You are on page 1of 10

Application of Computers and Operations Research in the Mineral Industry –

Dessureault, Ganguli, Kecojevic & Dwyer (eds)


© 2005 Taylor & Francis Group, London, ISBN 04 1537 449 9

Increasing underground coal mine productivity through


a training program

E.B. Kroeger
Mining & Mineral Resources Engineering, Southern Illinois University, Carbondale, Illinois, USA

M. McGolden
CoalTec, Newburgh, Indiana, USA

ABSTRACT: Over the last two years, the State of Illinois supported an underground miner productivity training
grant through the Illinois Clean Coal Institute. The main goal of this grant was to provide training to underground
coal mines in Illinois in an effort to increase mine productivity. It was hoped that by providing training to mine
personnel on how to make small changes to cyclic procedures, productivity increases would come at no additional
cost to the mines. Project staff conducted site walkthroughs and time studies underground at seven different mines
for four coal companies. The focus of the visits was the continuous miner cycle as all the underground mines in
Illinois use a continuous miner for production or longwall development. Data from the time studies were entered
into a spreadsheet that modeled mine productivity. Variables were changed in the models to predict productivity
increases that could be achieved by making changes suggested and to show sensitivity of the variables on the
productivity. The objective was to help the operations quantify the benefits of the specific changes so they
could make more informed decisions and focus their attention on the most critical issues. The findings from
the walkthroughs and mine models were incorporated into a miner productivity training presentation. Training
sessions were provided to mine management and frontline supervisors at five mines and additionally, to hourly
workers at one mine. In all, productivity increases ranging from 10% to 34% were suggested at each mine by
project staff at no additional production cost to the mines. If fully adopted, productivity from these mines would
increase by an estimated 2 million clean tons of coal per year, resulting in an additional $50 million in coal sales
from these five mines. Each mine visited had its specific challenges, but several had common issues. The issues
that kept recurring were not fully utilizing haulage capacity, mining out of sequence, and not taking the longest
cut possible. To illustrate the sensitivity of the productivity to these variables in a continuous miner production
panel, a hypothetical nine-entry, room-and-pillar mining plan was created and analyzed using a mine-modeling
spreadsheet. Results from the mine models are presented along with recommendations for possible changes to
increase productivity.

1 INTRODUCTION and procedural changes rather than keeping track of


cycle times and the workers becoming more efficient
Underground coal mining has always been a cost in their mining practices. Further productivity gains
competitive industry and will continue to be in the will continue by switching to larger, more powerful
foreseeable future. Any reductions in the production mining equipment, but these gains can be enhanced
cost or increases in productivity can turn a marginal by training on cycle times and efficient work prac-
mine into a profitable one. To reduce the costs of pro- tices. Miner productivity training has the ability to
ducing coal, many underground mines have focused significantly increase productivity without any capital
on raising the productivity per miner-hour. This has expenditures. This paper focuses on the productivity
been a nationwide goal over the last 25 years. Accord- of batch haulage systems, since this was the only type
ing to the Energy Information Administration (2002), of system analyzed during this training grant.
in the period from 1979 to 1999, the underground coal
productivity per miner-hour rose from 1.13 tons/hour
to 3.99 tons/hour, a 250% increase. This equates to 2 MINER TRAINING PROGRAM
an average annual increase of approximately 6.5% per
year. Suboleski and King (1991) attribute much of this Starting in September 2002, The State of Illinois sup-
increase to better equipment, new mining methods, ported an underground miner productivity training

