2m*4m CMDRR Center


# Materials Description Unit Qty Unit Cost Total Cost
1 CIS 35 Guage pcs 24 180.00 4,320.00
2 Mologa/Tsid pcs 26 200.00 5,200.00
3 Eucalyptus 6-8cm (Magar) pcs 20 40.00 800.00
4 Eucalyptus 10cm (Waraj) pcs 12 70.00 840.00
5 Eucalyptus 12cm (Waraj) pcs 12 90.00 1,080.00
6 Purlin 7*5cm pcs 18 55.00 990.00
7 Filx pcs 2400 1.50 3,600.00
8 Bandage (Bonda) kg 5 20.00 100.00
9 CIS Nail kg 1.5 140.00 210.00
10 #5 Nail kg 2.5 40.00 100.00
11 #6 Nail kg 3 40.00 120.00
12 #8 Nail pkt 1 80.00 80.00
13 #10 Nail pkt 1.5 90.00 135.00
14 #12 Nail pkt 1 90.00 90.00
15 Soil M3 30 134.00 4,020.00
16 Stone M3 21 140.00 2,940.00
17 Sand M3 21 110.00 2,310.00
18 Cement Bag 50 185.00 9,250.00
19 Paint Gallon 4 250.00 1,000.00
20 Olio Liter 8 15.00 120.00
21 Kerosen for Paint Liter 5 22.00 110.00
22 Brush small pcs 2 20.00 40.00
23 Brush Big pcs 2 40.00 80.00
24 Anti rust paint kg 2 120.00 240.00
25 Door 1m*2.5m pcs 1 3,500.00 3,500.00
26 Window 0.5m*1.5m pcs 1 1,600.00 1,600.00
27 Water Liter 20000 0.30 6,000.00
28 Rope 0.3mm M 200 0.80 160.00
29 Rope 0.1mm M 50 0.80 40.00
30 Skilled Labor LS 1 15,000.00 15,000.00
31 Unskilled Labor LS 1 8,000.00 8,000.00
32 Industrial Material Transportation LS 1 10,000.00 10,000.00
33 Local Material Transportation LS 1 6,000.00 6,000.00
Total 88,075.00