Professional Documents
Culture Documents
Abstract — Over the last two decades, the end-winding vibration frequency resulting from the operating force of the machine. In
monitoring of large generators and motors has been rendered other words, the purpose of the bump test is to locate
possible by various methods. This paper focuses on our components of the generator stator that have natural
experiences with nonconductive and nonmetallic fiber optic mechanical resonant frequencies near the magnetic operating
accelerometers. Over 2000 of these accelerometers have been frequencies of the unit. If the natural frequency of certain
installed in the field on various types and sizes of large rotating components, such as the phase leads, is close to the operating
machines. frequency, they may become mechanically excited. Any
excessive excitation may result in fatigue failure of the
Data obtained from the accelerometer under different operating
conductors or their insulation. By allowing resonant excitation
conditions and their interpretation have provided reliable
information and valuable knowledge to establish guidelines for
to become excessive or to last long enough, the epoxy bonds,
acceptable levels of end-winding vibration. But proper which consolidate the windings into a unified structure, may
interpretation also requires identification of the frequencies crack, and general or localized loosening may develop. This
where each vibration occurs. The combined effects of amplitude, may cause secondary bond cracking and additional loosening,
conversion of acceleration to displacement as a function of altering the natural frequency of the winding and making it
frequencies of the vibration, represent the true method to dangerously close to the resonant frequency formed by the
evaluate the level of stiffness of the end-winding system. electromagnetic forces. In other words, the mechanism used to
stiffen the end-windings must be carefully designed in order to
Keywords: Generator; End-windings; Vibration; Monitoring; limit the natural process of end-winding degradation and in no
Accelerometer form or any fashion, contribute to it.
I. INTRODUCTION Experience in the field proved to engineers that other
factors were affecting the stiffening of the end-windings.
Monitoring the end-windings of large generators has
Operating conditions such as temperature, unit active and
become a basic need to understand its electrical and mechanical
reactive loads and external stresses on the machine were also
condition as well as the condition of the generator end-
contributing to the loosening process. The need for a
windings, phase leads and connection ring [1, 2, 3].
permanent method to monitor the end-windings, connection
Electromagnetic forces are the main cause for stator end-
ring and/or phase lead terminals tightness or degree of
windings vibration that may create numerous problems.
loosening had become necessary. This aspect is heightened by
Essentially, stator vibration, which is caused by double
the fact that generator owners are increasing the period
frequency (100 or 120 Hz) operating forces for a 2 pole
between machine outages, in order to maximize the output of
generator, i.e. speed of the passing of the rotor poles, can
their fleet. Access to end-winding vibration of large machines
loosen the end turns over time and eventually some of the
and especially hydrogen-cooled types is becoming more and
following problems may result: erosion of coil insulation,
more difficult. It became a basic need for proper management
precipitating a ground fault; breakage of coil strands, leading to
of all generators to be able to provide operation and
overheating; and weakened end-windings, decreasing rigidity
maintenance engineers real time information on end-winding,
of the structure. The electromagnetic forces are essential to the
phase lead, connection ring vibration levels, and spectral
operation of the machines, but with time, its negative side
response of these vibrations [4]. A safe and reliable method for
effects on the end-windings rigidity will be observed. Thus,
constant measurement of these vibration levels became
over time, stator vibration can loosen the end-windings, despite
necessary.
safeguards introduced by generator manufacturers to stiffen the
end-winding bracing system. II. END-WINDING MONITORING SOLUTION
Some generator designs unfortunately created more Over the past 25 years of VibroSystM's field of experience
problems than solutions in attempting to build a better, bigger in the installation of its various sensors on generators, it has
and more effective machine despite a highly competitive always been imposed by utility personnel that cabling or
market. Generator manufacturers were well aware of the need sensors installed on their generators be positioned to avoid the
to evaluate the bracing system used to stiffen the end-windings high voltage part of the generator. However, to obtain a safe
of their machines. For newly built generators, the bump test is vibration monitoring of the end-windings, it was necessary to
a good off-line evaluation of the stiffening mechanism. Its have access to the high voltage area of the machine despite the
main purpose is to make sure the natural frequency of the many challenges it offered. May it be air gap cabling exiting
stiffening process is as far as possible from the double
286
The installation manual detailing every step required to
correctly locate, install and route the FOA measuring devices
inside a hydrogen-cooled machine must be respected to avoid
any doubts when interpreting the results. Examples of the
installation of the fiber optic accelerometer on an end-winding
“Fig. 3”, cable installation and exit through a penetration flange
for hydrogen-cooled machines “Fig. 4” are taken from this
manual.