611

Copyright © 2005 Taylor & Francis Group plc, London, UK


grant through the Illinois Department of Commerce (SCSS) and dual crew super-section (DCSS) should
and Economic Opportunity and the Illinois Clean Coal be made. A DCSS has two continuous miners and two
Institute. The authors began working on the project crews of personnel, allowing both miners to cut coal
in January 2003. The main goal of this grant was to simultaneously. Each miner has the appropriate num-
provide training to underground coal mines in Illinois ber of haulers taking the coal mined to a single feeder.
in an effort to increase productivity. Training pre- Conversely, while a SCSS (walk-between section) also
sentations were created covering a variety of topics utilizes two continuous miners, it has only one crew
including cycle times, action plans, problem solving, of personnel plus a set-up man, and operates a sin-
and the costs of reworking. It was hoped that by provid- gle continuous miner at a time. A single set haulers
ing training to mine personnel, productivity increases cycle back and forth between each miner, depending
could be gained at no additional cost to the mines. on which is cutting coal at a particular time. In addi-
The program was initiated by sending a letter of intro- tion to differences in staffing and equipment, there
duction to the underground coal mines in Illinois. The are also significant differences in the ventilation and
letter outlined the training program, presentations that power systems. Each mining system has its advan-
could be provided, and the possible benefits of the tages and disadvantages and conditions at a particular
program. mine most often determine which system is used.
There are several good papers that describe the advan-
tages and disadvantages of each system (Suboleski and
3 MINER TRAINING PROGRAM RESULTS Donovan, 2000; King and Suboleski, 1991).
Overall, project staff conducted site walkthroughs and 4.1 Base case scenarios
time studies underground at seven different mines
for four coal companies. The focus of the visits was To illustrate the sensitivity of the productivity to these
the continuous miner cycle and other processes mine variables in a continuous miner production panel, a
management identified as limiting the productivity. hypothetical nine-entry, room-and-pillar mining plan
Data collected from the operations included the cut was created as shown in Figure 1. The plan used entries
sequence, equipment used, mining height and width, and crosscuts on 60-foot centers with 18-foot wide
and other pertinent information. The results of the cuts. To make each crosscut sequence easy to analyze
walkthroughs and the data collected were entered into a and repeatable, the cuts in the entries were set to 30
spreadsheet that models mine productivity. The model feet long, with two, 21-foot long cuts in each of the
was then calibrated to match the average productivity crosscuts. The cut sequence was designed for use by a
under average mining conditions. SCSS but was also later used for a DCSS. To analyze
Single variables such as tonnage of coal on the the sequence as a DCSS, only one side of the figure was
haulage equipment were changed in the model to pre- used, so the right side miner would mine the odd cuts
dict the sensitivity of productivity to the variables. and the left side miner would mine all the even cuts.
The findings from the walkthroughs and mine models Because the sequence has symmetry, the productivity
were incorporated into a miner productivity training from one side could simply be doubled to determine
presentation that was presented to both mine manage- the productivity from the DCSS. This simplification
ment and hourly workers. By quantifying the benefits obviously ignores potential dumping interference at
or negative impacts of the specific actions, the mines the feeder-breaker.
could make more informed decisions and focus their The position of the feeder in the model should match
attention on the most critical issues. the actual mine condition. In Figure 1 it is shown just
During the mine walkthroughs, key issues were outby of the crosscut. For a SCSS this is perfectly
identified and solutions were presented to each mine. acceptable, as only one hauler would be unloading at
Productivity increases ranging from a minimum of a time. Of the mines visited during this training grant,
10% at one operation up to 34% at another were sug- most used this arrangement because it allows the load
gested by project staff. None of these changes required to be discharged at a faster rate because the pile of coal
additional cost. If fully adopted, cumulative annual discharged is being pulled away from the hauler as it
productivity from the mines visited would increase is unloaded, if the feeder chain is operating at a rate
by an estimated 2 million clean tons, resulting in an faster than the hauler is unloading. If the feeder chain
additional $50 million in coal sales from these mines. is operating at a slower rate due to some outby restric-
tion, then side discharging (utilizing a three-way dump
located in the center of the intersection) may be faster
4 VARIABLES AFFECTING MINE because the full length of the feeder chain is utilized
PRODUCTIVITY and flood loaded by the haulers. For a DCSS, the feeder
would have to be moved from the location shown in
Before discussing productivity and cut sequences, Figure 1 to the middle of the intersection because there
the distinction between a single crew super-section would certainly be instances where two haulers would

612

Copyright © 2005 Taylor & Francis Group plc, London, UK


Figure 1. Base case cut sequence for hypothetical mining sequence.

