Proposal Form
1. Executive Summary
Compassion International –Uganda operates in partnership with 324 Implementing Church Partners (ICPs) to
deliver a holistic child development program. In this respect, Compassion International –Uganda and ICPs
mutually contribute to the holistic development of registered children with an aim of preparing them to get skills
and knowledge that they require to grow and become responsible Christian adults.
Compassion International -Uganda advocates for children and takes deliberate effort to release them from poverty
in Jesus’ name. The ministry of Compassion International emphasizes that the most effective way to address
poverty is through educating, training and discipling children. Compassion provides unique learning
opportunities for the registered children. The Implementing Church Partners (ICPs) support the children with the
help of the Child development workers, and volunteers.
The main challenge faced by ICPs is that a number of them do not have safe and conducive structures to facilitate
effective learning. UG 575-Chekwir Child Development Centre is one of the ICPs that need support for
infrastructure development.
In an endeavor to address this, UG 575 plans to construct a classroom block with 5 rooms to enable children to
benefit from the curriculum in a safe and healthy environment. The efforts of UG 575 and the caregivers have
been prohibited by low income . Chekwir relies on local contribution from the caregivers, but it is too inadequate
to be used on such an infrastructure project.
The main objective of this activity therefore is to provide a conducive learning environment for 230 children.
Through this project, UG 575 will create space where the children will sit comfortably while learning. UG 575
will contribute locally towards the project by availing resources such as land and unskilled labor. During
implementation, the contact person for this project will be the Project director.
The classrooms will benefit 230 registered children and indirectly benefit over 300 caregivers and 3 ICP staff,
who will use the facilities for meetings. The construction phase is planned to start in March 2015 and end in April
2016.
UG 575-Chewir is one of the ICPs that demonstrate effective vision and leadership in the development of the
cognitive, social, economic, spiritual and physical characteristics of registered children.
UG 575 is located along Mbale -Kapchorwa –Kitale road, 52kms from Kapchorwa town. It is also located on the
slopes of Mountain Elgon. The Centre was established in 2013 and is currently supporting 230 children. The
children attend Centre days every Saturday, and participate in the curriculum activities that include skills training,
Christian lessons and practical exercises. However, they face many challenges resulting from dusty/unhygienic
class facilities with leaking roofs.
Chekwir village where the ICP is located is one of the poverty stricken areas in Eastern Uganda. Caregivers
spend many days without earning any income. As a result, they are not able to put resources together to work on
the construction of decent classrooms. Regardless of the limitation, in the past they made an effort to build the
existing classrooms which need replacement at the moment.
This proposal therefore seeks to raise funds to set up a five classroom block to create a good and safer learning
environment for the registered children at UG575. This intervention is a priority need, and is in line with the
Compassion International-Uganda’s strategy to enhance child attainment of programmatic outcomes through
infrastructure improvement at ICP level.
3. Problem Statement/Description:
A conducive and healthy environment is critical for the development of children. In an attempt to implement the
curriculum an improved learning environment , todate UG 575 caregivers and church borrowed an old school
structure made of off-cuts and wattle, but the structure leaks and an alternative one is urgently needed at the
church premises . The age groups of the children are indicated below. The children need to be divided
accordingly, during center day programing, but the current rooms available are inadequate.
Chart showing age groups and the number of children per group at UG 575 -Chekwir
2
in their age groups.
Due to the dusty floor and walls, the children frequently suffer from hygiene related illnesses such as cough, and
skin infections.
The caregivers are not in position to address the situation due poverty. Construction of permanent classroom
blocks will contribute to creating a safe learning environment for registered children to demonstrate commitment
to the Lordship of Christ, to support them to choose good health practices, to exhibit the motivation and skills to
be economically self-supporting, and to interact with each other in a healthy and compassionate manner.
4. Objectives:
Specific objectives
1. To enable 230 children to benefit from Child sponsorship when they are healthy and attain child
development milestones by the time they complete the program.
2. To avail adequate resources for classroom construction in order to provide a favorable learning
environment for a total of 230 registered children by April 2016.
