Professional Documents
Culture Documents
TCE.-M6-EL-TL-G SHEET i OF v
750-6801
DESIGN GUIDE
(NO. TCE.M6-EL-TL-G-750-6801
FOR
TRANSMISSION LINES
FLOPPY NO : TCE.M6-EL-FP-007
FILE NAME : M6-6801.DOC
REV.NO R1 R2 ISSUE
R1 94.4.25 Shs 180 of 181 and 181 of 181 updated for latest codes
and standards
ISSUE
R2
CONTENTS
1.0 SCOPE 1
12.0 EARTHING 30
ISSUE
R2
16.0 INSULATORS 53
FIG.7 CLAMPS 63
FIG.8 SPACERS 69
19.0 TOWERS 71
ISSUE
R2
ISSUE
R2
1.0 SCOPE
This guide covers the salient design features of overhead power lines of 66
kV to 400 kV on steel towers. The scope does not include protection and
switching equipment.
2.1 The standard nominal system voltages are 66, (110), 132, 220 and 400 kV
(rms). The 110 kV system is existing but not preferred. It is recommended
that limits of voltage tolerance be + 10% for voltages upto 220 kV and + 5%
for 400 kV based on allowable limits of the voltage ratings for which the
equipment is designed. The IS 12360 and IE Rules allows a voltage at the
consumers terminal for EHV upto 400 kV.
In the likelyhood of load growth, higher voltage and larger conductor may be
selected when the annual operating costs do not vary widely.
2.3 When selecting the transmission voltage, the present and future voltages in
the vicinity and neighbouring regions should be considered. The choice in
tying with a common voltage at the receiving end or neighbouring region
often has advantages over the choice of voltage based on lowest present cost.
Matching with existing transmission voltage will avoid additional step-
up/step-down transformers and associated switchgear.
ISSUE
R2
KV
ISSUE
R2
__________
E = 5.5 / L + KVA
√ 1.6 150
Where -
L = Distance of transmission in Km
ISSUE
R2
ISSUE
R2
ISSUE
R2
4.2.1 The all aluminium conductor (AAC) is used for low and medium voltage
lines. (Tarantula AAC conductor is some time used for HV lines).
4.2.2 The all aluminium alloy conductor (AAAC) has not yet found wide
application in India but is extensively used in many foreign countries because
of its following advantages and also much lesser cost than copper. (The
present cost in India is 30% more than that of ACSR).
Impedance of transmission circuits vary with the type, size and configuration
of the conductors. Impedance and susceptance parameters of phase
conductors to be considered in transmission line design are as given below.
Since the data tables in all reference handbooks is in miles/feet units, this has
been retained here also for easy application of the reference tables when
required.
5.1 Impedance
Z1 = Z2 = ra + j XL
ISSUE
R2
(a) Resistance
T+t
rdct = rdct20 x ---------
T + 20
The a.c. resistance at any frequency f will vary from the d.c. resistance
due to skin effect as follows :
f = frequency
(b) Inductance
ISSUE
R2
= Xa + Xd
ISSUE
R2
Factor
5.3 Susceptance
ISSUE
R2
rB = R [NR] 1/N
[R ]
__
Zs = / L ohms , where L is series inductance.
√ C
and C is the shunt capacitance per unit length of line. Thus, surge impedance
loading
It is that loading where the loss in reactive power due to load current (I2 XL)
is equal to the reactive power generated by the line capacitance (V2 / Xc).
5.4.2 With increased inter phase spacing and reduced bundle spacing the SIL
capacity of the line is reduced. The I2 R losses will get affected by change in
SIL.
ISSUE
R2
5.4.3 The concept of SIL gives a general idea of the load capability of a line and
allows comparing the approximate load capability of lines of different
voltages. Approximate values of surge impedance for single, double, triple
and quadruple bundle conductors used on EHV lines are 380, 300, 280 and
260 ohms.
5.4.4 It is usual to load short lines of low inductive reactance appreciably above
the SIL, and, because of stability limitations, to load long lines at lower than
SIL, unless series capacitor compensated. For stability reasons it is
recommended that the phase angle across the line including a voltage
transformation if it is part of the line) should not normally exceed 30o . For
example, line load in SIL for 230 kV line is 140 MVA for 300 miles, for the
same line of lengths 200 and 400 miles, the line loads would be
approximately 200 MVA (1.5 SIL) and 100 MVA (0.8 x SIL) respectively.
5.4.5 From reliability considerations, the line loading should be such that the
outage of a major line or generator will not cause over loading beyond the
short time capability of any of the paralleling lines or transformers, more
than 5% reduction of system voltage, or instability.
6.1 In EHV lines, because of relatively high tensions and large conductor sizes,
the wind pressure on the conductors and its effect on conductor vibrations
becomes significant. A tensioned conductor has several closely spaced
natural mechanical frequencies of oscillation and when certain frequencies of
wind induced forces corresponds to any of the natural frequencies of the
conductor, resonant vibration will occur.
These wind induced vertical vibrations are more or less always present but
most of the time they are harmless. Low and very high wind velocities do not
cause harmful vibrations. Excessive vibrations occurs only at wind velocities
which are less than and upto 25 km/hour in flat terrain. Turbulence helps to
reduce the vibrations and hence lines passing through hilly or irregular
terrain are less prone to vibrations. The frequency of the wind induced
vertical forces on the conductor is given by :
f = 2.065 V/d Hz
ISSUE
R2
The most favoured method for vibration control, to ensure that amplitude of
vibration is kept low so as to keep the dynamic strain induced in the
conductor to a permissible safe value, is by providing Stockbridge type
dampers. The damper consists of two hollow weights joined together with a
length of flexible steel cable which has a suitable attachment at its mid-point.
There are other variations to this type of dampers with adjustable type
weights.
ISSUE
R2
6.3 Galloping
Galloping causes large dynamic forces which could damage insulator strings,
conductors, fittings, spacers and cross-arms. It may also result in conductor
clashing, but the adoption of horizontal conductor formation greatly reduces
this danger. Some of the methods used in controlling galloping are (a) aero
dynamic stabilisers attached to the conductor in the form of narrow plastic
plates and (b) by insulated spacers interconnecting adjacent phases at the 1/3
points of the span.
ISSUE
R2
Corona induced oscillations occur only during rain and fog. These
oscillations and relatively small and normal damping for wind induced
conductor movements is adequate to control this type of oscillation.
7.1 The choice of conductor size will depend on factors like continuous and short
time current carrying capacity, length of the line to be considered for voltage
drop and power loss in transmission and the minimum conductor diameter
required to avoid corona. In addition, for higher voltages and long lines
(greater than 50 km) the charging current of the line will increase. This may
increase the current in the circuit depending on the power factor of that load
and consequently the corresponding change in I2 R and voltage regulation
should be checked. The charging KVA of a transmission line is
approximately = (KVL-L)2 x 3.13 x 10-3 per km.
7.2.1 The selection of conductor size from thermal consideration will be based on
maximum continuous current rating which is determined by the maximum
operating temperature of the conductor. For design purpose copper or ACSR
conductor total maximum temperature is usually restricted to 75oC as use of
this value has given good conductor performance from an annealing
standpoint. The annealing of copper and aluminium starts at 100oC. The
approximate maximum continuous current ratings of Cu and A1 conductors
are given in transmission line hand books. These are based on the formula
that the heat developed by I2 R loss is dissipated by convection and radiation.
Manufacturer’s test data should also be consulted. Rating of some of the
ISSUE
R2
ACSR conductors is given in Table 2 for a temperature rise of 30oC and 35oC
in an ambient of 40oC with a wind velocity of 2 feet per second. (2.16
Km/hrs)
If T1 = T2 (i.e. 75oC)
_____
Then I2 = I1 / ∆ t 2
√ ∆ t1
ISSUE
R2
The aluminium conductor area will be 1.6 times the copper equivalent area,
to carry the same current.
7.3 Corona
7.3.1 For EHV lines, specially 220 kV and above, the size of the conductor has to
be determined from corona consideration rather than current carrying
capacity. The breakdown strength of air at 76 cm mercury pressure and 25oC
is 30 kV peak per cm or 21.1 kV (rms) per cm. At any other barometric
pressure b cm and taoC the breakdown strength of air is δ 21.1 kV per cm.
Where δ = 3.92 b_
273 + ta
The value of the voltage at which the air breaks down and becomes a
conductor is the corona inception voltage. The phenomenon of corona
generates a faint glow, humming noise, radio interference (RI), conductor
vibration, ozone and energy loss. The visual corona inception voltage of a
conductor in fair-weather is given by -
m = roughness factor
= 1 for clean smooth conductor
= 0.82 for stranded conductors
go = V / √3__
r logn [D] kV (rms to neutral) per cm
[r]
ISSUE
R2
21.1 m δ r [1 + 0.3]
[ √δr ]
EHV transmission lines 400 kV and above use bundle conductors from the
stand point of corona performance. These are made up of 2, 3, 4 or more
conductors and are used as one phase conductor. The advantage of improved
corona performance and increased line loading of the bundle conductor is to
be weighed against increased cost and charging KVA. There is an optimum
number of sub-conductors and sub-conductors’ separation for bundle
conductors that will give an economically minimum voltage gradient on the
surface of the conductors. For 400 kV lines in India and upto 500 kV in
foreign countries, twin Moose bundle with 45 cm spacing is found to give
satisfactory corona and RI performance.