have to unload at the same time. This usually causes a analysis of the cut sequence are provided in Table 1.
slight delay in the unloading of the hauler that arrives In addition to these variables, three more variables are
to the feeder after the first hauler. Most mines that typically needed to accurately model a mining system:
operate battery haulers in a DCSS usually unload onto number of haulers used, tram delays, and in-cut delays.
the sides of the feeder, allowing the entry directly inby These variables can be input and changed from cut-to-
the feeder to be used for short-term storage. For mines cut on the cut sequence entry page in the model. In
that operate cable shuttle cars, the cable anchor points the hypothetical cut sequence mined using a SCSS,
require haulers to unload from the front and both sides the number of haulers used was four, tram delays were
of the feeder. This requires the feeder to be placed in set to zero, and the in-cut delays were set to 5 minutes
the middle of the intersection. except for the first cuts in the cross-cuts, which were
Since most of the mines visited during the first year set to 10 minutes, recognizing that cutting a turn takes
of the training program operated ram-dump type cars, longer. In the hypothetical DCSS cut sequence, the
the following analysis is for that type of equipment number of haulers used was four, tram delays were
and the analysis should not be inferred to work with set to three minutes, and the in-cut delays were set to
cable shuttle cars. The following analysis also assumes 5 minutes except for the first cuts in the cross-cuts,
that there are no delays in the roofbolting that would which were set to 10 minutes. These are typical values
cause the continuous miners to wait on the roofbolter. measured from time studies during the first year of the
For the base case scenarios, the variables used in the training program.

613

Copyright © 2005 Taylor & Francis Group plc, London, UK


Table 1. Input parameters used in the mine model Table 2. Output from the mine model spreadsheet for the
spreadsheet. hypothetical SCSS base case.

Input parameter Value used in models Average/ Average/


Output parameter Total cut shift
Number of cuts 102
Shift duration 520 minutes Expected production 2166
Travel in and out 40 minutes rate (raw tons/shift)
Preparation time to start and leave 15 minutes Expected mining rate 6.28
Lunch time 0 minutes (raw tons/minute)
Service miner time 0 minutes Tons per foot of advance 4.91
Unexpected delays 120 minutes Feet per car 2.44
Mining height 78 inches Shifts per cycle 6.26
Cut width 18 feet Load time (minutes) 860.9 8.4 137.6
In-place Coal density 84 pounds/cubic foot Change-out time 667.3 6.5 106.7
Hauler capacity 12.0 tons (minutes)
Loading rate (standard) 15.0 tons/minute Wait on car (minutes) 0.0 0.0 0.0
Loading rate (clean-up) 15.0 tons/minute In-cut delays (minutes) 630.0 6.2 100.7
Hauler speed from change-out 250 feet/minute Cycle time (minutes) 2158 21.2 345.0
point to face Cars loaded 1076 11 172
Hauler speed from face to 320 feet/minute Linear advance (feet) 2756.9 27.0 440.7
change-out point
Hauler speed from change-out 320 feet/minute
point to feeder Table 3. Output from the mine model spreadsheet for the
Hauler speed from feeder to 320 feet/minute hypothetical DCSS base case.
change-out point
Dump time of haulers 0.50 minutes Average/ Average/
Length of miner 30 feet Output parameter Total cut shift
Hauler length 35 feet
Tram speed of miner 60 feet/minute
Expected production 1572
Switch in time (time to turn 0.20 minutes
rate (raw tons/shift)
around at the feeder)
Expected mining rate 4.56
Switch out time (time to turn 0.217 minutes
(raw tons/minute)
around at the change-out point)
Tons per foot of advance 4.91
Feet per car 2.44
Shifts per cycle 4.11
Load time (minutes) 430.5 8.4 104.8
4.2 Base case results Change-out time 329.8 6.5 80.3
Using the values provided in Table 1, the mine model (minutes)
spreadsheet determined the base case productivity was Wait on car (minutes) 0.0 0.0 0.0
2166 raw tons per unit shift using a SCSS. The output In-cut delays (minutes) 315.0 6.2 76.0
Cycle time (minutes) 1417 27.8 345.0
from the spreadsheet for the base case is provided in
Cars loaded 538 11 131
Table 2. The output from the mine model spreadsheet Linear advance (feet) 1314.0 25.8 319.9
for the base case using a DCSS is provided in Table 3.
The productivity from the model for the DCSS was
1572 tons per unit shift for each miner, or 3144 tons
per unit shift total. As haulers have increased in capacity over the last
ten years, especially battery ram cars, the beds on
the haulers have increased in width and length. It
has become important for continuous miner operators
4.3 Utilizing haulage capacity
to fan the conveyor tail from side to side to evenly
All seven mines visited in Illinois thus far have used distribute the coal across the bed of the hauler in con-
batch haulage and only three of these operations were ditions where the mining height limits height of the
fully utilizing the hauler capacity. For the mines that coal pile in the bed. If the operator does not fan the
were not, this was the single easiest way to increase conveyor, then the coal piles up in the middle of
productivity. Not having a full load could be attributed the bed and does not fill the corners and the tonnage
to a number of issues, but two of the most com- hauled is lower than possible.
mon were not fanning the miner conveyor tail to Another reason the hauler capacity may not be fully
evenly distribute the coal across the width of haulers utilized is related to the mining height and diameter of
and signaling the haulers to leave the miner before the drum on the continuous miner. Depending on these
completely full. conditions at a mine, the haulers may be filled after

