Personal Details:
Date of Birth: 22-Nov-1988 – Participated in Paper Presentation STHAPANA-2k9 conducted by VNR
Nationality: India Vignana JyothiInstitute of Engineering & Technology in area of concrete
(Slurry Infiltrated Mat Concrete (SIMCON)).
Residency: KSA
Family status: Married Availability:
Current Location: Al-Hofuf, KSA Immediately
Iqama Status: Transferable Professional Profile:
Professional Civil Engineer over 10+ years experienced in the Project
Education: Management, Designing, Quality Inspections, Estimation, planning and
Execution of Buildings, Roads, bridges, transmission line towers and
PHD – Civil Engineering(ongoing from 2018)
underground systems. Seeking a position in which engineering expertise
Career Point University can be put to good use.
M.Tech-Structural Engineering My progressive engineering experience has provided me with the
opportunity to develop strong client relation building skills and an ability to
Jawaharlal Nehru Technological University: 2014 lead multi-disciplinary teams. I am experienced at Designing, Project
B.Tech-Civil Engineering Management, Quality Management,planning & overseeing the
construction and maintenance of structures and facilities.
Jawaharlal Nehru Technological University: 2010 .
Project Management Professional (PMP) IT SKILLS:
STAAD-PRO
Primavera –P6
E-TABS
Microsoft Project 2013 - MSP SAP-2000
AUTOCAD
Agile Methodologies overview CIVIL 3D LAND DESKTOP
PRIMAVERA-P6
Agile & Scrum Overview
MICROSOFT PROJECT- MSP
QMS Auditor / Lead Auditor Course EARTHWORK PROGRAM
PROKON
Quality Management Essentials Simplified MS-OFFICE
Apply Finance Concept for Smart Project Management
Cash and Credit Management for Business EXPERIENCE:
Negotiation – Understanding Personality Types
Learn the truth about AGILE vs WATERFALL ALOTHMAN Consultants-Saudi Electricity Company – K.S.A
Civil Site Engineer-Project Management Department (PMD)
BPMN 2.0, or Business Process Model and Notation
May-2017 – Present
Supply Chain Management that Delivers a competitive edge
Projects
Affiliations: (1) North uthmaniya 52 (115kV/13.8kV- AIS substation)
(2) Aindar 30 (115kV/13.8kV- AIS substation)
(3) Qatar road-1 s/s (115kV/13.8kV- GIS substation)
Member of Saudi Council of Engineers – K.S.A
(4) Qatar road-2 s/s (115kV/13.8kV- GIS substation)
Member of Institution of Civil Engineers (I.C.E) - UK (5) Khalidiyah s/s (115kV/13.8kV- GIS substation)
(6) Abqaiq-2 s/s (115kV/13.8kV- GIS substation)
Member of Indian Engineers Forum- Dammam
(7) Mazrueah s/s (115kV/13.8kV- GIS substation)
(8) Mansoorah s/s (115kV/13.8kV- GIS substation)
Awards: (9) Jabal al qarah s/s(115kV/13.8kV- GIS substation)
(10) Abqaiq (Overhead Transmission Line- 230 Kv)
(11) Umm al arad (Overhead Transmission Line- 115 Kv)
– Stood first in Bridge modelling at TECHNOZION ‘09 conducted by (12) Urariyah (Overhead Transmission Line- 115 Kv)
National Institute of technology, Warangal (NIT WARANGAL) - (13) SAOO (Overhead Transmission Line- 115 Kv)
2009
Responsibilities:
– Stood second in Inquest at TECHNOZION ‘09 conducted by
National Institute of technology, Warangal. (NIT WARANGAL)-2009
(1) Inspections of precast concrete slabs (double tee, hollow core),
columns, beams, staircases, corbels, parapet, scupper drains, canopies,
– Stood first in Bridge model making at COLLOQUIUM ‘2010
manholes, hand holes, firewalls, splash blocks, boundary wall panels at
conducted by Mufakkam jah college of engineering, Hyderabad
prainsa, alkifah precast factories and ensure that it is performed as per
approval from client. (2) Inspection of Erection and Installation of precast
– Stood first in Fluid mechanics Laboratory experiments at
COLLOQUIUM ‘2010 conducted by mufakkam jah college of concrete slabs (double tee, hollow core), columns, beams, staircases,
engineering, Hyderabad corbels, parapet, scupper drains, canopies, manholes, hand holes,
1
RR
Syed Munawar Ali –(BTech, MTech)- PHD(pursuing)
Civil Engineer
firewalls, splash blocks, boundary wall panels at project sites and and hand hole covers, cat eyes, signboards, sub base, base course,
ensure that it is performed as per approved IFC drawing. binder course, wearing course, plumbing pipes, sewer pipes, lavatory
(3) Review of method statement (MOS) of erection, concrete dormitories etc. and ensuring that material arrived at site are as approval
placements, rebar installation, transportation of materials, steel from client. (19) Reporting to sr transmission Engineer
structure erection etc. for proper procedure to be followed as per (20) Coordination with Main-contractor, Sub-Contractor, MEP engineers
SEC standards and ensuring HSE at all times submitted by and design engineers
contractor. (21) Checking, Reviewing and approved Project technical documents
(4) Inspection of trial mix at precast concrete and ready-mix such as Material submittal, Method Statement and drawings.
