Table of Content
INTRODUCTION 7
SAFETY LEADERSHIP 16
2
ORGANOGRAM 18
SAFETY RISK 19
ENVIRONMENTAL RISKS 21
Stop Look Assess Manage (SLAM) 22
TRAFFIC MANAGEMENT 23
VEHICLE OPERATION 23
SIGNS 23
SHE INDUCTION 24
b) Pre-Task Risk Assessment Training 24
C) COMMUNICATION AND CONSULTATION 25
D) DOCUMENT AND RECORDS MANAGEMENT 26
FALLING OF LOADS: 27
SIMULATION PLAN 28
PROJECT CLOSE-OUTS 31
REFERENCES 32
APPENDIXES 32
4
INTRODUCTION
Staff Connect (Pty) Ltd has developed a SHE Management Plan so as to give an insight to areas
that will require attention in terms of Hazards, Activities, Products and Services in a safe manner
through developing and implementing Policies, Procedures and Risk assessment processes. Our
SHE management Plan is aligned to OHSAS 18001:2007 and ISO 14001: 2004 standards and
takes into consideration Debswana Site Rules, Regulations and Botswana legislation.
(a) SCOPE AND PURPOSE OF WORK
The purpose of this safety health and environment plan is to guide and provide SHE framework
to management and our employees in order to implement the SHE programmes.
The scope of work for this project is to:
Transportation ,Delivery of material on site
Off- loading of material on Site
Fabrication of access step ladder
Welding of access step ladder
Fabrication of support stands
Erection of scaffolding
Installation of support stands
Installation of life wire
Installation of corner units
Installation of transmax sliders
Installation of retractable life lines
Demobilisation
housekeeping
Hand over
b) EXCLUSIONS FROM THE SCOPE OF WORK
Staff Connect is not responsible for erection of scaffolding, Rand sandblasting to erect the
scaffolding in all areas to be worked on.
5
HEALTH, SAFETY AND ENVIRONMENT POLICY
Staff Connect Pty Ltd is a 100% citizen owned company that seeks to provide its products and
services to customers and clients around the industry. In so doing, the company is committed to
the protection of safety and health of the workers as well as its clientele and stake-holders,
including the equipment and the environment within which we operate.
To this end, Staff Connect strives to promote and balance its business prospects with sound and
reputable safety and health practices and responsibilities by maintaining good working conditions
and relations to safe guard our employees , contractors ,visitors and workers of clientele within
which we operate against injury and occupational health risks. We further strive to reduce the
impacts associated with our activities products and services on the environment and the
surrounding communities.
This is made possible by our compliance to Botswana and international standards laws and
legislation to SHE legal requirements and to other requirements as may be laid down by our
clientele to which we operate. Guided these requirements, we are therefore committed to;
Periodic identification of hazards and aspects as well as assessment of risks and impacts
due to our activities, products and services;
Preventing injuries and ill health to workers as well as pollution and depletion of the
environment
Continual improvement of our SHE performance and that of our clientele.
Communicating this policy to persons working for or on behalf of staff connect
Managing natural resources and waste responsibly
Promoting a SHE culture and personnel behaviour aligned with this policy
Periodic review of this policy when necessary
Promote sustainable development
To achieve this, we are committed to ensure our safety talks are conducted at every start of shift
during which HSE representatives; SHE Stewards, first aid & hygiene coordinators will be
appointed as custodians of sections SHE files where records and forms are kept to be accessed
upon demand
6
EFFECTIVE 26 January 2018 NEXT REVIEW DATE:26/01/2019
DATE:
In compliance with the applicable legislation, all employees are eligible to go through medical
examination certified by an accredited medical officer prior to their engagement with staff
connect to ensure that they are fit for duty. The company is further committed to releasing
employees for such medical examination on a periodic annual basis or as and when required. The
company further undertakes to respect the health status of every employee and their rights, as
well as to maintain confidentiality. Staff Connect commits to zero tolerance to stigmatization of
any kind.