614

Copyright © 2005 Taylor & Francis Group plc, London, UK


only a single sump and shear down cycle or two cycles. Much of the productivity loss occurred because the
The problem occurs when the number of cycles is not wait-on-hauler time increased to 4.1 minutes per shift
even. Many continuous miner operators will signal the for the SCSS, and 3.3 for each miner for the DCSS.
hauler to leave with a partial load rather than starting
another sump and shear cycle. 4.5 Distance between belt moves
Fanning the conveyor tail and starting a new sump
and shear cycle will increase the load time, but the The distance between the coal faces and the feeder
productivity increase gained from larger loads far off- should match the mining conditions. For example,
sets the slight drop in productivity from longer load when a unit encounters a low area and the floor
times. To many continuous miner operators this may becomes soft, the more quickly the unit can advance
seem contrary, but is easily demonstrated using the past the soft floor, the less effect the soft area will have
mine model spreadsheet. on productivity. In this condition, the feeder may have
To demonstrate this, in the base case models, the to be moved forward as soon as the crosscuts are com-
tonnage on the haulers was reduced from 12 tons to pleted. The crews may not be happy with this option,
10 tons and no other parameters were changed. This but the more the machinery travels over soft floors, the
resulted in the tonnage per unit shift dropping from more degraded they become.
2166 tons to 2044 tons, or a loss of 5.6% (122 tons per In general, the fewer the number of rooms or entries,
unit shift) for the SCSS. For the DCSS, the productivity the further the face can advance between belt moves
dropped from 3144 to 3000 tons, or a loss of 4.6% (144 with the same number of haulers. For example, a unit
tons per unit shift). in a 12-entry plan may need only three haulers operat-
ing behind each miner when the coal faces are only two
crosscuts from the feeder. However, after the section
4.4 Operating the correct number of haulers has advanced two additional crosscuts or four cross-
Having an adequate number of haulers behind each cuts from the faces to the feeder, an additional hauler
continuous miner is dependent on several variables would be needed behind each miner to keep the pro-
such as the cut sequence, which cut is being mined, ductivity at the same level. If the section was reduced to
haulage conditions, hauler type, hauler speeds, hauler seven entries, then the number of haulers behind each
capacity, unload time, change-out distances, etc. The miner could be decreased and the number of cross-
ideal situation is to have the empty haulers arriving at cuts that could be mined before a belt move could be
the change-out point slightly before the loaded haulers increased because the haulers do not have a lengthy
are arriving to the change-out point. This ensures that haul to the feeder.
the miner does not waste time waiting on the next This change was calculated with the mine model
hauler. There will be cuts with a short change-out dis- spreadsheet by decreasing the number of cuts in the
tance where the miner has to wait on haulers because sequence to 68 to show that only two crosscuts were
they do not arrive back to the change-out point in time mined before moving the feeder and belt. For the
and other cuts where the haulers wait on the miner such SCSS, there was no change in the productivity when
as the second cut in a crosscut. the other variables were kept the same. However, with
With this in mind, for cuts that have a minimal more frequent belt moves, the haulers do not travel
change-out distance, it is imperative that all the haulers as far, and the number of haulers could be reduced
are operating. In cuts where the change-out distance to three. This resulted in a drop of 0.7% (15 tons per
is long or where the cutting rate is slow, then all unit shift) because the wait on hauler time increased
the haulers may not be required. Mine managers and from zero to 1.8 minutes per shift. For the DCSS, there
supervisors should determine the cuts in the sequence was no change by moving the belt more often when
where a hauler could be taken out of the system for bat- there were four cars operating behind each continu-
tery changes. These cuts can be identified fairly easily ous miner. However, the productivity dropped by 0.4%
using the mine model spreadsheet. (14 tons per unit shift) when the number of cars was
This was illustrated in the base case models by decreased to three. Reducing the number of haulers
reducing the number of haulers behind each contin- behind the miners does have the potential for sig-
uous miner from four to three and holding all other nificant cost savings and could add the flexibility of
parameters constant. In both base cases, the wait-on- having an additional hauler on the section that could be
hauler time was zero. Reducing the number of haulers utilized when a hauler needs to go for battery change.
resulted in the tonnage per unit shift dropping from The effect of moving the belt every four cross-
2166 tons to 2151 tons, or a loss of 0.7% (15 tons per cuts was also modeled. This was done by increasing
unit shift) for the SCSS. For the DCSS, the produc- the number of cuts to 136. For the SCSS, there was
tivity dropped from 3144 to 3114 tons, or a loss of no change in the productivity, which suggests that
1% (30 tons per unit shift). For the DCSS, the number this would be a viable option as there was no drop
of haulers removed from the system was actually two, in productivity. The results for the DCSS were the
because a hauler was removed from behind each miner. similar. When the number of haulers was reduced to