concrete factories, ensure that it is performed as per approval from (22) Progress monitoring as per planned schedule, review and reporting
client and international standards and SEC standards are being (23) Reviewing shop drawing, design drawing and specification
followed. (24) Project management, construction supervision and material
(5) Inspection of concrete delivery, concrete temperature, concrete inspection (25) Supervising tendering procedures and putting together
slump, delivery ticket, Rebar and formwork at precast factories and proposals
ready-mix concrete at site for various structures like retaining walls (26) Thinking both creatively and logically to resolve design and
,raft foundations, cast insitu columns, cast insitu beams, cast insitu development problems
slabs, transformer foundations, boundary wall foundations, service (27) Managing budgets and other project resources and scheduling
transformer foundations, monopoles foundations, capacitor bank material and equipment purchases and delivery
foundations, circuit breaker foundations, post insulator foundations, (28) Gather actual data from the construction site to assesses/analyses
current transformer foundations, disconnector switch foundations, some problem encountered during the implementation in the aid of
gantry structure foundations, fence foundations, duct banks, cable establishing correction procedure in the future.
trenches, GIB foundations, PACU foundations, PACU support (29) Conduct inspection of every activity in the construction of stages prior
structure foundations and ensure that it is performed as per approval to execution to ensure compliance with contract specifications, approved
from client. (6) Inspection of Auguring of pile foundations, concrete Method statement, Material submittal and working drawing.
pouring for transmission line towers, pad and chimney foundations (30) Has over all responsibilities in ensuring safety at all times of the
for transmission line towers and other isolated support structures workers in conduct of civil work as per client’s approved safety regulation.
precast foundations at site and ensure that it is performed as per (31) Prepare all necessary documents for the turn-over of the project
approval from client. (32) Preparation of Daily, weekly, Monthly Progress reports and attending
(7) Witness concrete placement and ensure quality control with weekly meeting with client, contractor and subcontractor.
specific standards at site and precast factory, performed as per
approval from client.
(8) Inspection of rebar’s and formwork prior to concrete placement at
site and ensure it is done as per approved IFC drawing.
(9) Witness bore hole tests, soil investigation and uplift pile load test ALOTHMAN Consultants-Saudi Electricity Company – K.S.A
for substations buildings and transmission line towers. Civil Site Engineer-Project Management Department (PMD)
(10) Inspection for erection of transmission line towers, gantry May-2016 – April 2017
towers, circuit breakers, transformers, post insulators, GIB, voltage
transformer, service transformer, capacitor banks etc.
(11) Inspection of finishing works such as elastomeric cementitious Projects
Construction Management for 380KV Substation and 380KV
painting for basement, manholes and hand holes, Self-levelling
Transmission Line Work Associated with Integration of PP-9
epoxy, floor hardener, raised floor tiles, ceiling tiles, internal and Expansion Project.
external painting, internal and internal finishing, and application of
coal tar epoxy, polyurethane painting, industrial door and gate Responsibilities:
painting.