The basic expression for go in para 7.3.1 is generally true based on the
assumption that the conductors are separated by large distances from each
other and from ground relative to their diameters. For a transmission line
strung at height H above a equipotential ground plane, its effect is taken into
account by considering image charges of each conductor at distance 2H from
the conductor. In the case of a 3-phase line having bundle conductors with
horizontal configuration of phases, following Mangoldt formula has been
derived for the maximum voltage gradient on the surface of a subconductor
on the centre phase.
1 + (N-1) r/R x V / √3
9 (Max centre phase) = [ ( 2HavD ) ]
in kV rms/cm Nr logn [ (rB (D2 + 4H2av)½ ]
ISSUE
R2
= R (Nr) 1/N cm
(R)
Where
The gradient on the sub-conductor is not uniform due to the effect of the sub-
conductors on each other and varies as follows :
7.3.3 The conductor size should be chosen such that the normal design gradient of
a conductor should not exceed 17.5 kV/cm. At this value overhead lines do
not exhibit much corona in fair weather. As corona is a variable phenomenon
it is not practical or economical to design an EHV line such that there will be
no corona at all times. Bad weather such as fog, snow, rain may reduce the
corona starting voltage to as low as 0.7 of the fair-weather value. Also
surface irregularities like abrasions, scratches and contaminating particles are
dominant sources of corona.
ISSUE
R2
8.1 A breakdown of air causes dissipation of energy and that has to be supplied
by the power station. The corona current is mainly in phase with applied
voltage and forms a component of the line charging current. For lines of 220
kV and above serious attention has to be paid to corona loss and RI. A
weathered, (aged) conductor in use for more than 1½ year will have less
corona loss, audible noise and RI.
8..2 Lightning and switching surge will cause corona loss and in so doing it loses
energy while it travels and its amplitude decreases corresponding to lower
energy content. Corona thus helps to attenuate high voltage travelling waves.
Similarly, corona helps to reduce overvoltages on long open-circuited lines.
8.3.1 Many countries have conducted experiments to evaluate corona losses and
derived empirical formulas from the measurements and theoretical analysis.
However, they do not fit in for universal application. One of the more useful
formulas, valid for lines between 400 to 700 kV, (Project EHV, USA), giving
the corona loss in rein above fair weather loss, in KW/3 phase Km is given
in Table-3.
TABLE 3
CORONA LOSS IN RAIN
[ 1.6√3 ] 1
ISSUE
R2
For a region of warm, temperature, rainy climate the yearly average foul -
weather corona loss/km has been estimated to be about 3.5% of the value
computed from heavy rain test corona loss in snow, specially wet snow, can
exceed that in rain for snow, the test data of project EHV suggests a loss
multiplier of about 2 and the following equivalent rain rates.
8.3.2 Curves and procedures are also described in Transmission Line Reference
Book 345 kV and Above (EPRI) to enable a designer to estimate the likely
corona losses. However, due to the variable nature of the losses, the.
accuracy of the estimated value cannot be much better than ±30%.
Calculations show that during rain or snow, corona losses can go upto more
than 50 times that under fair weather. Since rain would be for 3 months in a
year and heavy rain would occur for only a short-time and on a short length
of line, the yearly average loss is estimated to be 5-10 KW/3 phase Km for
ISSUE
R2
voltages upto 500 kV. The cumulative annual average corona loss may
amount to 10% of I2 R loss at full load.
Studies of EHV line above 220 kV have shown that major fair weather losses
were insulator leakage losses. These losses are a function of the square of the
voltage. The representative values for strings having standard 146 x 254 mm
insulator units are as follows:
Watts per
Voltage kV string
345 60
500 95
8. 5 Radio-Interference
8.5,1 Other corona effects are audible noise, radio and television interference (RI,
TVI). Corona discharge process produces pulses of current and voltage
whose frequency range can cover a considerable portion of the radio and TV
broadcast bands. Most literature data available deal particularly with
interference in the radio band 535-1605 kHz and TV band 54-88 MHz. Both
RI and TVI come under the broad classification of radio noise which is
predominantly caused by corona discharges on the positive half cycle of
power frequency voltage.
For transmission lines below 500 kV audible noise level is sufficiently low
and of no concern but radio noise problem becomes acute above 345 kV.
Hence the 400 kV line has to be designed to have an acceptable radio noise,
and when so designed there normally will be no audible noise problem.
The level of radio noise that will cause interference will depend on factors
such as the transmission line geometry, weather condition, distance of the
transmission line to the communication receiving device, direction of the
antenna and the accepted signal to noise ratio. Signal to noise strengths
(.SNR) are expressed in terms of decibels (dB above 1. µV (micro volt/m)
This would be as follows:-
ISSUE
R2
Both measured by the same antenna and meter. The voltmeter, basically a
radio receiver, is calibrated to indicate the rms value, in micro, volts or dB
above 1 UV, of a sinusoidal input signal whose frequency is equal to the
tuning frequency of the meter. The frequency used in the measurements is
around 1 MHz for RI and 83 MHz for TVI. Investigations based on listening
tests have shown that a tolerable SNR for satisfactory broadcast and TV
reception is 25 dB. The broadcast signal strengths along the edges of a
proposed right-of-way (R.O.W.) may be measured or ascertained from signal
level contour maps prepared by radio stations. Then at a fixed lateral distance
from the outer conductor, the allowable limit of noise level, given by
minimum signal strength minus acceptable satisfactory signal-to-noise .ratio,
should not be exceeded. The minimum radio signal strength in rural/suburban
areas is about 60 dB (1000 µV/m) . In urban regions this would be 10 to 15
dB more. It is apparent that, a noise level which is tolerable in a high signal
strength area may not be tolerable in a low signal area.
The RI limits an, laid down by some European countries, range from 46 dB
to 57 dB measured at 500 kHz, at a lateral distance of 20 m from outer phase,
in average fair weather. .At 0.5 MHz the noise is 4.5 dB higher than at 1
MHz while at 2 MHz it is 8 dB lower than at 1 MHz. Also there is generally
a decrement of 8 to 10 dB at 1 MHz for every doubling of lateral distance
Therefore, a change of a few hundred feet in the right of way will aid in
protecting the communication service from RI.
ISSUE
R2
line voltage classes from 360 to 1500 kV. In these base curves, heavy rain (≥
12 mm/hour) RI figures are given for a lateral measuring location 15 m (50
ft) from an outside phase, for a typical ground resistivity of 100 Ohm.m and
for a measuring frequency of 1 MHz and radio noise meter bandwidth of 5
kHz. To determine precise RI level of a line whose geometry and other
measuring conditions differs from those of the base case designs, additional
curves are given which take into account the effect of variation of all the
above parameters and of different measuring distances. Using heavy rain RI
level of the line as obtained from these curves, the average fair weather RI
level, as suggested from experimental data, is 22 dB less than the heavy rain
RI level. The fair-weather value should not exceed the acceptable RI level
obtained from the relationship of (S-SNR) dB.
Based on investigations from operating lines and the results of tests at Project
UHV a comparative method has been adopted for determining the TVI level
of 3 phase transmission lines. The frequency spectra of corona noise
attenuates by an inverse frequency law. TVI is measured at picture carrier
frequency of 83 MHz and with 3 MHz bandwidth of the meter compared to
1 MHz frequency and 5 kHz bandwidth for RI levels. The net effect
(attenuation for frequency and noise adder for larger bandwidth) is that 10
dB must be subtracted from RI levels to determine the TVI levels.
9.1 If more than one conductor satisfies the requirements of current carrying
capacity and corona performance, then a study is required for optimisation of
conductor size. The cost of line conductor alone need be considered as the
cost of insulators and line termination equipment will be common for all
alternatives.
ISSUE
R2
V = Line Voltage, kV
or
= CA + P2m RJ
V2Cos2 φ
Pm = V Cos φ [ CA]1/2
[ RJ ]
ISSUE
R2
Rs/Km = C + T [ (1 + i)30 - 1 ]
[ i (1 + i)30 ]
9.4 In an overhead line the cost of conductor would be approximately 40% of the
total line cost, therefore it is important to select the conductor which will
give minimum capitalised and running costs of. line per Km along with
satisfactory technical requirements.
The weight and hence cost of towers are influenced by conductor parameters.
Factors affecting the choice of conductors based on structural conditions are
as follows:
In open terrain where few angle towers are required, longer spans will
be more economical. For lines with longer spans conductor, with
smaller Al/St area ratio should be chosen to give less sag. Lines with
many angle and dead-end towers will require shorter spans so that the
towers will be subject to lesser unbalanced tension during broken wire
conditions.
