq.m. 29,576.35 1,464.00 43,299,776.40 57.761% 29,074.13 42,564,519.00 56.780% - 0.000% 29,074.13 42,564,519.00 56.780% ON-GOING
Portland Cement Concrete Pavement, 200mm
311 (1) a2 sq.m. 1,190.00 1,329.79 1,582,453.11 2.110% - - 0.000% - 0.000% - - 0.000% NOT YET STARTED
thk.
PART F. DRAINAGE AND SLOPE PROTECTION
103 (1) Structure Excavation cu.m. 437.68 293.58 128,494.09 0.171% 148.94 43,725.81 0.058% - 0.000% 148.940 43,725.81 0.058% ON-GOING
500 (1) a3 Pipe Culvert, 910mm. Dia., Class II l.m. 63.00 5,490.00 345,870.00 0.461% 23.00 126,270.00 0.168% - 0.000% 23.000 126,270.00 0.168% ON-GOING
500 (1) a Pipe Culvert, 610mm. Dia., Class II l.m. 38.00 4,911.75 186,646.65 0.249% 23.00 112,970.34 0.151% - 0.000% 23.000 112,970.34 0.151% NOT YET STARTED

506 (1) Stone Masonry (Headwall & Catch Basin) cu.m. 227.21 3,808.98 865,438.35 1.154% - - 0.000% - 0.000% - - 0.000% NOT YET STARTED

PART G. CHB CANAL LINING


103 Excavation Works cu.m. 1,513.00 163.23 246,966.99 0.329% 805.00 131,400.15 0.175% 210.00 34,278.30 0.046% 1,015.000 165,678.45 0.221% ON-GOING
704 (1) Masonry Units each 41,072.00 36.06 1,481,056.32 1.976% 14,290.00 515,297.40 0.687% 945.00 34,076.70 0.045% 15,235.000 549,374.10 0.733% ON-GOING
404 (1) a Reinforcing Steel kgs. 18,487.53 79.51 1,469,943.51 1.961% 6,432.29 511,431.38 0.682% 425.98 33,869.67 0.045% 6,858.270 545,301.05 0.727% ON-GOING
601 Sidewalk sq.m. 645.48 2,206.09 1,423,984.95 1.900% - - 0.000% - 0.000% - - 0.000% NOT YET STARTED

600 Curb and Gutter l.m. 600.00 1,300.29 780,174.17 1.041% - - 0.000% - 0.000% - - 0.000% NOT YET STARTED

PART H. MISCELLANEOUS STRUCTURES


605 (1) c1 Road Sign (Warning Signs & Regulatory each 10.00 3,965.00 39,650.00 0.053% - - 0.000% - 0.000% - - 0.000% NOT YET STARTED

Reflectorized Thermoplastic Pavement


612 sq.m. 1,205.25 732.00 882,243.00 1.177% - - 0.000% - 0.000% - - 0.000% NOT YET STARTED
Markings
TOTAL PHP 74,963,896.00 100.000% 65,021,378.51 86.738% 102,224.67 0.136% 65,123,603.18 86.875%
Time Frame 340 Cal. Days
Time Elapsed 253 Cal. Days
Work Schedule 74.412% (Based on time elapsed, revised Bar chart/PERT CPM needed to submit by contractor)
Work Accomplishment 86.875%
Variance 12.463% AHEAD OF SCHEDULE
Approved Time Suspension Approved Time Extension Additional Variation Order
From To ETT No. of Days Expiration Date VO # Amount Add'l Days Expiration Date
Additional Data March 30, 2020 May 3, 2020 1 1 6,067,642.50 120 CD October 17, 2020
Approved Budget Cost ₱ 74,963,896.00 2 2 27,879.76 None October 17, 2020
Total Cost Incurred (Total Disbursement) ₱ 57,753,937.07 3 3
Seed Money (15%) ₱ 10,330,256.06 Total 35 CD Total Total 6,095,522.26 120 CD

Prepared by : Checked by : Approved by :

ROMEL B. CADION JOSE PASTOR P. DELA CERNA III ALBERT D. YULO


Engineer II Engineer IV Provincial Engineer
Chief, Maintenance Division
PROVINCIAL ENGINEER'S OFFICE
Provincial Capitol, Malaybalay City
STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED
CONTRACT REFERENCE NO. : 2019-102
PROJECT NAME : Concreting of Jct. (Manolo Fortich) Lingi-on Road

CONTRACTOR : JT GAMOLO CONSTRUCTION

As of : July 22, 2020


Original Contract Time : 220 CALENDAR DAYS
Revised Contract Time : 340 CALENDAR DAYS
Date of Effectivity of Contract : October 09, 2019
Original Contract Amount : Php 68,868,373.74
Revised Contract Amount (VO#1) : Php 74,936,016.24
Revised Contract Amount (VO#2) : Php 74,963,896.00
Original Expiry date : May 15, 2020
Revised Expiry date : October 17, 2020

Effectivity of Time Suspension : March 30, 2020


Shutdown days due to Suspension of
: 35 days
Work
Effectivity of Resume Order : May 4, 2020

Total calendar days Elapsed to Date : 253 days


Total calendar days Remaining to Date : 87 days
Contract Time Elapsed (After Extension) :
Percentage of Time Elapsed (%) : 74.412%
Schedule of Work Accomplishment -
: 74.412%
Planned (%)
Percentage of Work Accomplished -
: 86.875%
Actual (%)
Variance (%) (+/-) (This Week) : 12.463%
Prepared by:

ROMEL B. CADION
Engineer II

Checked by: Approved by:

JOSE PASTOR P. DELA CERNA III ALBERT D. YULO


Engineer IV Provincial Engineer
Chief-Maintenance Division
POURING DATE
Concrete Breaking
December 02, 2019 301.50 m December 16, 2019
December 06, 2019 301.50 m December 20, 2019
December 12, 2019 288.00 m December 26, 2019
December 18, 2019 288.00 m January 01, 2020
January 10, 2020 324.00 m January 24, 2020
January 14, 2020 252.00 m January 28, 2020
January 20, 2020 288.00 m February 03, 2020
January 21, 2020 288.00 m February 04, 2020
January 29, 2020 297.00 m February 12, 2020
February 04, 2020 351.00 m February 18, 2020
February 13, 2020 274.50 m February 27, 2020
February 15, 2020 279.00 m February 29, 2020
February 19, 2020 288.00 m March 04, 2020
February 21, 2020 229.50 m March 06, 2020
February 28, 2020 288.00 m March 13, 2020
March 04, 2020 279.00 m March 18, 2020
March 09, 2020 324.00 m March 23, 2020
March 14, 2020 283.50 m March 28, 2020
March 19, 2020 283.50 m April 02, 2020
April 30, 2020 333.00 m May 14, 2020
May 06, 2020 288.00 m May 20, 2020
May 12, 2020 324.00 m May 26, 2020
May 15, 2020 274.50 m May 29, 2020
May 20, 2020 288.00 m June 03, 2020
May 26, 2020 288.00 m June 09, 2020 4+338.00 4+626.00 R/L 288.00
May 28, 2020 405.00 m June 11, 2020 3+579.00 3+984.00 L/L 405.00
June 01, 2020 324.00 m June 15, 2020 2+982.00 3+306.00 L/L 324.00
June 05, 2020 288.00 m June 19, 2020 2+092.00 2+380.00 R/L 288.00
June 11, 2020 310.50 m June 25, 2020 4+020.00 4+330.50 R/L 310.50
June 17, 2020 121.50 m July 01, 2020 3+889.50 4+011.00 R/L 121.50
June 17, 2020 168.00 m July 01, 2020 4+632.00 4+800.00 L/L 168.00
June 26, 2020 328.50 m July 10, 2020 4+309.50 4+638.00 L/L 328.50
July 14, 2020 292.50 m July 28, 2020 4+611.00 4+800.00 R/L 292.50
(plus gap)
PROVINCIAL ENGINEER'S OFFICE
Provincial Capitol, Malaybalay City
WEEKLY REPORT No. 38

Name of Project : : Concreting of Jct. (Manolo Fortich) Lingi-on Road


Contract Reference No. : : 2019-102
Project Location : : Manolo Fortich, Bukidnon
Contract Amount (RMI) : Php 74,963,896.00
Revised Contract Amount :
Contractor : : JT GAMOLO CONSTRUCTION
Start of Contract : October 09, 2019
End of Contract : May 15, 2020
Revised End of Contract : -
Period covered : October 06, 2017 - October 16, 2017

Previous This Period To date


Planned Accomplishment 2.845% 2.24% 5.080%
Actual Accomplishment 0.748% 0.892% 1.639%
Variance -2.097% -1.343% -3.441%

Activities of the Week:


1. Surplus Common Excavation
2. Sub Grade Preparation
3. Aggregate Sub Base Coarse
4. Portland Cement Concrete Pavement( sta. 0+300.00 - sta. 0+650.00)

Projected Activities for the following week:


1. Continue to excavate unsuitable materials.
2. Sub Grade Preparation
3. Deliveries, spreading and compaction of Item 200
4. Pouring of Concrete

Weather and Unworkable Time:


No. of rainfall hours Unworkable Time (Days)
This Period To date This Period To date

Remarks:
1. Contractor needs to catch up their activities and provide necessary facilities for engineer.

Prepared by: Checked by:


KAREN M. GAMOLO LEIZEL G. SABANDAL
Project Engineer Engineer II
Reviewed by: Approved:

BONIFACIO G. SUAREZ ALBERT D. YULO


Engineer IV Provincial Engineer
Chief, Maintenance Division
CONCRETING OF JCT.(VALENCIA-
BATANGAN) LALIGAN ROAD
VALENCIA CITY, BUKIDNON
MEETING

CONCRETING OF JCT.(VALENCIA-
BATANGAN) LALIGAN ROAD
VALENCIA CITY, BUKIDNON

PLAN & POW


MAINTENANCE OF ROADS &
BRIDGES @ VALENCIA A AREA
2017

VARIATION 1

MAINTENANCE OF ROADS &


BRIDGES @ VALENCIA B AREA
2017
VARIATION 1

CONCRETING OF JCT.(VALENCIA-
BATANGAN) LALIGAN ROAD
VALENCIA CITY, BUKIDNON
DIAL

CONCRETING OF JCT.(VALENCIA-
BATANGAN) LALIGAN ROAD
VALENCIA CITY, BUKIDNON
PERT/CPM

LEIZEL G. SABANDAL
TRAVEL ORDER

CONCRETING OF JCT.(VALENCIA-
BATANGAN) LALIGAN ROAD
VALENCIA CITY, BUKIDNON
ACCOMPLISHMENT REPORT

LEIZEL G. SABANDAL
TRAVEL REPORT
MAINTENANCE OF ROADS &
BRIDGES @ VALENCIA A AREA
2017

POW & STRAIGHT LINE


MAINTENANCE OF ROADS &
BRIDGES @ VALENCIA B AREA
2017

POW & STRAIGHT LINE

REHABILITATION OF BARANGAY
ROADS @VALENCIA AREA 2017
POW

MAINTENANCE OF ROADS &


BRIDGES @ VALENCIA A & B
AREA 2016

VARIATIONS

You might also like