Professional Documents
Culture Documents
E.B. Kroeger
Mining & Mineral Resources Engineering, Southern Illinois University, Carbondale, Illinois, USA
M. McGolden
CoalTec, Newburgh, Indiana, USA
ABSTRACT: Over the last two years, the State of Illinois supported an underground miner productivity training
grant through the Illinois Clean Coal Institute. The main goal of this grant was to provide training to underground
coal mines in Illinois in an effort to increase mine productivity. It was hoped that by providing training to mine
personnel on how to make small changes to cyclic procedures, productivity increases would come at no additional
cost to the mines. Project staff conducted site walkthroughs and time studies underground at seven different mines
for four coal companies. The focus of the visits was the continuous miner cycle as all the underground mines in
Illinois use a continuous miner for production or longwall development. Data from the time studies were entered
into a spreadsheet that modeled mine productivity. Variables were changed in the models to predict productivity
increases that could be achieved by making changes suggested and to show sensitivity of the variables on the
productivity. The objective was to help the operations quantify the benefits of the specific changes so they
could make more informed decisions and focus their attention on the most critical issues. The findings from
the walkthroughs and mine models were incorporated into a miner productivity training presentation. Training
sessions were provided to mine management and frontline supervisors at five mines and additionally, to hourly
workers at one mine. In all, productivity increases ranging from 10% to 34% were suggested at each mine by
project staff at no additional production cost to the mines. If fully adopted, productivity from these mines would
increase by an estimated 2 million clean tons of coal per year, resulting in an additional $50 million in coal sales
from these five mines. Each mine visited had its specific challenges, but several had common issues. The issues
that kept recurring were not fully utilizing haulage capacity, mining out of sequence, and not taking the longest
cut possible. To illustrate the sensitivity of the productivity to these variables in a continuous miner production
panel, a hypothetical nine-entry, room-and-pillar mining plan was created and analyzed using a mine-modeling
spreadsheet. Results from the mine models are presented along with recommendations for possible changes to
increase productivity.
611
612
have to unload at the same time. This usually causes a analysis of the cut sequence are provided in Table 1.
slight delay in the unloading of the hauler that arrives In addition to these variables, three more variables are
to the feeder after the first hauler. Most mines that typically needed to accurately model a mining system:
operate battery haulers in a DCSS usually unload onto number of haulers used, tram delays, and in-cut delays.
the sides of the feeder, allowing the entry directly inby These variables can be input and changed from cut-to-
the feeder to be used for short-term storage. For mines cut on the cut sequence entry page in the model. In
that operate cable shuttle cars, the cable anchor points the hypothetical cut sequence mined using a SCSS,
require haulers to unload from the front and both sides the number of haulers used was four, tram delays were
of the feeder. This requires the feeder to be placed in set to zero, and the in-cut delays were set to 5 minutes
the middle of the intersection. except for the first cuts in the cross-cuts, which were
Since most of the mines visited during the first year set to 10 minutes, recognizing that cutting a turn takes
of the training program operated ram-dump type cars, longer. In the hypothetical DCSS cut sequence, the
the following analysis is for that type of equipment number of haulers used was four, tram delays were
and the analysis should not be inferred to work with set to three minutes, and the in-cut delays were set to
cable shuttle cars. The following analysis also assumes 5 minutes except for the first cuts in the cross-cuts,
that there are no delays in the roofbolting that would which were set to 10 minutes. These are typical values
cause the continuous miners to wait on the roofbolter. measured from time studies during the first year of the
For the base case scenarios, the variables used in the training program.
613
614
615
616
The effect of cut depth was demonstrated by increas- between the double cuts should be minimized to ensure
ing the cut length in the entries from 30 feet to 32.5 feet. the change-out distances are minimal. For mines that
This allows the hypothetical mine to skip nine cuts in employ long cuts in their cut sequences, adding to
a sequence every six crosscuts. The mine model indi- the change-out distance can be disastrous on the pro-
cated the productivity would increase by 1.4% (30 tons ductivity. Many miner operators will drive the entries
per unit shift) for a SCSS and 2.2% (70 tons per unit forward an extra cut before the crosscuts are fin-
shift) for a DCSS. ished (cut 37 would be made before or after cut 27
in the sequence in Figure 2). This can add a signifi-
cant amount of change-out time to the mining cycle.
4.9 Cutting doubles
For example, if a 40-foot cut fills 20 haulers and
Cutting doubles with a SCSS should be avoided, as it takes an additional 15 seconds for the haulers to
the goal of cutting doubles is to reduce the tram time change out due to longer change-out distances, then
between cuts. Because a SCSS usually has an extra an additional 5 minutes are lost to change-out time
person to move the miner that is not cutting, the tram for that single cut. A continuous miner can be moved
time between cuts does not affect the productivity as quite a distance in the extra time that is lost due to
long as the miner is moved and ready to start the next change-outs in that cut. Conversely, for a 20-foot cut
cut before the second miner is finished. that only fills 10 haulers and it takes an additional
For a DCSS, many different cut sequences incorpo- 8 seconds for each hauler in change-out time, then
rating double cuts can be more productive than similar only 1.33 minutes are added to the change-out time in
cut sequences that do not. However, the distance that cut.