(b) Compactness
(d) Weight/Diameter
ISSUE
R2
ISSUE
R2
Moose -conductor creep history shows a creep of 500 mm/Km with 20%
UTS tension and 700 mm/Km with 25% UTS tension, over a period of 20
years. The creep overtension is 3578 Kg at 32o C erection temperature to
reduce the design sag from 9.88 m at (20% UTS) 3255 Kg tension to 8.99 m
at erection. The span being 350 m.
11.1 All EHV lines are provided with earth wire arranged above the phase
conductors and grounded at every tower. Their main purpose is to shield the
line conductors from direct lightning strokes by intercepting the strokes and
distributing the current in two or more paths, thereby reducing the voltage
drop. The earth wire also reduces the voltage stress, due to stroke, across the
insulator string, due to its coupling with the phase conductor.
ISSUE
R2
The lightning surge remains at the point struck, at tower top or midspan, till
the time taken by the surge to travel to ground through tower footings and the
reflected wave to return back to the incident point. For a mid-span stroke,
potential of the earth wire will be approximately one-half of the stroke
current times (Zg-Zm), where Zg is the surge impedance of the earth wire
and Zm the mutual surge impedance between the earth wire and line
conductor. The voltage on the earth wire may, therefore, cause flashover
from earth wire to conductor (known as back flashover), if the midspan
clearance between the earthwire and conductor is not adequate. This
clearance should be 1 to 1.5 metres more than that at the tower. The mid-
span clearance is the, direct distance between earth wire and top power
conductor, in case, of vertical or triangular formation of conductors, or outer
power conductors, in case of horizontal formation, at minimum temperature
and still air conditions. As per IS 5613, following values of mid-span
clearances may be considered.
ISSUE
R2
These should also meet the requirements of (a) shielding angle and (b) earth
wire sag to be not greater then 90 percent of the corresponding, power
conductor sag in still air conditions for the entire specified temperature
range.
Minimum Mid-span
Line Voltage kV Clearance Metres
66 3
110 4.5
132 6.1
220 8.5
400 9.0
11.4 Sizing
11.4.1 The earth wire should be adequate to carry the very short duration lightning
surge currents of about 100 kA without excessive overheating. The sizing
may be based on 200 microsecs short time and a safe temperature rise of
300o C, approximately same for Cu and steel, with bolted connections the
formula is -
Since the earth wire has to be under tension to provide for adequate mid span
clearance it has to be mechanically strong. The earth wire also has to
withstand the effects of eolian vibrations which are directly proportional to
the tension in it. From mechanical considerations, size will be higher than
that required for current rating and for EHV lines it is suggested as 70 sq.mm
(7/3.66 mm). This size of stranded, galvanised earth wire of 95 Kg/sq.mm
quality is found to be adequate to give the required strength. Vibration
dampers should also be provided to minimise fatigue damage.
For long life and protection against corrosion, the minimum guaranteed
weight of zinc coating should be 260 gm/sq.m of each uncoated strand wire
surface as specified in IS 4826.
ISSUE
R2
The tension/weight ratio of' ACSR earth conductor should be greater than
that of the power conductor to obtain a midspan clearance more than that at
the tower. It has been found that ACSR of size 12/3.0 mm AL + 7/3.0 mm
steel can conveniently be used as earth wire.
12.0 EARTHING
12.1 To reduce the earthwire potential and stress on the insulator at time of stroke
and also for safety,. it is essential to keep the tower footing resistance low.
This should be, as far as possible, not more than 20 ohms. The degree of
protection provided by earthwire depends on its ground resistance. In
practice it is difficult to obtain tower footing resistance of 10 ohms.
12.2 Earth wire is connected to the tower top generally by tension clamps and tin
plated copper earth bonds are used to connect earthwire to the towers which
in turn is earthed. The earth resistance will depend on soil resistivity at the
lower location. Soil conditions prevailing at the tower locations are to be
ascertained in dry season. This will ensure that the value of earth resistance
throughout the year is below this value. A general average valve is 100 ohm-
metre.
In this method one or more lengths of wires are buried in the backfill of the
tower foundation. If the wire, is arranged as several shorter radial wires it is
more effective than laid as one wire. The group of wires is connected to the
tower leg,. This method is inexpensive and used where the soil resistivity is
low.
12.3.2 Counterpoise
ISSUE
R2
confined to only upper layers of the soil. One or all four legs could be
earthed in this way depending upon the value of earth resistance required.
12.3.3 Rods/Pipes
Pipe/rod of 3 to 4 m long is driven into the ground near the tower and the top
of rod/pipe is connected to the tower leg by a suitable size wire/strip. This
method is costly but gives better results because with normal soil, ground
conductivity increases with depth.
If soil resistivity in very high near the tower location, the rod/pipe 3 to 4 m
long are buried in treated earth pits. The treated earth pits are filled with
charcoal/coke and salt and watered during dry season.
12.3.5.1 The tower footing resistance will depend on (a) type of electrode
configuration employed and (b) the soil resistivity. In all cases, sufficient
area must be exposed between the electrode and soil in order for the current
to spread over a large area.
a = rod/pipe radius, m
ISSUE
R2
a = wire radius, m
b = burial depth
12.3.5.3 In practice, a transmission line does not have a constant value of footing
resistance but a range of values, .depending on the composition of the soil
and its moisture content at the tower location. If the expected variation of
footing resistance about a mean value is less than half the average value, then
the average value can be used for any calculation purposes with an
acceptable error.
ISSUE
R2
13.2 However, if the rights of way of the two lines are close to each other, it is
necessary to determine the minimum safe separating distance that will not
induce more than 650 or 430 V, as required, in any -communication line that
may be in parallel with the power line.
V = 2π f MIL x S
L = Length of parallelism in Km
13.4 Each power line case is to be examined by the power and Telecom Co-
ordination Committee (PTCC), regional in the case of lines upto 132 kV and
central (CEA) in the case of lines above 132 kV, who will issue the final
clearance.
ISSUE
R2
The insulation design must prevent flashover during these voltage stresses
and if such flashover occur they should be restricted at the protective arcing
horns and lightning surge arresters locations where the damage is not done.
ISSUE
R2
ISSUE
R2
14.2.1 The temporary overvoltages generally arise from faults, load rejection and
resonance. They are overvoltages having several successive peaks, with a
decrement of the amplitude such as to be comparable with a sustained
voltage at power frequency or at harmonic frequency. For voltages upto 245
kV the performance under power frequency, temporary overvoltages and
switching overvoltages is checked in general by a short duration (1 minute)
rms power frequency voltage test. On effectively grounded systems (Xo/Xl
≤ 3, Ro/Xl ≤ 1) the voltages on healthy phases during a line to ground fault
may reach 1.3 to 1.4 pu (1 pu = line to neutral crest voltage). Sustained
overvoltages on loss of load can be in the same range of values an fault
voltage and can exist for many cycles or seconds.
14.2.2 Switching surges are to be considered on systems of 345 kV and above. The
causes, magnitudes and waveshapes of switching surges are numerous. The
main causes are energisation/de-energisation of lines with or without
transformers/shunt reactors, de-energisation of reactors and capacitor banks,
out-of-phase switching and high speed reclosing. Field tests have indicated
the magnitude as high as 3.5 p.u. due to energising or high speed reclosing.
The use of preinsertion closing resistors of suitable value in the circuit
breakers can reduce this magnitude to less than 2.3 p.u. This allows
significant reduction in transmission line dimensions at 400 kV and above.
14.3.1 The critical flashover (CFO) voltage is the crest voltage that yields flashover
in 50% of the number of shots given to insulator strings or air-gap. This
inherent breakdown characteristics of large gaps is greatly influenced by
following types of gap geometry:
(a) The effect of the presence of insulator string and other hardware. This
is ex-pressed as the ratio of the shortest distance in air between
conductor and tower at no swing to the length of the porcelain string.
ISSUE
R2
(b) The ratio of the height of the insulator string from the ground plane to
the length of the porcelain insulator string.
(c) The ratio of the width of the tower leg/truss to the distance between
conductor to tower leg/truss.
14.3.2 Based on these gaps and string configurations, the spark over voltages have
been measured in field tests and in laboratories and the design data curves of
CFO voltages versus large gap spacings and insulator strings in proximity to
tower leg and truss, are available in EPRI/GEC Transmission Line Reference
Book for the switching and lightning surges of respective wave shapes and
also for 50-60 Hz power frequency. Some of these data curves are given in
Figs. 2 & 3.
14.4 Formula
14.4.1 Based on the large amount of experimental data from all over the world,
empirical relations called Paris formulas are found between the large air gaps
d in metres and the CFO voltage V50 crest. They are useful in the insulation
design of the line along with the detailed design curves mentioned earlier.
Following are the formulas, all dimensions in metre.
ISSUE
R2
14.5.1 The relationship between the 50% CFO voltage V50 kV crest and the
probable withstand voltage of a gap depends upon the following factors:
(a) In hundreds of test series the switching, surge flashover voltage values
for one gap geometry is found to deviate by an average of 5% of the
V50 value. This is called standard deviation Sf. The flash over
probability is found to be 0.2% at V50 (1-35f) and 99.8% at V50.