615

Copyright © 2005 Taylor & Francis Group plc, London, UK


three behind each miner, the productivity of the SCSS tons, or an increase of 8.4% (262 tons per unit shift).
dropped from 2166 to 2151 tons, or a decrease of 0.7% In the models, the wait-on-hauler time increased to 0.8
(15 tons per unit shift). For the DCSS, the productivity minutes per shift for the SCSS, and 0.6 minutes for
dropped from 3144 to 3128 tons, or a decrease of 0.5% each miner for the DCSS, which suggests that having
(16 tons per unit shift). This suggests that the number four haulers behind each miner is barely adequate and
of haulers can be reduced and the belt and feeder could having a hauler leave to change batteries will cause a
be moved less often. Both mine management and the drop in productivity.
hourly workforce would readily adopt these recom-
mendations. As mentioned above, for this scenario, it
would be absolutely imperative that three haulers are 4.7 Reducing delays
operating for most of the cuts in the sequence. In the mine model spreadsheet, unexpected delays are
basically anything that happens that is not part of a
typical mining cycle.These could be a myriad of delays
4.6 Having haulers turned around such as having to stop the haulers because the bolter
For mines that use ram cars, the haulers should be is moving across the section or stopping the haulers
waiting at the change-out point with their beds pointed to re-hang a cable or curtain. Some of these delays
towards the continuous miner whenever possible. On are unpreventable such as equipment failure or outby
average, it requires about 15 seconds for a hauler to stoppages due to problems with a belt. Unexpected
turn around so the bed is pointed forward. If a mine delays do not include normal delays or in-cut delays
loads 200 haulers over an 8-hour shift, the loss of 15 such as resetting the continuous miner or moving the
seconds per hauler amounts to a loss of 50 minutes miner between places. Any reduction in unexpected
per shift. This would be enough time to make an addi- delays can contribute directly to increased loading time
tional cut or a loss of about 150 tons of coal per unit on the miner.
shift. When asked why the hauler is not turned around, The effects of reducing the unexpected delays were
most hauler operators will state that it only takes a calculated by reducing the value in the mine model
few seconds to turn the car around and do not real- spreadsheet from 120 minutes per shift to 90 minutes
ize the amount of time lost over a shift by not having per shift, or a 25% reduction in unexpected delays.This
the haulers turned around. For the mine spreadsheet increased the tonnage per unit shift from 2166 tons to
model, the time to turn the haulers around at the feeder 2354 tons, or a gain of 8.7% (188 tons per unit shift) for
was set to 0.2 min (12 seconds) and the time to turn the SCSS. For the DCSS, the productivity rose from
the haulers around at the change-out point was set to 3144 to 3416 tons, or an increase of 8.7% (272 tons per
0.217 min (13 seconds). These were average measured unit shift). For the DCSS, the decrease in unexpected
times from a recent mine visit. delays was 30 minutes for each continuous miner. As
Having the empty haulers turned around so they shown in Tables 2 and 3, because of the breakdown of
can drive directly under the miner tail will most likely the times in the mining cycle, the gain in productivity
require changes to the haulage patterns. This may also was less than the 25% reduction in unexpected delays.
require the full haulers to make a turn directly after Of the extra 30 minutes available, only 12 minutes went
pulling away from the miner. Maintenance personnel to loading time, 9.3 minutes went to change-out time,
will likely be opposed to this as it will shorten the life and the remaining 8.7 minutes went to in-cut delays for
of the wheel units on the haulers. Heavier wheel units the SCSS. For the DCSS, the extra 30 minutes went
should be available to offset the shortened life due to into four different areas, 10.1 minutes went to loading
making more turns. The productivity gained by having time, 5.9 minutes went to change-out time, 7.3 minutes
the cars turned around at the change-out point will far went to in-cut delays, and the remaining 6.7 minutes
offset the extra cost of heavier wheel units and more went to miner tram time between the cuts.
frequent repair of the haulers.
To illustrate this, in the base case models, the switch-
4.8 Making full depth cuts
out time for the haulers was reduced to zero to reflect
that the haulers did not have to turn around. The time Taking the longest cuts possible will increase pro-
to turn around before going back to the change-out ductivity because the number of cutting and bolting
point had to be added to the route somewhere, so it cycles are reduced. This is especially important for a
was added to the switch-in time (turning around at the DCSS because production is halted when the miner
feeder). No additional parameters were changed. In is tramming between cuts. Minimizing the number of
both base cases, the wait-on-hauler time was zero. By times the miner has to tram can significantly improve
having the haulers turned around, the tonnage per unit productivity. Not making full-depth cuts could be
shift increased from 2166 tons to 2430 tons, or a gain attributed to a number of different factors including
of 12.2% (264 tons per unit shift) for the SCSS. For the operator misjudgments of distances or not installing
DCSS, the productivity increased from 3144 to 3406 the last row of roof bolts as close to the face as possible.