(12) Inspection of stubs installations, brick work, door installation,
precast slab cover installation, door accessories, gate accessories, (1) Inspections of precast concrete slabs (double tee, hollow core),
signboards installation, lightning mast and lightning pole installation. columns, beams, staircases, corbels, parapet, scupper drains, canopies,
(13) Inspection of Access road, backfill, sub base, base course, manholes, hand holes, firewalls, splash blocks, boundary wall panels at
asphalt, road marking, cat eyes, kerbstone, sewer line, waterline, priainsa, alkifah precast factories and ensure that it is performed as per
waterproofing of roof, waterproofing of canopies, water proofing approval from client. (2) Inspection of Erection and Installation of precast
tanking system, aluminium flashing installation, roof tiles on concrete slabs (double tee, hollow core), columns, beams, staircases,
waterproofing. corbels, parapet, scupper drains, canopies, manholes, hand holes,
(14) Witness FDT for Access road, backfill, cutting, sub base, base firewalls, splash blocks, boundary wall panels at project sites and ensure
course. that it is performed as per approved IFC drawing.
(15) Inspection of tiles in toilet and battery room. (3) Review of method statement (MOS) of erection, concrete placements,
(16) Witnessed core cutting for asphalt, concrete crushing, and rebar installation, transportation of materials, steel structure erection etc.
preparation of concrete cylinders for laboratory testing. for proper procedure to be followed as per SEC standards and ensuring
(17) Inspections of brick work for walls, column alignments, wall HSE at all times submitted by contractor.
panel’s alignment, anchor bolts placement, stubs etc. (4) Inspection of trial mix at precast concrete and ready-mix concrete
(18) Inspection of material for waterproofing, concrete, self-level factories, ensure that it is performed as per approval from client and
epoxy, floor hardener, painting material, doors, door frames, tiles, international standards and SEC standards are being followed.
aluminium flashing, steel structure, tower material, rebar’s, manhole (5) Inspection of concrete delivery, concrete temperature, concrete slump,
delivery ticket, Rebar and formwork at precast factories and ready-mix
2
RR
Syed Munawar Ali –(BTech, MTech)- PHD(pursuing)
Civil Engineer
concrete at site for various structures like retaining walls ,raft (24) Supervising tendering procedures and putting together proposals (25)
foundations, cast insitu columns, cast insitu beams, cast insitu slabs, Thinking both creatively and logically to resolve design and development
transformer foundations, boundary wall foundations, service problems
transformer foundations, monopoles foundations, capacitor bank (26) Managing budgets and other project resources and scheduling
foundations, circuit breaker foundations, post insulator foundations, material and equipment purchases and delivery
current transformer foundations, disconnector switch foundations, (27) Gather actual data from the construction site to assesses/analyses
gantry structure foundations, fence foundations, duct banks, cable some problem encountered during the implementation in the aid of
trenches, GIB foundations, PACU foundations, PACU support establishing correction procedure in the future
structure foundations and ensure that it is performed as per approval (28) Conduct inspection of every activity in the construction of stages prior
from client. to execution to ensure compliance with contract specifications, approved
(6) Witness concrete placement and ensure quality control with Method statement, Material submittal and working drawing.
specific standards at site and precast factory, performed as per (29) Has over all responsibilities in ensuring safety at all times of the
approval from client. workers in conduct of civil work as per client’s approved safety regulation.
(7) Inspection of rebar’s and formwork prior to concrete placement at (30) Prepare all necessary documents for the turn-over of the project
site and ensure it is done as per approved IFC drawing. (31) Preparation of Daily, weekly, Monthly Progress reports and attending
(8) Witness bore hole tests and soil investigation for substations weekly meeting with client, contractor and subcontractor.
buildings and transmission line towers.
(9) Inspection for erection of transmission line towers, gantry towers,
circuit breakers, transformers, post insulators, GIB, voltage
transformer, service transformer, capacitor banks etc.
(10) Inspection of finishing works such as elastomeric cementitious Abdul Ali Al Ajmi Co. – K.S.A
painting for basement, manholes and hand holes, Self-levelling Civil Site Engineer-Road and Bridges
epoxy, floor hardener, raised floor tiles, ceiling tiles, internal and May-2012 – April 2016
external painting, internal and internal finishing, and application of
coal tar epoxy, polyurethane painting, industrial door and gate
painting. Reporting to the Sr. transmission specialist/project Projects
Engineer. Construction supervision of 8lane, 61kms expressway
MOT project No- 10606
(11) Inspection of stubs installations, brick work, door installation,
precast slab cover installation, door accessories, gate accessories, Responsibilities:
signboards installation, lightning mast and lightning pole installation.