(1+3Sf). The accepted withstand voltage is therefore taken as V5o (1-
3Sf) for satisfactory switching insulation performance. Similarly for
lightning and power frequency, the considered standard deviations are
5% and 2% respectively and going by 2Sf for lightning and 3Sf for
power frequency below the respective CFO voltages is sufficient to
secure a satisfactory performance for these overvoltages.
(c) The factors which change the switching/ lightning surge flashover
strength of insulator string in combination with clearance gaps between
tower-leg/truss (this is called conductor-tower window) are as follows:
iv. Change from a single string to two strings in parallel gives about
3% reduction in the switching surge flashover strength. For most
practical purposes the lightning impulse strength of single and
several strings in parallel is the same.
(d) Rain has very little influence on the flashover strength of air gaps but
for gaps in combination with insulator strings there is a reduction in
ISSUE
R2
(f) Insulation strengths are directly proportional to relative air density. The
relative air density = 1.00 at a barometric pressure of 760 mm Hg and
25oC temperature. Tests have led to the conclusion that for insulators
and gaps with spacings greater than 0.76 m an insulation reduction of
2.5 percent per 300 m of altitude would be satisfactory.
ISSUE
R2
Horizontal and' inclined (V) strings remain more effective than vertical
strings in regions of heavy contamination.
14.6.1 In the range of vo1tage upto 245 kV switching over voltages are seldom a
major problem and insulation design is mainly based on withstand of
lightning overvoltages and power frequency short duration (1 minute)
overvoltages. The minimum electrical line clearances in use for line voltages
upto 245 kV 'have been specified in IS 5613 (P2 Section 1).
14.6.2 For higher voltages of 300 kV and above, the insulation has to be designed
for both lightning,. and switching over voltages. The switching surge
withstand value is rather inferior and for 300 kV and above this becomes the
most important consideration. The electrical clearances and selection of
insulation level will therefore be based on switching surges. The clearances
and conductor spacing are indicated in para 4.3.
14.6.3 The recommended correlation between the rated lightning and switching
impulse withstand voltages and between the rated lightning impulse and
power frequency short duration withstand voltages are given in IS 2165
(Parts 1 & 2), associated with each highest system, voltages upto 765 kV.
Standard insulation withstand level combinations other than those given in IS
can also be selected when the design of the system/methods of control of
overvoltages and the limiting effect of surge diverters justifies it technically
and economically.
14.6.4 The overvoltage between two phases is determined from two overvoltages to
earth having opposite polarity. The switching impulse voltage peak is very
much dependent on time to crest of the two components having opposite
polarity and the time delay between these two components. Based on
statistical observations and accepted risk of failure, for 300 kV and above,
the selected value of the ratio between rated switching impulse withstand
voltage phase-phase and phase-earth is in the range of about. 1.5 to 1. 8. The
value 1.5 being used upto 400 kV lines. For voltage range 52' kV to 245 kV,
the lowest phase to phase rms power frequency withstand values associated
with each system voltage are close to a temporary overvoltage of 1.5 p.u. (i.e.
1.5 p.u. x √ 3/2).
ISSUE
R2
14.6.5 The phase to phase horizontal spacing is decided on sag and conductor swing
under dynamic lateral forces or in maximum wind, so as not to cause arc over
between them at midspan in case of out of step swinging of conductors if
any. In certain conditions of wind/ice it will also depend on
galloping/dancing movement of conductors due to vibrations of high
amplitude It is difficult to estimate the probable travel of the conductors
under all conditions. Long spans increase the sag and consequently the phase
spacing. There are several empirical formulas adopted by different countries
for the phase to phase spacing and they give widely varying results. One of
them is the following VDE formula which can be used as a design check.
14.6.6 The vertical clearance above ground of the lowest conductor is laid down by
the rule 77 of the Indian Electricity (I.E.) Rules, 1956. For the purpose of
computing the vertical clearance, the maximum sag is to be calculated on the
basis of still air and-maximum temperature of the region.
14.6. 7 Some of the representative values of standard insulation, levels and the
minimum associated air clearances are given in Table 4. They are suitable for
general application, providing as a first approximation a clearance to be
specific in relation to the specified impulse withstand voltage. The values of
phase to phase spacing, ground clearances and conductor to tower clearances,
as applied, are given in Item 19.0 under Tower Design.
15.1 For voltages upto 245 kV it would suffice to presuppose the temporary
overvoltages lightning impulse magnitude based on previous experiences of
comparable system. The insulation level selection is then made, from the IS
tables of standardised values of withstand voltages, giving a suitable margin
of safety.
15.2 For 300 kV and above, the high cost of line equipment, while, in turn, the
serious consequences of a failure necessitates a more precise estimate of the
overvoltages to be expected. The magnitude of switching overvoltages are
evaluated by the use of digital computer studies or transient network
analysis, considering credible system contingencies and electrical parameters
of the system. The insulation level selection should be optimised and based
upon a statistical evaluation of the probability of withstand/risk of failure
rather than a prior choice of safety margin.
ISSUE
R2
TABLE – 4
NOTE:
The minimum clearances have to be increased by safety factor of 1.1 to 1.2 to take
care of actual site conditions. Tolerances in manufacture, variations in Gap Geometry.
ISSUE
R2
15.3 Example
(a) In still air and at a 15o C swing angle the minimum clearance to tower
steel is based on switching surge withstand, for 345 kV and above. For
voltages less than 345 kV, at a 30o swing angle the minimum clearance
should withstand the lightning impulse strength.
(b) At a 45o swing angle (and 60o for voltages lower than 220 kV) the
minimum clearance to tower steel is to be sufficient to withstand power
frequency overvoltages.
Line to ground peak value = 420 √2/3 = 343 kV crest (1.00 op.u.)
Let the maximum switching surge be limited to 2.5 p.u by (a) pre-insertion of
circuit breaker closing resistors in series with the line, (b) shunt reactors to
drain the trapped charge of the line and aid in proper interruption of unloaded
lines and (c) by correctly rated surge arresters. There may be random
overvoltage upto 2.7 p.u due to high speed reclosing after fault, however, it is
uneconomical to design with such a high degree of safety such that insulation
can sustain all types of overvoltage under all conditions.
ISSUE
R2
Using the formulae of 14.4 (all values are peak voltages) the CFO
voltage is :
This checks with GEC reference curves (See Fig. 2), for 23 unit string
and ratio d/D = 4.3/3.35 = 1.28.
(b) At 15o swing, the clearance d = 3.35 between live point and tower
leg.
This is the switching surge strength of air gap between conductor and
tower leg. This also can be checked with GEC reference curves.
ISSUE
R2
= 1.718 m
= 994 kV
= 747 = 2.17
343
ISSUE
R2
H = (32. 4 - 2 x 7) = 27.7 m
3
b = 19.6 m
IK = 60 (assume)
ii The trip out rates per 100 km per year for shielding failure and
for strokes to tower can then be computed from a family of
curves related to footing resistance, tower height, spans and
shield angles as given in GEC Reference Book, see Fig. 4. The
trip out rates for strokes to tower increase about 6 times for an
ISSUE
R2
iii. For high towers with shielding angle upto 20 degrees and for
smaller towers with shielding angle upto 30 degrees, the
probability of shielding failure is very low i.e. 5 x 10-3.
= 78 x 5 x 10-3 = 0.39
The number of trip outs rate for strokes to tower based on a tower
geometry of a 500 kV line a span of 300 m, 40 ohms resistance
(assumed), a 23 insulator string unit and isokeraunic level of 100,
is given from the reference curves Fig. 4 as equal to 3.125 (say
3.2).
iv. The T = indicated total outage rate of the design case, i.e. trip
outs per 100 km of line per year.
= 0.39 + 1.92
= 2.3
ISSUE
R2
(a) Creepage
Actual creepage for 23 fog type unit string will be 432 mm/unit x 23 =
9936 mm. Hence creepage requirement is adequate.
= 1615 kV peak
Is = Stroke current, kA
ISSUE
R2
V1 = Vt (l - Kf) + Em
V1 = 22.56 Is + 343 kV
ISSUE
R2
= 1066 kV
Maximum sag for a 350 m span, 31.77 mm diameter ACSR conductor with
3500 kg tension would be about 9 m.
V = 420 kV
= 0.75 √9 + (420)2
20000
= 2.25 + 8.82
= 11.07 m
As per rule 77, the minimum ground clearance for an EHV line will be 5.2 m
plus 0.3 m for every 33000 volts or part thereof by which the line exceeds
33000 volts.
= 5.2 + 12 x 0.3
= 8.8 m
16.0 INSULATORS
16.1 Insulators are required to attach the line conductors to supporting structures
and maintain insulation to ground. The basic requirements of the insulators is
ISSUE
R2
16.2.1 High grade electric porcelain is the recognised dielectric for insulating EHV
lines. It has the outstanding features of being non-porous, chemically inert,
having high di-electric properties, high mechanical strength and very high
melting point.
16.2.2 Toughened (tempered) glass is a good material for insulators. The toughened
glass insulators are equal to porcelain insulators in all respects. They have the
added advantage of having higher resistance to the effects of power arc and
chipping damage than porcelain. Also unlike a porcelain insulator, a
damaged/punctured glass insulator can be detected easily by visual
inspection and they do not require periodic testing for electrical deterioration.