616

Copyright © 2005 Taylor & Francis Group plc, London, UK


Figure 2. Cut sequence including cutting doubles with a DCSS.

The effect of cut depth was demonstrated by increas- between the double cuts should be minimized to ensure
ing the cut length in the entries from 30 feet to 32.5 feet. the change-out distances are minimal. For mines that
This allows the hypothetical mine to skip nine cuts in employ long cuts in their cut sequences, adding to
a sequence every six crosscuts. The mine model indi- the change-out distance can be disastrous on the pro-
cated the productivity would increase by 1.4% (30 tons ductivity. Many miner operators will drive the entries
per unit shift) for a SCSS and 2.2% (70 tons per unit forward an extra cut before the crosscuts are fin-
shift) for a DCSS. ished (cut 37 would be made before or after cut 27
in the sequence in Figure 2). This can add a signifi-
cant amount of change-out time to the mining cycle.
4.9 Cutting doubles
For example, if a 40-foot cut fills 20 haulers and
Cutting doubles with a SCSS should be avoided, as it takes an additional 15 seconds for the haulers to
the goal of cutting doubles is to reduce the tram time change out due to longer change-out distances, then
between cuts. Because a SCSS usually has an extra an additional 5 minutes are lost to change-out time
person to move the miner that is not cutting, the tram for that single cut. A continuous miner can be moved
time between cuts does not affect the productivity as quite a distance in the extra time that is lost due to
long as the miner is moved and ready to start the next change-outs in that cut. Conversely, for a 20-foot cut
cut before the second miner is finished. that only fills 10 haulers and it takes an additional
For a DCSS, many different cut sequences incorpo- 8 seconds for each hauler in change-out time, then
rating double cuts can be more productive than similar only 1.33 minutes are added to the change-out time in
cut sequences that do not. However, the distance that cut.

617

Copyright © 2005 Taylor & Francis Group plc, London, UK


Table 4. Summary of the variables and their effects on the productivity.

SCSS DCSS
Productivity Change Productivity Change
Scenario tons per unit shift % (tons) tons per unit shift % (tons)

Base case 2166 3144


Longer change-out distances 1781 −17.8 (−385) 2720 −13.5 (−424)
Lower haulage capacity 2044 −5.6 (−122) 3000 −4.6 (−144)
Fewer haulers 2151 −0.7 (−15) 3114 −1.0 (−30)
Distance between belt moves 2166 0 3144 0
Longer cuts in the entries 2196 1.4 (+30) 3214 2.2 (+70)
Cutting doubles 3061 −2.7 (−83)
With haulers turned around 3315 5.2 (+171)
Less unexpected delays 2354 8.7 (+188) 3416 8.7 (+272)
Haulers turned around 2430 12.2 (+264) 3406 8.4 (+262)
Compounded variables 2849 31.5 (+683) 4146 31.9 (+1002)