(1) Construction of abuhadrea bridge at km 57+592 Length:484.35m;
(12) Inspection of Access road, backfill, sub base, base course,
Span Arrangement: (29.25m x15m) +(22.8m x 2); Foundation1.5m depth
asphalt, road marking, cat eyes, kerbstone, sewer line, waterline, raft foundation; superstructure: precast, prestressed T-BEAM girder.
waterproofing of roof, waterproofing of canopies, water proofing (2) Construction Supervision of Bridge (0+000) at km 0+245
tanking system, aluminium flashing installation, roof tiles on Length:353.100m; Span Arrangement: (28.10m x 11m) +(22.0m x 2);
waterproofing. Foundation 1.5m depth raft foundation; superstructure: precast,
(13) Witness FDT for Access road, backfill, cutting, sub base, base prestressed T-BEAM girder.
course. (3) Responsible for preparation of BBS, False work for structures, quality
control as per MOT & AASHTO specifications.
(14) Inspection of tiles in toilet and battery room.
(4) Preparation of shop Drawing’s
(15) Witnessed core cutting for asphalt, concrete crushing, and (5) Preparation of coordinates, and level’s
preparation of concrete cylinders for laboratory testing. (6) Estimating the concrete and steel quantities
(16) Inspections of brick work for walls, column alignments, wall (7) Responsible for Designs, Review and supervision of Bridges works,
panel’s alignment, anchor bolts placement, stubs etc. approval of the working drawings, bar bending schedule etc. Report to
(17) Inspection of material for waterproofing, concrete, self-level Project Manager on progress and difficulties faced during construction.
epoxy, floor hardener, painting material, doors, door frames, tiles, (8) Construction supervision and Estimation the quantities of
embankment, subgrade, Aggregate base course, bitumen base course,
aluminium flashing, steel structure, tower material, rebar’s, manhole bitumen wearing course, road marking(paint), cat eyes, ceramic tiles,
and hand hole covers, cat eyes, signboards, sub base, base course, kerb stone and interlocks of 61+000 Km’s.
binder course, wearing course, plumbing pipes, sewer pipes, (9) Raising RFI’S and conducting the inspection.
lavatory dormitories etc. and ensuring that material arrived at site are (10) Attend the meeting’s with Ministry of transport.
as approval from client. (18) Reporting to the Sr. transmission (11) Do all that is possible to see that the construction work is executed
specialist/project Engineer. in accordance with the technical specifications’ and other contract
documents.
(19) Coordination with Main-contractor, Sub-Contractor, MEP
(12)Responsible for construction and Execution of day to day, NGL
engineers and design engineers recording by auto – level, Total Station, clearing & grubbing, earthwork
(20) Checking, Reviewing and approved Project technical documents embankment, Hard-Cutting, sub-grade, ABC, BBC, BWC, New Jersey
such as Material submittal, Method Statement and drawings. Barrier, Interlock, Ceramic Tiles, Cat Eyes, Road Marking, Upvc Duct
(21) Progress monitoring as per planned schedule, review and Installation, Kerb stone and other utility for highway and
reporting Bridges(mentioned in BOQ), inspection of works to ensure that they are
(22) Reviewing shop drawing, design drawing and specification carried out in compliance with the contract specifications and as per
AASHTO,MOC(K.S.A),MOT(K.S.A).
(23) Project management, construction supervision and material
(13) Preparation of Daily Progress report,Weekly Progress Report and
inspection Monthly Progress Report / showing the deployment of machinery &
manpower location wise on the basis of targeted quantity vis-à-vis
achieved quantity-executed at site and prepare a relevant submission to
3
RR
Syed Munawar Ali –(BTech, MTech)- PHD(pursuing)
Civil Engineer
Projects
Construction of Type I, II, III, IVA, IVB, VA, VB Quarters, RPF
Barrack, Training Centre, Administrative Building, GM’s Bungalow,
other service buildings Transit Accommodation I & II, Rest House,
Officer’s Club House along with allied infrastructure for new Zonal
Headquarters for South East Central Railway, Bilaspur (Package – I
& II).
Activities Involved:
1) Involved in project monitoring and management activities right
from activity start-up to delivery to the client.
2) Execution of different items of structural foundations works like
Raft, Pile, Isolated Footing, columns, Slabs (PT & Non-PT)
3) Various finishing works like block masonry, plastering, false
ceiling & painting
4) External facade glazing and ACP cladding.
5) Co-ordination with project consultants (Structural & utilities
services), contractor and all agencies included.
6) BBS checking as per the drawings issued by the designers and
consultant