A disadvantage is that they are more susceptible to breakage from small fire
arms.
16.2.3 Fibreglass and polymeric compounds are being used for insulators. This
composite insulator consists of a glass fibre core for mechanical strength and
a polymeric incapsulation for electrical performance.
16.2.4 The choice of insulator material is governed by the availability, price and
ease of maintenance.
Porcelain insulators are the ones, that are largely used in India, at present.
16.3.1 The disc insulator consists of a central suitably shaped porcelain/glass body
resembling a disc with a metal cap on one side and a metal ball pin on the
other, cemented to it. The cap is of malleable cast iron and the ball pin is of
forged steel. The porcelain transmits the mechanical load applied on the disc
from pin to the cap through the cement. The porcelain has adequate thickness
to withstand powerful lightning strokes and the shed outside the cap gives
sufficient distance between cap and pin for the required flashover voltage.
Suitably sized and shaped corrugations in the underside of the porcelain disc
give the required leakage (creepage) distances. Technical particulars of disc
insulator units are given in Table-5.
ISSUE
R2
TABLE : 5
TECHNICAL PARTICULARS OF DISC INSULATORS
ISSUE
R2
16.3.2 Strut type insulator comprises of several insulator discs cemented altogether
without any links. Strut insulators are rigid and can take both tension and
compression loads. These are used for holding the conductors out of the way
of the structure, thus making the structure and cross arm shorter. They can be
mounted either in vertical or horizontal positions to suspend jumpers and
conductors.
16.3.3 Another type is the long rod insulator made of solid porcelain rod with
numerous sheds and the caps are cemented at both ends of the rod. The
advantages of long-rod insulators are :
(a) The insulator is absolutely puncture proof because of its long porcelain
length.
(b) The porcelain body is not subject to tensile stresses due to the
expansion of cement. Owing to this, the routine lines maintenance
work and maintenance cost is greatly reduced as only occasional visual
inspection is required for checking the damages to porcelain sheds.
(c) Since there are lesser number of metal parts there is less failure due to
corrosion of metal parts and cementing of caps and pins.
(d) The leakage distance is slightly more than that of disc insulator string
of identical length and it has an excellent antipollution performance.
16.3.4 The disc type insulators are readily available and economically priced. This
is the type that is widely used for transmission lines in India, at present.
16.4.1 The disc insulators are joined by their ball pins and sockets in their caps to
form a string. The number of disc insulators in a string is decided based on
the system voltage, the switching and lightning overvoltages, altitude and
pollution level. Sometimes it is required to increase the number of discs to
provide safety and reliability in places where it is difficult to inspect the
insulators regularly. The insulator string is used for either supporting
(suspension string) or taking the tension of the conductor. Requirements of
string insulators are given in Table 6.
16.4.2 Suspension strings support the weight of the conductor length between the
maximum sag points of the spans on either side of the string location. Two
suspension strings in parallel are used at railway, road and river crossings
etc., as required by statutory regulations or site conditions.
ISSUE
R2
The swinging of suspension string due to wind etc. has to be taken into
consideration, so as to ensure the minimum required clearances of the line
conductor with the tower members.
TABLE 6
STRING INSULATOR CHARACTERISTICS
(REF. IS 731)
NOTE : Power Frequency Puncture withstand voltage kV (rms) for all strings is 1.3
ISSUE
R2
16.4.3 The strain or tension insulator strings are used where the line is dead ended
or at angle points, to take the conductor tension load and also to provide
adequate insulation clearance between the line and earth. These insulators
should have sufficient mechanical strength to counter balance the forces due
to tension of the line. When a single string is not able to withstand the
conductor tension or for the purpose of greater reliability, two or more
strings are used in parallel to share the mechanical loads. They are also used
at railway, river, road crossings etc. as required by statutory regulations or
site conditions.
The voltage distribution along the length of the insulator string is not uniform
because of the capacitance between the discs, the disc caps and the earth.
This results in a voltage of about 20 to 30% of the line voltage being
impressed on the line end units and produce localised corona around the line
side units. This is also associated with radio interference and accelerated
corrosion damage to the insulator. Grading rings (corona shields) are used to
achieve uniform voltage distribution to the extent possible besides screening
the line-side hardware fittings which are potential sources of RIV.
16.6.1 Deposit formation on the line insulator discs cannot be avoided as they are
always exposed to the atmosphere. These deposits pollute the surface of the
insulator and impair its electrical characteristics. The deposits which are
particularly harmful are those that contain greasy ash, soot, salt deposits (in
coastal areas), cement dust, chemical deposits (industrial areas), agricultural,
fertilisers and cost dust. The amount of deposit on the insulator is not
uniform because of the combined action of electrical field, rain and wind.
The unequal contamination of units from one end of an insulator string to the
other, is more deleterious than uniform contamination. The layer of deposits
have little influence when dry but in the presence of humidity that moistens
the dust without washing it, a highly conductive electrolyte is formed.
Considering the difficulty in controlling pollution it is very necessary to
ensure that, as far as possible the line is routed through pollution free regions.
This may increase the length of the line, but the extra cost on account of this
derogating would be more than compensated by the problems and cost
which, otherwise would have been incurred for overcoming the effects of
pollution.
ISSUE
R2
16.6.2.1 Periodic washing and cleaning of insulators, gives the best results. When the
line is de-energised the insulators can be rubbed clean with a piece of cloth
soaked in solvent. Live line washing can also be done by a jet of water under
pressure, but adequate safety measures have to be observed, properly
designed/insulated equipment and specially trained manpower has to be used
for this. Washing of insulators becomes costly if it has to be carried out
frequently.
16.6.2 More number of insulators may be added to the insulator string. However,
increasing the number of disc in insulators does not increase its performance
linearly. An increase of the number of discs by 33% results in increasing the
flashover voltage by 18% only.
Increasing the string length will also increase the cost of the towers, as longer
cross arms will be required to maintain the required conductor to tower
clearances.
16.6.2.3 The length of the creepage path of an insulator is a very important factor
controlling its ability to withstand electrical stresses. For a constant amount
of contamination, the maximum operating voltage that a string can withstand,
is directly proportional to the leakage distance. Therefore, it is better to use
special insulators (fog type) having longer leakage path under pollution
condition than to increase the length of the string by adding more of the
standard leakage path discs.
ISSUE
R2
A Light * 10 8 16 13 25 23
B Medium 12 8 19 13 25 23
C Heavy 13 9 22 15 27 25
D Very Heavy 14 9 23 15 30 27
E Salt precipta- 17 13 28 18 - 30
tion 0.2-0.5
mg/cm2 (sea-
side regions,
salt marsh)
* The minimum number should be based on rated BIL/switching surge withstand of the
line.
ISSUE
R2
(b) Special disc insulators with semi conducting glaze are sometimes used.
The heat produced by the semiconducting coating keeps the insulator
surface dry under fog and drizzle and prevents flashover. The
semiconducting glaze also helps to some extent in establishing a more
linear potential distribution along the string.
Horizontal strings are washed most effectively by rain but they can be
used only with strain-towers. The T-string configuration is a
compromise between strain and vertical (tangent) strings. The
horizontal string in this configuration can be made as long as required
to withstand contamination and the vertical string permits the
combination to function as a tangent string. This could be useful in
areas of very heavy contamination and salt precipitation.
16.6.3 A through survey of present and future contamination conditions along the
proposed line route is essential so that adequate clearances for installing
effective string lengths and string configurations can be considered during
tower design stage.
17.1 Line hardware are fittings used for connecting the insulator string to cross
arm support at one end and the conductor at the other and they have to ensure
proper mechanical and electrical performance of the electrical string.
ISSUE
R2
17.2 The line hardware consists of many component parts. The commonly used
hardware components in the assembly of suspension and tension strings are
shown in Figs. 5, 6 and 7. The maximum stress in conductor takes place at
suspension and tension clamped points and it is of vital importance that these
fittings do not cause damage or abrasion of the conductors. The following
important components are discussed from the view point of mechanical and
electrical considerations.
i. Suspension clamps
ii. Compression type and bolted type tension (strain) clamps
iii. Protective devices (arcing horns, grading rings and corona control
rings)
iv. Sag-adjustment devices
ISSUE
R2
17.3.1 Clamps
(b) The suspension clamp has to ensure that the conductor does not
completely slip from the clamp under broken wire conditions but it
shall permit the conductor to slip to a certain extent just before the
failure of the conductor occurs. The IS 2486 (PI) specifies the slip
strength for suspension and tension clamps as 25% and 90% of the
breaking load of the conductor respectively. The breaking load shall be
taken as specified in IS 398 for conductors.
(c) The magnetic power loss caused by the hysterisis and eddy currents in
the clamp has to be kept to a minimum. This is achieved by using non-
magnetic material for the clamps and hence aluminium alloy clamps
are used for this purpose. The power loss takes place only in the
galvanised steel bolts. These clamps are generally used where the
currents carried by conductor are large, as the power loss is greatly
reduced. Aluminium alloy clamps also reduce corrosion problems
which would arise due to galvanic action between the dissimilar
materials of clamp and conductor. Clamps of malleable iron/forged
steel would require aluminium liners for use with Al conductors.