When the cut sequence was changed to include cut- the productivity dropped from 2166 to 1781 tons or a
ting doubles as shown in Figure 2, the productivity drop of 17.8% (385 tons per unit shift). For the DCSS,
was 3061 tons per unit shift, or 2.7% (83 tons per the drop was even more dramatic. The productivity
unit shift) lower than the base case for the DCSS. This dropped from 3144 to 2720 tons, or a reduction of
was due to losing an extra 5.9 minutes per shift the 13.5% (424 tons per unit shift).
longer change-out distances because the faces were
20 feet further inby at the start of the cycle. The aver-
age tram times per cut were also a bit longer for the 4.11 Compounding variables
cut sequence shown in Figure 2. For the base case, the The examples provided above show the sensitivity of
average was 6.71 minutes of tram time and for the dou- productivity to the changes single factor. Table 4 pro-
ble sequence, the average was 6.82 minutes. However, vides a summary of the variables discussed above
when the haulers were turned around before return- and their effect on the productivity. The goal of mod-
ing to the change-out point, the productivity jumped eling these changes was to quantify the benefits of
to 3315 tons per unit shift or a gain of 5.2% (171 tons the changes so mine management can make more
per unit shift) over the base case. This is 100 tons less informed decisions and focus their attention on the
per unit shift than the base case cut sequence having most critical issues. Without modeling these changes
the cars turned around, which shows the importance first, many frontline supervisors would have been
of minimizing the change-out distance. skeptical of the changes. However, after presenting the
model and the results of the changes, the acceptance
rate proved to be high.
4.10 Minimizing change-out distances When several variables are changed at the same
When using ram-dump type batch haulage, a signifi- time, the effects are compounded. For the hypothet-
cant amount of a shift is taken up by the time it takes ical SCSS, the variables identified above are most
for one hauler to pull away from the continuous miner likely the easiest ways of increasing productivity. To
and another to take its place. Even under perfect condi- demonstrate the effects of compounding, the following
tions, two hours a shift may be lost to haulers changing changes were made to the base case: having the haulers
out. Most miner operators prefer to cut the entries turned around, lowering the unexpected delays from
rather than crosscuts because they are easier and take 120 minutes to 90 minutes, increasing the cut depths
less time, resulting in higher productivity. However, as in the straights from 30 feet to 32.5 feet, decreasing
the straights are cut further inby, the amount of time the in-cut delays from 5 minutes to 4 minutes in the
lost to changing out increases. It should be noted that straights and second cuts in the crosscuts, and decreas-
the continuous miner is not idle during this time, but ing the in-cut delays from 10 minutes to 8 minutes in
is commonly completing other tasks such as cleaning the first cut in the crosscuts.
up, setting over, checking the sights, etc. When these variables were changed in the model,
The effect of change-out distance can be demon- the productivity increased to 2849 tons, or a jump of
strated by having the haulers change out one crosscut 31.5% (683 tons per unit shift) in productivity with-
further back in the cut sequence. This was mod- out any additional expenditure. For the DCSS, the
eled by removing 60 feet from the haul distance and variables were changed as above with one additional
adding it to the change-out distance. For the SCSS, change, the tram delays were reduced from 3 minutes

618

Copyright © 2005 Taylor & Francis Group plc, London, UK


Figure 3. Head-on cut sequence for a SCSS mining a seven-entry room and pillar panel.

to 2 minutes. The productivity for the DCSS jumped may require the cut sequence to be modified to allow
to 4,146 tons per unit shift, for a change of 986 tons or the continuous miners to make the crosscuts straight
a 31.9% increase. Using a sale price of $25 per ton and ahead rather than having to turn to make the cut as
a reject rate of 25%, the productivity increase from the shown in Figure 3. This type of cut sequence has sev-
SCSS would amount to over $12,000 per unit shift in eral advantages and disadvantages. Making the first
saleable coal. For the DCSS, the productivity increase cut in the crosscut straight-on is faster than cutting
would generate almost $18,500 in additional coal sales a turn and the roof tends to be more stable because
per unit shift. the corner of the pillar is not cut away as when the
miner cuts a turn. The roofbolting also takes less time
because fewer rows and fewer moves need to be made
5 OTHER CONSIDERATIONS when the roofbolter is square with the cut.
However, this type of cut sequence is more compli-
5.1 Matching the cut sequence to the mining cated and may be much more difficult for new mining
conditions crews to learn. It may also require more tramming of
the continuous miners and roofbolters.
At some mines, the roof conditions may be such that
the roof falls in the crosscuts before the bolters can
5.2 Cutting in sequence
enter the place. In this condition, the cut depth in the
crosscuts needs to be shortened so the roof can support An underground coal mine is an ever-changing envi-
itself long enough for the bolters to do their job. This ronment, but the cut sequence for a particular mine