3
5.1.1 Contract management
UG 575 leadership and Umbrella partner – (Perfection church and ministry) will identify the contractor
through competitive bidding process. The contract will be signed by UG 575 Umbrella Partner
according to the regulations of the denomination. Day today management of classroom construction
will be handled by the Church Partner Committee.
The Partnership Facilitator (P.F) will be the contact Person for Compassion International –Uganda
during the time of implementation. The P.F will conduct monitoring visits and will report to the
Supervisor who will be available to provide guidance from time to time.
All implementation reports will be submitted to the Country Management Team through the Program
Director.
4
-Procurement of Contract March 2015 -Church UG 575 –
contractors and signed Partner Chekwir
signing of contract Committee
agreement. (CPC)
-Procurement of members
materials.
MONITORING SCHEDULE
ACTIVITY INFORMATION HOW INFORMATION PERIOD/PEOPLE
TO COLLECT WILL BE COLLECTED RESPONSIBLE
-Procurement -Bid documents -Take minutes during CPC March 2015
of contractors submitted to Chekwir meetings. -Church Partner
and signing of CDC/Procurement -Report of bid opening. Committee (CPC)
contract process. -Report for award of members
agreement. contract.
-P.F
-Completion of -Multiple pro forma -Make a copy of invitation -April 2015 to April
construction invoices. of suppliers. -Produce the 2016 -CPC/Project
work on the -Types of report of the market -Director
hall. construction survey.
materials. -Keep stores records.
EVALUATION INDICATORS
Objective Indicator How to measure Person responsible
1. To enable 230 Number of children - Demonstration of -Project Director
children to benefit from utilizing the classroom child achievement of P.F
Child sponsorship when during center days milestones,
they are healthy and classroom
attain child
development milestones
by the time they
complete the program.
To avail adequate Number of classrooms - Observation through Program Director
resources for classroom completed site supervision.
construction in order to
provide a favorable
learning environment
for a total of 230
registered children by
April 2016
6
damp course
Sand - 18 trips x 200,000/= 3,600,000 1,440 1,440
Cement - 100 bags x
3,000,000 1,200
30,000/= ,1,200
Coarse aggregates- 12 trips x
1,800,000 720
150,000/= 720
PRC Wire A98 6
2,160,000 864 864
rolls*360,000/=
Marram 15 trips *100,000/= 15,000,000 6,000 6,000
Hard coarse (stones) 30
3,000,000 1,200 1,200
trips*100,000/=
Bricks -12,000 pieces
6,000,000 2,400
x500 /= 2,400
River sand 12 trips x
2,400,000 960
200,000/= 960
Timber - 64 pieces x
960,000 384 384
15,000/=
Water proof material
600,000 240
-3pieces x 200,000/= 240
Transport - 2 routes x
400,000 160
200,000/= 160
Sub total 22,180,000 8,872
8,872
Super structure work -
(work above the damp
course)
Cement - 300 bags x
9,000,000 3,600
30,000/= 3,600
Sand - 12 trips x 200,000/= 2,400,000 960
960
Bricks – 38,838 x 500/= 19,419,000 7,767.6 7,767.6
Iron bars - 40 pieces x
1,120,000 448
28,000/= 448
Styr up wires - 50 pieces x
500,000 200
10,000/= 200
Binding wires - 30Kg x
180,000 72
6,000/= 72
Timber shuttering boxes - 40
600,000 240
pieces x 15,000/= 240
Coarse aggregates - 3 trips x
450,000 180
150,000/= 180
Ventilators - 200 pieces x
800,000 320
4,000/= 320
Paint brushes - 10 pieces x
30,000 12
3000/= 12
Related transport costs - 2
400,000 120
routes x 200,000/= 160
6 technical builders 4 weeks
4,800,000 1,920