(e) The clamp should be designed for corona and RIV performance either
equal to or better than that of the conductor. All edges, lips and corners
of the clamp should be round and smooth to minimise corona and radio
interference. The hexagonal nuts can be provided with corona
suppression caps to have a corona free clamp. The armour grip
suspension clamp is claimed to be corona free and is widely used in
U.S.A, Canada and Australia.
ISSUE
R2
(f) Armour rods are helical layers of round aluminium rods used for
reinforcing the conductor at suspension points. The parameters of the
armour rods are designed to suit the specific size of the conductor.
Such helical shaped rods are available as factory performed rods to
make them convenient to apply on the conductors without excessive
clamping pressure at any point. The armour rods protect the conductor
from the effects of power arcs and substantially reduce the vibrations
strain at clamping points.
(g) Tension (strain clamps) can be either bolted type or compression type.
i. Bolted type are used in slack span and in overhead ground wire
assemblies. With bolted type clamps, continuous jumper loops
without cutting conductor are easily formed by stringing the
conductor at angle point through the clamps. The jumper is
formed by the uncut slackened portion of the conductor. On the
terminal structures, the uncut conductor can be run through the
clamp directly to the equipment with considerable cost savings in
labour and' material. The bolted type strain clamps are available
with clamp body of aluminium alloy or malleable iron/forged
steel hot dip galvanised. The clamps of iron/steel material are
used mainly for ground wire assembly. If used for ACSR
conductors, aluminium liners are provided to prevent corrosion.
ISSUE
R2
(h) The electrical conductivity of clamps should not be less than that of the
conductor.
(a) Insulator strings have to be protected from the damaging effects of high
intensity arcs during a flash over. Arcing devices are therefore placed
at the ends of the insulator string to provide a secure route for the arc
and keep it far from the insulator.
The report of CIGRE Study Committee No.22 gives the arcing distance
between protective fittings for 132 to 500 kV by the formula d = 140 +
0.6 V cm; V= Line Voltage in kV. For example for 400 kV, d = 3800
mm. However, d/kV decreases as the voltage increases. These devices
should have adequate cross-section to withstand without deformation,
erosion and rupture the thermal effects of arc and mechanical stresses
due to the vibrations/galloping of the conductors. Their additional
functions are they should have such forms which will improve voltage
distribution and reduce corona and radio interference levels of the
insulator string.
(b) The arcing horns are made of 18 mm diameter galvanised steel rod
with 40 mm spheres on its ends. The arcing horns are attached to
hardware fittings. For voltages upto 66 kV arcing horns are generally
provided on the line side, and for 132 kV they are provided both at
tower and line side.
(c) For 220 kV and above, grading corona control rings are provided on
the line side and arcing horns on the tower side. The grading corona
control rings upto 220 kV can be of galvanised steel tube but for higher
voltage these rings are normally of aluminium alloy of suggested size
38 mm dia. with wall thickness of 2 mm.
(a) Bundle conductors face the problem of sag mismatch between sub-
conductors. Therefore sag adjustment devices are used along with
tension hardware to adjust and match the sag of all the sub-conductor.
The devices usually used are the sag adjustment plate/link and turn
buckle types. The former type is used in America, Canada and
ISSUE
R2
Australia and the latter in European countries. In India both types have
been used.
(b) The sag adjustment plate/link require extra care at time of adjustment.
Also it has a limited number of adjustments in steps of 15 to 25 mm
and unlike in turn buckles, fine adjustment are not possible. However,
the sag adjustment plate design is sturdy giving it a longer service life
and it is more economical than the turn buckle. Failure probability due
to pull under broken wire conditions is comparatively more for turn-
buckle due to fatigue failure of threads.
17.3.4 For lines subject to heavy contamination, insulator and fitting shall be
suitable for hot line maintenance.
ISSUE
R2
18.1 Spacers
18.1.1 Spacers are required on bundle conductors to maintain the design separation
between the sub-conductors and to prevent them from clashing due to wind
action. They have to withstand the forces due to aeolian and subconductor
vibrations and also to-provide latitude for conductor longitudinal, vertical
and horizontal movements.
18.1.2 Under fault currents many times the normal current, the sub-conductors are
drawn towards each other until they collide. Spacing devices installed at
intervals of 100 M or less will ensure rapid separation once the fault is
cleared. This will permit circuit reclosing within the period required in the
interconnected systems.
18.1.3 The short circuit conditions produce large compressive forces on the spacers.
Spacer flexibility reduces clamp forces and makes clamp loosening less
likely. Some typical types of spacers are shown in Fig.8.
ISSUE
R2
18.1.4 Flexible spacers are recommended because the compressions forces, if large
enough, will collapse the spacer without causing deformation to the
conductors near the spacer location. In addition, the spacer will exert a
restoring force on the conductors after fault clearance. In flexible spacers, the
quality and strength of the central member consisting of stainless steel helical
spring has to be of very high order, so as to ensure that it does not loose its
property and flexibility under the stresses induced by wind. The pair of
clamps at both ends of the central member consist of aluminium alloy body.
Instead of a spring type central member the flexible spacer can also be
designed with the connecting element as a flexible ring of stranded high
tensile galvanised steel wire permanently mould casted to the two aluminium
alloy clamps.
18.1.5 Semi-rigid spacers are composed of rigid components but with (a) flexible
joints containing springs, rubber bushes/elastomeric inserts or (b) with
flexible clamp conductor interface. The armour, grip type spacers of the latter
type, consisting of aluminium alloy tube frame with neoprene moulded
integrally on aluminium inserts at the ends provide good combination of
strength and cushioning. The method of attachment to the cable employs
helical shaped (performed) aluminium alloy retaining rods. This eliminates
bolts and also spreads the load on the conductor which helps to minimise
stress concentration.
18.1.6 Another type of spacer in the combined spacer damper. This type, in addition
to maintaining bundle geometry, in weighted to damp the aeolian vibrations
and sub-span oscillations.
There are two sleeves, the inner one of galvanised or stainless steel and
the outer of pure aluminium. The aluminium sleeve (body) in initially
ISSUE
R2
inserted over one of the conductor ends, before making the steel core
joint. The ends of the steel core of the two conductors are inserted into
the steel sleeve and compressed with hydraulic compressor. This
ensures good tensile strength of the jointed conductor. The aluminium
sleeve is then placed over it and compressed on to the aluminium
strands of the two conductors. This ensures good electrical
Conductivity.
(b) Combined compression and wedged joint. In this type instead of using
the steel sleeves a wedged type arrangement is utilised for jointing of
the steel core. An aluminium tube, similar to the one in compression
joint is used for joining the overall conductor. This type of joint is
shorter in length which is an advantage when the joints run through
stringing rollers. The combined type joint takes lesser time to make.
(b) There shall be no joints in important crossing spans, except where the spans
are longer than the standard conductor drum length.
(c) There shall be not more than one joint per conductor in a span.
19.0 TOWERS
19.1 Types
The two types of towers which are mostly, in use for EHV lines are guyed
towers and self supporting towers.
(a) The guyed tower is directly supported by guys or stays against the
transverse load. Therefore there is negligible bending moment at the
base but there is a high vertical force on the tower due to the guys
tension. Guyed towers are cheaper but require considerable extra land
to encompass the guys which may create right-of-way problems.
Guyed towers are more vulnerable to sabotage. This type of tower are
in use in America and Canada on the earlier 500-735 kV lines.
(b) In self-supporting type towers the overturning moment due to wind and
other forces is transmitted to the tower base and transferred to the
ground by tension/compression members of the leg. For narrow base
ISSUE
R2
towers the loading on the foundation is higher than in the case of broad
based tower and the cost of the foundation is more but the cost of
clearing right-of-way is less. Self-supported towers being more robust
and reliable are extensively used in India and other countries.
19.2 Material
The two types of steel used in the fabrication of towers are mild steel and
high tensile steel. The use of high tensile steel results in considerable
economy because of the lighter weight. This type is widely used in all
foreign countries. In India, at present, mild steel is used for towers. However,
for 400 kV lines high tensile steel 40% by weight to total steel weight has
been also used. For protection against corrosion hot-dip galvanising method
is used for application of zinc coating on steel surface. The protective life of
hot-dip galvanised coating on steel is directly proportional to the thickness of
the coating for any given condition of exposure. Bolts and nuts are also hot-
dip galvanised and spring washers may be electroplated with zinc. Usually
the weight of zinc coating is 610 g/m2 for steel structure and half that for
bolts and nuts.
The tower structure outline is composed of its height, arrangement and length
of cross arms based on conductor configurations, phase spacing and
clearances and the tower widths at base and cross-arm levels. Both electrical
and mechanical considerations determine these dimensions. Some typical
ISSUE
R2
110 kV, 220 kV and 400 kV tower outline diagrams are shown in Figs 9 to
15.