619

Copyright © 2005 Taylor & Francis Group plc, London, UK


should be followed to the highest degree possible. the roofbolters on the number of rows of roofbolts they
This will avoid bottlenecks at the face and ensure install each shift.
continuous flow of coal from the unit.This is extremely Mine management should identify key issues at the
important in longwall development or when operating mine such as worker safety, roofbolting, or not fully
a DCSS with ten or fewer entries. utilizing haulage capacity. The first questions asked
An example of this was occurred on a recent visit by mine management should cover these issues. The
to a longwall development section. The top was fair in frontline supervisors will realize that these are the crit-
the entries and the cuts were to 25–30 feet deep. In the ical issues and they should be given at least equal
crosscuts, the roof was bad and the cuts were limited priority production.
to about 15 feet. The pillars were on 150 by 75 foot
centers and the crosscuts were staggered 75 feet. The
unit had two roofbolters on the section to try keep the 6 CONCLUSIONS
roofbolting ahead of the mining.
The night shift had driven the left entry forward As shown, there are many variables that have an effect
two extra cuts past where the crosscut should have on the productivity from an underground coal mine.
been rather than starting on the crosscut. Because of There are many more variables than those shown here,
this, the day shift could not make any additional cuts but these were the most common encountered during
in that entry. This left them the middle entry and the the miner productivity training program. One of the
right entry to mine. The miner made the cuts in about goals of this paper was to illustrate the need for mines
half the time it took the roofbolters to bolt them, so to model their production systems and determine if fur-
the miner had to wait 20–40 minutes after every cut ther improvements can be made. Many of the changes
for the roofbolters to finish and move before making suggested can be implemented with minimal effort and
the next cut. There may have been circumstances that may have a profound effect on the productivity at no
caused this to occur, but if it was a decision made additional cost.
by the supervisor of the night shift, then the loss of
production could have been minimized by cutting in ACKNOWLEDGEMENTS
sequence rather than cutting to meet his footage quota
that shift. This would have allowed the day shift to The authors would like to acknowledge the work done
cut in all three entries rather than being limited to two by Stan Suboleski and thank him for providing his
entries and would have significantly reduced the wait- mine model spreadsheet to the public. For a free copy
on-bolter time for the day shift. of the model, contact Dr. Kroeger and a copy of the
spreadsheet will be emailed to those interested.
5.3 Identifying and reinforcing the The authors would also like to thank the Office
important issues of Coal Development of the Illinois Department of
Commerce and Economic Opportunity for funding the
Everyone at the mine knows the importance of produc- miner productivity training program. In addition to the
tion and this is an issue that is always at the forefront funding agencies, the authors would also like to thank
of their minds. Even though mine management knows the mines that participated in the program.
this, the first question that is asked is of the frontline
supervisors is about the production. This reinforces the
fact that production is the highest priority and all other REFERENCES
issues are secondary. This may not actually be the case,
but this may be the perception management is giving Energy Information Administration, 2002, Annual Coal
by asking about production first.The frontline supervi- Report, U.S. Department of Energy, Washington, D.C.
sors will track the items that they believe management King, R.H. and Suboleski, S.C., 1991, Opportunities for
wants to know. For example, if roofbolting is an issue Continuous Mining Productivity Improvements, Mining
Engineering, October, pp. 1226–1231.
and management started asking the supervisors how Suboleski, S.C. and King, R.H., 1990, Estimating Technol-
many rows of roofbolts were installed on their shift ogy’s Impact on Underground Coal Productivity, Mining
each day, then the supervisors would see that roofbolt- Engineering, October, pp. 1159–1164.
ing is an important issue and they should start tracking Suboleski, S.C. and Donovan, J.G., 2000, Super Sections
that number. They would in turn focus the attention of Prove Worthy, Coal Age, August, pp. 32–36.

620

Copyright © 2005 Taylor & Francis Group plc, London, UK

You might also like