617
SCSS DCSS
Productivity Change Productivity Change
Scenario tons per unit shift % (tons) tons per unit shift % (tons)
When the cut sequence was changed to include cut- the productivity dropped from 2166 to 1781 tons or a
ting doubles as shown in Figure 2, the productivity drop of 17.8% (385 tons per unit shift). For the DCSS,
was 3061 tons per unit shift, or 2.7% (83 tons per the drop was even more dramatic. The productivity
unit shift) lower than the base case for the DCSS. This dropped from 3144 to 2720 tons, or a reduction of
was due to losing an extra 5.9 minutes per shift the 13.5% (424 tons per unit shift).
longer change-out distances because the faces were
20 feet further inby at the start of the cycle. The aver-
age tram times per cut were also a bit longer for the 4.11 Compounding variables
cut sequence shown in Figure 2. For the base case, the The examples provided above show the sensitivity of
average was 6.71 minutes of tram time and for the dou- productivity to the changes single factor. Table 4 pro-
ble sequence, the average was 6.82 minutes. However, vides a summary of the variables discussed above
when the haulers were turned around before return- and their effect on the productivity. The goal of mod-
ing to the change-out point, the productivity jumped eling these changes was to quantify the benefits of
to 3315 tons per unit shift or a gain of 5.2% (171 tons the changes so mine management can make more
per unit shift) over the base case. This is 100 tons less informed decisions and focus their attention on the
per unit shift than the base case cut sequence having most critical issues. Without modeling these changes
the cars turned around, which shows the importance first, many frontline supervisors would have been
of minimizing the change-out distance. skeptical of the changes. However, after presenting the
model and the results of the changes, the acceptance
rate proved to be high.
4.10 Minimizing change-out distances When several variables are changed at the same
When using ram-dump type batch haulage, a signifi- time, the effects are compounded. For the hypothet-
cant amount of a shift is taken up by the time it takes ical SCSS, the variables identified above are most
for one hauler to pull away from the continuous miner likely the easiest ways of increasing productivity. To
and another to take its place. Even under perfect condi- demonstrate the effects of compounding, the following
tions, two hours a shift may be lost to haulers changing changes were made to the base case: having the haulers
out. Most miner operators prefer to cut the entries turned around, lowering the unexpected delays from
rather than crosscuts because they are easier and take 120 minutes to 90 minutes, increasing the cut depths
less time, resulting in higher productivity. However, as in the straights from 30 feet to 32.5 feet, decreasing
the straights are cut further inby, the amount of time the in-cut delays from 5 minutes to 4 minutes in the
lost to changing out increases. It should be noted that straights and second cuts in the crosscuts, and decreas-
the continuous miner is not idle during this time, but ing the in-cut delays from 10 minutes to 8 minutes in
is commonly completing other tasks such as cleaning the first cut in the crosscuts.
up, setting over, checking the sights, etc. When these variables were changed in the model,
The effect of change-out distance can be demon- the productivity increased to 2849 tons, or a jump of
strated by having the haulers change out one crosscut 31.5% (683 tons per unit shift) in productivity with-
further back in the cut sequence. This was mod- out any additional expenditure. For the DCSS, the
eled by removing 60 feet from the haul distance and variables were changed as above with one additional
adding it to the change-out distance. For the SCSS, change, the tram delays were reduced from 3 minutes
618
to 2 minutes. The productivity for the DCSS jumped may require the cut sequence to be modified to allow
to 4,146 tons per unit shift, for a change of 986 tons or the continuous miners to make the crosscuts straight
a 31.9% increase. Using a sale price of $25 per ton and ahead rather than having to turn to make the cut as
a reject rate of 25%, the productivity increase from the shown in Figure 3. This type of cut sequence has sev-
SCSS would amount to over $12,000 per unit shift in eral advantages and disadvantages. Making the first
saleable coal. For the DCSS, the productivity increase cut in the crosscut straight-on is faster than cutting
would generate almost $18,500 in additional coal sales a turn and the roof tends to be more stable because
per unit shift. the corner of the pillar is not cut away as when the
miner cuts a turn. The roofbolting also takes less time
because fewer rows and fewer moves need to be made
5 OTHER CONSIDERATIONS when the roofbolter is square with the cut.
However, this type of cut sequence is more compli-
5.1 Matching the cut sequence to the mining cated and may be much more difficult for new mining
conditions crews to learn. It may also require more tramming of
the continuous miners and roofbolters.
At some mines, the roof conditions may be such that
the roof falls in the crosscuts before the bolters can
5.2 Cutting in sequence
enter the place. In this condition, the cut depth in the
crosscuts needs to be shortened so the roof can support An underground coal mine is an ever-changing envi-
itself long enough for the bolters to do their job. This ronment, but the cut sequence for a particular mine
619
620