19.4 Height
The minimum safety clearances above ground of the lowest point of the
conductor and clearances over roads, railway, tracks, telecommunication and
power lines as laid down. In IE Rules and IS 5613 (Part 2) are as follows :
c) Over maximum flood level -------- ---------- 3.05 --- ---------- -------------
of rivers (not navigable) ----- ---- --- ----
d) For navigable rivers, in consultation with concerned authorities.
ii. At Crossings with
a) Telecom lines 2.44 2.75 2.75 3.05 4.88
c) Railway tracks, on 25 kV ac
ISSUE
R2
ISSUE
R2
19.4.2 Sag
19.4.2.1 The size and type of conductor, wind and climatic conditions of the region
and span length determine the conductor sag and tension. The maximum sag
for conductor span occurs at the maximum temperature and still wind
conditions. Under snow conditions with wind, the maximum sag may
perhaps occur at minimum temperature with conductors loaded with ice.
ii. The conductor tension at 32oC (90oF) without external load of wind or
ice shall not exceed the following percentages based on their UTS.
For sag tension stringing chart calculations the final modules of elasticity
values are to be considered, however, the tension at 32oC has to be also
checked with the initial modules of elasticity. In accordance with above,
therefore, the sag tensions computations made for final stringing of the
conductors must ensure a minimum F.O.S 2 under worst loading conditions
and a minimum F.O.S.4 under everyday loading conditions.
19.4.2.3 The standard sag tension parabolic equation considering the combined effect
of elasticity and temperature is given as :
conditions = (t2 - t1 )
K = f1 - 12 δ2 q21 E = f1 - Z1
24 f21 f 21
ISSUE
R2
Ice load W1 Kg/m can be estimated from 12.7 mm radial thickness at rate of
916.8 Kg/m2.
f = UTS of conductor
2xA
ISSUE
R2
(c) Sag = q δ 12 /8 fm
19.4.2.4 A stringing chart has to be prepared, for a particular ruling (design) span,
tabulating the tension and sag corresponding to each of the temperatures in
the range of minimum to maximum ambient temperatures at site. A typical
stringing chart is shown in Table 7.
d1 = 1 _ Th ; T = fA
2 W1
ISSUE
R2
TABLE - 7
Ref. CBIP
ISSUE
R2
19.4.3.1 The length of insulator string assembly, jumpers, their swings and the
corresponding electrical clearances to earthed parts (i.e. cross arms, tower
legs) in the deflected positions of strings/jumpers and the tower width at
cross arm level determine the length of the cross arm level determine the
length of the cross arms and the vertical and horizontal spacings between the
conductors. The optimum cross arm lengths will give the most economical
tower outline.
ISSUE
R2
For the vertical and horizontal spacings the swing angle and the
corresponding electrical clearances under these deflected positions of the
strings are to be considered. These are illustrated in Fig. 16.
S = String length
φ1, φ3 = Swing angles and corresponding
X1 = maximum clearance
φ2, φ4 = Maximum swing angle and X2 - corresponding
clearance
(B + C) = Flange width of the nearest projecting angle connected
to main angle member + distance to the centre of
gravity (CG) of the main angle section.
Y = Depth of jumper terminal point below cross arm level
and approximately it is
= Maximum sag of conductor x S/Half span
φ = Angle of deviation
D = Depth of the jumper, usually selected to be 1.18 X 1
H = Hanger length
α = Angle between the cross-arm lower main member and
the upper inclined member. This is usually between
20o to 30o
h = Height of the cross arm between the main horizontal
member and the inclined member = (a + offset) tanα
= (a + offset + S sinφ/2) tanα for angle tower
ISSUE
R2
= Y+b=h
where b = D Cos φ3 + (X1 + B + C) Cosα
when α > φ3
or
b = D Cos φ3 + (X1 + B + C) Cosα
when α > φ3
= S Sin φ1 + X1 + B + C
or
= S Sin φ2 + X2 + B + C
The greater of the above two values gives the length of cross arm
considered from the point of suspension of the string to the CG of main
leg member. Twice the length of cross arm so determined may give the
width of tower window for centre-phase in the case of towers with
horizontal configurations. Clearances have to be checked from the tip
of arcing horns or grading rings used on the line side. Allowance is also
made in the horizontal distance corresponding to the sloping of leg
members, if any.
ISSUE
R2
The greater of the two values gives the length of cross arm from
the point of attachment of conductor to CG of main leg member.
19.4.3.4 The cross arm spacings can also be determined graphically by drawing the
swings and clearances to scale. Following are representative values of
minimum spacings adopted currently, as given in IS 5613 (P2/Sec. 1).
ISSUE
R2
19.4.4.1 The height and location of the earth wire will depend on the shield angle, that
is the angle made by the line joining the earthwire to the outermost conductor
with the vertical. This angle is 25 and 30 degrees for lines upto 220 kV in
horizontal and vertical formations respectively and 10 to 15 degrees for 400
kV lines. The protective value approaches 100 percent as the shield angle is
decreased from 20 degrees to less than 15 degrees. Smaller shield angles
means higher height and it is not economical to keep small angles for lines
upto 220 kV. In horizontal formation with two earth wires, the shield angle is
usually maintained at 45o for the central conductor.
19.4.4.2 The mid span clearance (direct distance) between the earthwires and
conductors has to be more than the clearance at the tower, as discussed in
Item 11.0 (Earth Wires) to prevent a flashover from earthwire to conductors
during a direct stroke on the earthwire midspan. The height of the earth wire
and its tension should be checked to ensure that under minimum temperature
and still wind conditions, the sage of the earth wire is such that the direct
minimum mid span clearance between it and the power conductor is
maintained as given in earlier Item 11.0
19.4.4.3 The position of power conductors with reference to which, earth wire
position is determined, is fixed depending upon the length of the insulator
strings, their swings and the corresponding electrical clearances as discussed
in Item 19.4.3. Having fixed the angle of shield, the location of the earthwire
is known and the height of the earthwire peak is determined.
Spacing between the tower footings, that is the based width at the concrete
level, is the distance from the centre of gravity (CG) of one corner leg to the
CG of the adjacent corner leg angle. Towers with larger base width result in
low footing costs and lighter main leg members at the expense of larger
bracing members. Based on many years experience certain empirical
relations have been developed to determine the optimum base width which
will give minimum total cost of tower and foundation. The relations
developed between height and width are as follows :
(a) Ratio between height of tower upto the lowest cross arm and base
width for suspension towers, is generally between 2.5/3 for single -
circuit and 3.5/4 for double circuit.
ISSUE
R2
(b) Ratio between overall height of the tower and base width generally
varies between 6 for suspension towers, 5 for medium angle and 4 for
heavy angle towers.
19.6.2 Double circuit towers have the conductors in vertical formation and their
heights are more. Typical configurations of conductors on towers is shown in
Figs. 17 and 18.
b) Small angle towers with tension strings, to be used for line deviations
from 2o to 15o.
d) Large angle and dead end towers with tension strings, to be used for
line deviations from 30o to 600 and dead ends.
The angle of line deviation specified are for the normal span. The span may
however, be increased upto an optimum limit by reducing the angle of line
deviation.
ISSUE
R2
19.7.2 Where specially long spans are necessary because of river, creek,
mountainous crossing, the categories of towers listed above cannot be used
and the towers should be specially designed taking into consideration the
very long span lengths at times upto 1000 m, soil conditions at the location
etc. These are known as special towers. The river span crossing are usually
suspension towers and are provided with anchor (angle) towers on either
ends.
19.8.1 Loads
Towers are designed to withstand under normal as well as broken wire
conditions the following loads :
b) Longitudinal load acts along the direction of the line and the
component of conductor tension at right angles to the longitudinal axis
of the cross arm is considered for design. Longitudinal load is due to
unbalance tension in the conductor produced either due to dead ending
of the conductor or due to broken wire - conditions. Unbalance tension
produces torsional loads causing twisting moments about the central
axis of the tower.
c) Vertical loads are applied at the point of conductor supports and they
are due to weight of conductors/groundwires, with ice if any, insulator
strings/accessories and weight of tower. An overload to be considered
for erection/maintenance at conductor cross-arm and lifting point is
usually 350 kg for weight of man with tools and tackles.
ISSUE
R2
a) All single circuit towers and Any one power or earthwire broken
double circuit suspension towers whichever is more stringent
b) Double circuit, small and medium Any two power conductors or one
angle towers power and one earth wire broken on
the same span, whichever
combination is more stringent.
19.8.2 Codes
The application of the tower loads are governed by the following codes
stipulated in IS 802 (P1) and factors of safety given in I.E. Rules :
ISSUE
R2
19.8.2.1
Minimum Factor of
Safety
i. Metal supports, based on crippling load , (steel 2.0
to IS 226, has yield strength 26 kg/mm2)
Wind pressure shall be the maximum wind pressure, based on the wind
zones map of India, and the separate values of the wind pressure on
towers and conductors shall be as given in IS 802. This map is given in
Fig. 19. The maximum tension will be when the maximum wind
pressure on the conductor in assumed to act at minimum temperature of
the region.
ii. 50 percent of projected area of the insulator with diameter equal to that
of insulator skirt. The pressure shall be assumed as for tower.
iii. For towers, 1.5 times the projected area of the tower members on the
wind-ward face.