On a turbo-generator, it is typically recommended to install Figure 4. Installation of penetration flange on generator casing exposing the
at each generator end (turbine end and exciter end) 6 sensors in hydrogen side of the plate before it is closed and fixed to the flange.
radial axis and 1 for tangential axis of the end-basket, thus
providing a total of 14 vibration inputs per machine “Fig. 1”. IV. FIELD EXPERIENCE
This is done by means of 5 FOA-100E accelerometers and 1 Due to the importance of the information provided by these
FOA-200 bi-axial accelerometer for both radial and tangential. accelerometers, it is mandatory that a certified technician
Monitoring the axial vibration is usually less significant and supervise the installation in order to avoid errors that become
overlooked, but if a customer wishes to do so, a FOA-200 close to impossible to repair once the special epoxies have
accelerometer may be substituted for one of the FOA-100E at hardened and the machine is closed and operating. The
each end of the machine. The fiber optic accelerometers are following are typical errors that were observed:
usually mounted at the far end of the end-windings “Fig. 2”.
1. Probes installed in an improper location. One original
It is recommended to monitor both ends of the turbo- equipment manufacturer installed all FOAs for
generator as mechanical vibration from the machine as well as tangential monitoring direction, which represents an
phase bus leads may generate different end-winding vibration axis where vibration was least likely to occur.
behaviour, even amongst bars of the same end. Nevertheless,
the fiber optic accelerometers can always be installed at any
other locations on the generator.
287
Field experience has provided various case studies which
have been presented at conferences [4, 5] and it is important to
note the typical initial reaction of users: Why is there only one
winding higher than others monitored? Disconnect the probe
with the high readings; there is probably a problem with the
accelerometers (!) Are you sure the probe is working?
Extensive field experience has demonstrated how FOA has a
high reliability rate and is a sturdy device considering that it is
a very precise, nonmetallic type probe.
Once tested, most of the returned probes met their original
specification, even those that were clearly mishandled and not
covered by any standard manufacturer’s warranty.
The few probes that were actually damaged would not
288
TABLE IV. END-WINDING VIBRATION TOLERANCES
289
We wish to quote Mr. B.S. Berstein, Project Manager,
Electrical System Division of The Electrical Power Research
Institute (EPRI) [6]:
“The single most important parameter influencing the
reliability of a rotation machine is the electrical insulation. If
the insulation fails to maintain its integrity during operation,
the equipment will fail. In practice, insulation does not fail at
once. Multiple stresses acting on the insulation – voltage
stress, mechanical forces, and thermal effects – all combine to
induce a slow but steady change in its nature over years.”
The fiber optic accelerometer presented in this paper has
shown to be a valuable tool for the generator owner to manage
the stresses acting upon the machine insulation. Providing real
time information on the end-winding condition allows utility
personnel to better manage a machine that generates revenues
and represents an important asset to its owners.
Complementing the end-winding vibration with measurements
of rotor temperature, stray flux, electromagnetic interference
patterns, shaft voltages and currents, as well as machine
operating conditions are solutions available today for the
proper operation and maintenance of generators that are
solicited ever more.
REFERENCES
[1] Clyde V. Maughan, Maughan Engineering Consultants, Schenectady,
NY, USA. “Monitoring of Generator Condition – and some Limitations
Thereof”. IEEE/EIC Conference, October 2005, Indianapolis, IN, USA.
[2] Mike Hoffer, Consmers Energy, Jackson, MI, USA. “Stator Bar
Vibration Sensors and Fiber-Optic Accelerometers – New Tools Used to
Measure Stator Winding Vibration in Large Turbine Generators”. EPRI
Winter Technical Workshop and TGUG Meeting, January 2003,
Orlando, FL, USA.
[3] M. R. Patel and J. M. Butler, “Endwinding vibrations in Large
Synchronous Generators”, IEEE Trans PAS, May 1983
[4] 2012 Electric Power Research Institute (EPRI) Phoenix TGU meeting:
“Generator Monitoring and Maintenance Workshop”
[5] FOA-Doble 2008-RM-8 2008 Doble Engineering Company –
74th Annual International Doble Client Conference
[6] Handbook to Assess Rotating Machine Insulation Condition, EPRI
EL-5036, Vol 16 1987
290