x 200,000 1,920
7
Sub total 39,699,000 15879.6
15,879.6
Roofing
Timber
6 x2” - 80 pieces x 10,000/= 800,000 320
320
4 x3” - 75 pieces x 10,000/= 750,000 300
300
3 x2” -100 pieces x 6000/= 600,000 240
2 40
4 x 2” -94- pieces x 7,000/= 658,000 263
263
8 x1” -38 pieces x 13,000/= 494,000 198
198
9 x1” boards -75 pieces x
1,125,000 450
15,000/= 450
Wire nails (assorted) -
-
2” - 15 kg x 5,000/= 75,000 30
30
3” - 20 kg x 5,000/= 100,000 40
40
5" -10kg *5000/= 50,000 20
20
4” -18 kg x 5,000/= 90,000 36
36
6” -15 kg x 5,000/= 75,000 30
30
Roofing nails -34 kg x
204,000 82
6,000/= 82
Rubber washers 6pieces x
72,000 29
12,000/= 29
Timber preservatives -10 tins
200,000 80
x 20,000/= 80
Galvanized iron sheets
(gauge 28) -243 sheets x 17,010,000 6,804
6,804
70,000/=
Ridges - 60 pieces x
900,000 360
15,000/= 360
Paint brushes - 10 x 2500/= 25,000 10
10
65 scaffold poles x 4000/= 260,000 104
104
Hoop irons -25 rolls x
1,000,000 400
40,000/= 400
Sub total 24,488,000 9795.2
9,795.2
Shutting -
-
Doors - 5 doors x 300,000/= 1,500,000 600
8
600
Metallic window frames –
5,000,000 2,000
25 x 200,000/= 2,000
Tinted glasses - 115 pieces x
5,750,000 2,300
50,000/= 2,300
Putty - 65kg x 2,000/= 130,000 52
52
Labor for roofing and
shutting -6 People x 1,800,000 720
720
30,000/= x 10 days 1800,000
Related transport costs 2
300,000 120
routes x 150,000/= 120
Sub total 14,480,000 5,792
5,792
Ceiling
4''x2'’ - 75 pieces x 10,000/= 750,000 300
300
3''x2'' - 75 pieces x 10,000/= 750,000 300
300
Assorted wire nails - 20 kg
100,000 40
x 5,000/= 40
Ceiling nails - 30 kg x
150,000 60
5,000/= 60
Ceiling boards - 100 pieces x
5,000,000 2,000
50,000/= 2,000
Sub total 6,750,000 2,700
2,700
Finishing of floor, walls,
verandah and other -
-
sections
Cement - 100 bags x
3,000,000 1,200
30,000/= 1,200
Paint – Water paint -63 jerry
3,465,000 1,386 1,386
cans x 55,000/=
- Oil paint - 88 tins x
3,520,000 1,408
40,000/= 1,408
Sand papers - 1 piece x
50,000 20
50,000/= 20
oxide powder 25kg*10,000 250,000 100
100
Over all technical builder 60 1200
3,000,000 1,200
days x 30,000/= 720
Sub total 10,321,000 4,128
4,128
Furniture
Desks 200*75,000 15,000,000 6,000
6,000
wall black boards 5*50,000 250,000 100
100
Assorted Transport 3trips x 600,000 240
9
200,000/= 240
Sub total 6,850,000 2,740
2,740
Caregiver's local labor - 40
1,800,000 720 -
caregivers x15x 3000/= 720
Land - 1 Project x
8,000,000 3,200 -
8,000,000= 3,200
9,000,000 3,600
3,600
Total 38,682
106,505,240 42,602 3,920
US $ 1=
Exchange rate
2,500/=
Budget Summary:
Budget Summary
National Amount in Local Amount
(subtotals of each main
currency US $ contribution requested
category of expense)
Site clearance
1,858,865 744 744
Sub structure –below the
damp course 12,988,000 5,195 5,195
Super structure work -(work
11,301
above the damp course) 28,253,375 11,301
Roofing
15,204,000 6,082 6,082
Shutting
14,480,000 5,792 5,792
Ceiling
6,750,000 2,700 2,700
Finishing of floor, walls,
verandah and other sections 10,321,000 4,128 4,128
Furniture
6,850,000 2,740 2,740
Caregiver labor and land 3,920
9,800,000 3,920 -
Total
106,505,240 42,602 3,920 38,682
US $ 1=
Exchange Rate
2,500/=
Disbursement Schedule:
Uganda Country office requests for the grant of US $ 38,682 for UG 575 in February 2015.
Future Feasibility
After completion of the class rooms, future maintenance will be the responsibility of the Implementing Church
Partner.
Conclusion
10
This activity will bring a positive change in the learning environment of Compassion assisted children.
11