ISSUE
R2
ISSUE
R2
iv. The wind span of conductors and earth wires. The wind span is
the sum of the two half spans adjacent to the tower support and it
s considered equal to the normal span. Under broken wire
conditions, 50% of the normal span and 10% of the broken span
shall be assumed as the wind span for both suspension and angle
towers.
Under normal conditions this load is nil, except equal to the tension of
conductors and earth wires for dead-end towers. The unbalanced pull
due to broken conductor, in the case of suspension string towers, is
assumed as equal to 50% and 100% of the respective maximum
tensions of the conductor and earthwire. In the case of tension string
towers, for conductor and earth-wire broken conditions, the component
of the respective maximum tensions of the conductor and earthwire
corresponding to the relevant angle of deviation is to be considered for
tower loading.
ISSUE
R2
ii. For tower design following estimated values of weight span are
used :
Maximum - 1.5 x normal span (to cover the weight at hill top
positions)
ISSUE
R2
20.1 Installation of overhead line involves clearing of the work site and the line
route prior to detailed survey.
This is required to be done both legally and physically. The line alignment
should involve least amount of tree cutting as laid down by Government
authorities. Minimum width should cover safety clearances and requirements
of transport of equipment/material for construction and maintenance.
20.2 For the purpose of computing minimum horizontal safety clearance, the
maximum deflection shall be calculated on the basis of the maximum
regional wind pressure or may be taken as 35o, which is greater. The angle of
swing of the conductors in wind is obtained from total wind on the conductor
(loaded with ice, if any) and the total weight of the conductor (with ice, if
any).
20.3 The line clearance requirements is shown in Fig. 21. The following right-of-
way width are recommended in IS 5613 (P2 Section 2).
66 18
110 22
132 27
220 35
ISSUE
R2
21.1 The line clearing and survey work locates all the tension/angle/terminal/river
crossing anchor towers taking into consideration the desired section lengths,
site conditions, etc. and the levels of the ground along the route are
measured. From this field data, the Route Plan and Profile drawing (also
known as Survey charts) for each section is plotted and prepared to the scales
of 1 in 200 horizontal and 1 in 200 vertical on square paper. Locating the
intermediate towers along the profile of the ground is called tower spotting.
A very important factor to be considered for tower spotting is the span,
which in practice and for design purpose is taken as the horizontal distance
between centre lines of adjacent towers between which the conductor is
freely suspended. The span consideration is dealt with in detail as follows :
21.2 Span
Nominal System
No. of Circuits Span Range (m)
Voltage kV (rms)
66 1 204 - 305
2 240 - 320
2 305 - 380
(not in IS applied)
ISSUE
R2
(a) One of the above spans is initially selected as the Basic Span,
depending on line voltage, terrain conditions, ease and cost of
construction and maintenance. The Basic Span is also referred as
Design Span, Ruling span or Normal span. The basic span length is the
maximum distance between standard towers on level ground so that the
requisite statuary ground clearance is obtained at the maximum
specified temperature. This will determine the height of the standard
tower from level ground upto the bottom conductor attachment.
(b) In actual practice, due to the changing profile of the ground, any
section of an overhead line route will consist of a number of spans of
variable length. Since, at any time, only one tension can be applied at
the tensioning positions of any section, this applied tension will be
constant and uniform throughout the whole section, irrespective of the
span lengths. This uniform tension for the whole section will produce a
specific sag on a specific basic (design) span at a given temperature.
The sags and tensions at various temperatures (in the specified
temperature range) are calculated on this basic span. Then the sags on
the other spans in the line section at the same uniform applied tension
corresponding to a particular stringing temperature, are correlated as
follows :
Sag for any span X = (Span length X)2 x Sag for basic span
Basic span length
The uniform applied tension for the entire line section is based on the
calculations of sag-tension versus temperature on the basic span. A
specimen stringing chart is shown in Table 7.
(c) One basic (ruling span should normally be selected for the entire line,
except for certain sections where, on account of exceptionally rough
profile, long and short spans cannot be avoided. In such cases, a longer
or shorter basic span should be used and separate sag template are to be
prepared. The conductor must be dead-ended at the point where a
change in basic span occurs, because with variations in temperature
and loading, the horizontal tensions in sections of line with different
basic spans do not vary by the same amounts and unbalanced tensions
ISSUE
R2
(d) Since the basic span is used as a basis for calculating the sag-template,
it must be assumed before the towers are “spotted” (i.e. located). Dead-
ending for the purpose of changing the basic span is costly. A
representative basic span should be so selected that it can be applied to
the whole line length so far as is practical. An equivalent hypothetical
span which would give uniform tension for all the spans in the line
section is given by the formula.
_____________________
LR = / L31 + L32 + L33 + ........
√ L1 + L2 + L3 +.........
For each ruling span selected the sag and tensions for the minimum
and maximum span lengths should be checked for the loadings and
temperatures specified. Any individual maximum span should not
exceed the ruling span by more than 50 percent.
21.3.1 It is necessary to obtain the tower design data indicating the limits of the
normal span, weight span, maximum tension of conductor etc. which are not
to be exceeded. A specimen tower spotting design data sheet is given in
Table 8.
ISSUE
R2
TABLE 8
IMPORTANT INSTRUCTIONS FOR FIELD ENGINEERS
ISSUE
R2
TABLE - 8 (CONTD.)
Sl. Tower Type Suspension Angle Angle Angle
No ‘A’ ‘B’ ‘C’ ‘D’
.
4 Permissible sum of adjacent spans 2o 800 15o 800 30o 800 60o 800
for various deviation angles.
1o 902 14o 902 29o 897 59o 888
0o 1003 13o 1003 28o 995 58o 978
12o 1105 27o1096 57o
1066
11o 1206 26o 56o
1198 1155
o
10 1308 25o 55o 1244
1295
5. a) Design long tension GW 1358 1346 1312 1176
(Bracketed figures are or CASE-I) (1381) (1369) (1334) (1196)
Cdt 4323 8568 8352 7487
(4139) (8203) (7997) (7169)
b) Broken wire condition Any one GW or any one bundle conductor broken
Remarks : For calculating wt. span following are considered.
i. G K Clamp weight : 10 kg
iii. Weight of men with tools at each conductor cross -arm point : 150
kg
iv. The cross-arms medium and heavy angle towers types C & D are
designed for a wt. span of 3 times the normal span.
Figures with (*) asterisk mark for span with double suspension insulator
ISSUE
R2
d) The weight and wind span on any tower should be within design limits.
These terms are as explained in Item 19.
e) The tower data sheets should also indicate the loading capability range
of each category of tower for various deviation angles. That is, if 60o
tower is used for a deviation of 45o, the extra available wind and,
weight span can be utilised. This helps in deciding the type of tower to
be used in various conditions.
21.4.1 The use of sag template facilitates locating the towers on the line profile
correctly and economically. The template for sag versus span curves is
prepared for maximum and minimum temperatures of the region through
which the line passes, on the same scale as profile charts, i.e. scales of
1:2000 for horizontal and 1:200 for vertical distances. The sag template is
made out of transparent celluloid sheet of about 1 mm thick. A typical sag
template is shown in Fig. 22.
ISSUE
R2
b) The ground clearance is drawn through the origin ‘O’ at the centre line
of the template, parallel to the maximum sag curve.
c) The cold curve is normally drawn through the origin ‘O’ as a parabola
on the minimum sag of the ruling span and extended as explained for
the hot curve.
d) The support foot curve is drawn parallel to the hot curve and at a
distance equal to the bottom conductor height at the tower support.
The method of using the sag template for spotting the tower positions on the
line profile is shown in Fig. 22. The tower spotting is carried out section by
ISSUE
R2
section, i.e. from one terminal or angle tower to the next angle tower and so
on.
The weight span on either side of the tower is obtained by marking the low
points of the sags in the two adjacent spans.
On steeply inclined slope, the upward pull exerted by the conductor in the
uphill span should be counter balanced by the weight of the conductor from
the lower tower to the low point in the sag. Should the upward pull of the
uphill span be greater than the downward load of the next adjacent span,
actual uplift would be caused. For an easy check whether a tower is under a
uplift or not, the template is applied horizontally until the tops of alternate
supports coincide with the cold curve. If the curve is above the intermediate
support, it indicates that the support would be under uplift during the cold
season. This can be overcome by extending the intermediate support until it
touches the cold curve.
The tower spotting is continued upto the tower just prior to the next fixed
angle point location of the line section. If the last span turns out to be bigger
or much smaller than the design span, then the previous spans are to be
suitably readjusted.
The minimum number of towers and thus the cost of the transmission line
will depend on a careful and judicious application of the template for
ISSUE
R2
Minor changes if required, could be made at site while actually locating the
towers, for providing stable foundation and minimise avoid additional civil
works, viz. protection, excavation, etc. depending on actual site condition
prevailing at the time of construction. However, these changes should be
rechecked by sag template and incorporated in the profile drawing.
22.0 REFERENCES
22.11 The Indian Electricity Rules, 1956 alongwith CEA Regulations, 1979.
ISSUE
R2
ISSUE
R2
ISSUE
R2