Staff Connect recognizes the seriousness of HIV/AIDS epidemic and its impact on the workforce
and the economy. We therefore stand firm and support the government’s efforts and strategy to
reduce the impact of the scourge.
The purpose of this policy to ensure a consistent and equitable approach to the prevention of
HIV/AIDS among employees and their families and to the management of the consequences of
HIV/AIDS including the care and support of employees living with HIV/AIDS. The policy has
been developed and will be implemented in consultation with employees at all levels. It is in
compliance with existing laws regarding the subject.
Staff Connect does not discriminate or tolerate discrimination against employees or job
applicants on any grounds including HIV status. As a company, we recognize that there are
circumstances unique to HIV infection, this policy rests on the principle that HIV infection and
AIDS should be treated like any other serious conditions or illness that may affect employees. It
takes into account the fact that employees with HIV may live full and active lives for a number of
years. The company’s commitment to maintaining a safe and healthy work environment for all
employees is based on the recognition that HIV is neither spread by casual contact nor airborne.
To this end, HIV positive employees will be protected against discrimination, victimization or
harassment. Otherwise serious company disciplinary and grievance procedures shall apply
equally to all employees.
7
Appropriate awareness education programmes will be conducted to inform employees about
HIV/AIDS which will enable them to protect themselves and others against infection by HIV.
Furthermore, we recognize the importance of involving employees and their representatives in
planning and implementation of awareness, education and counselling programmes. This will be
rolled out through nominated peer counsellors. Through community health centers within the
region, male and female condoms will be distributed to staff on regular basis. Training shall be
arranged for all employees including managers, supervisors and reasonable time off will be given
for participation in such education and training.
The Human Resources Manager, assisted by all safety officers, shall coordinate and implement
this HIV/AIDS programme. He/she will report to the board on three months basis.
This policy will be reviewed annually and revised as necessary in the light of changing
conditions and the findings of surveys/ studies conducted.
Staff Connect (Pty) Ltd has developed and implemented a policy to protect its non-tobacco
smoking employees and visitors from the exposure to second hand tobacco smoking policy. This
policy is based on implementing the legal requirements as prescribed in the Control of Smoking
(Chapter 65:04) Act 28 of 2004. The policy would seek to prevent risks of fire incident due to
improper disposal of used lit cigarette (Refer to smoking control policy Appendix 003)
ii) DRUG AND SUBSTANCE ABUSE POLICY
The objective of this policy is to insure all employees understand and comply with this procedure
in order to prevent any employee coming under influence and so ensuring alertness, health and
safety of all employees in the work place.
Site Rules and Regulation (STD-SHE-017) Clause Number 7.4.20.1and 7.4.20.2 state that:
Intoxicating liquor and narcotic drugs are not permitted in the mine, and Debswana premises and
any person found under the influence or appears to be under the influence under this Regulation
will be removed and not permitted back to the mine
Staff Connect (Pty) Ltd will carry out random testing for alcohol on site and refer those
suspected to be under the influence of drugs to the hospital for further testing:
8
FATAL RISK CONTROL STANDARDS
Staff Connect (Pty) Ltd will adhere and comply to Debswana Fatal Risk Control
Standards (FRCS) and before commencement of work, Employees will undergo FRCS
induction/briefing. Self-assessment audits shall be undertaken at specified periods. The
following are applicable standards.
FRCS 6. Isolation-
Isolation shall provide positive protection against harm and shall be achieved by use of locking
devices or the establishment of a physical barrier or separation. Designated isolation points shall
be labelled clearly to identify the circuit or system being isolated or locked out. We shall acquire
isolation permit, permit to work, and use of competent, appointed electricians
9
FRCS 7. Working at Heights-
All employees working at heights will have certified competency training, and all equipment for
working at heights shall comply with and be used in accordance with relevant approved design
standards and manufacturer’s specifications. Where personnel are required to work within two
meters of an opening where they could fall, they shall use personal fall restraint equipment, such
as fixed lanyard and harness as a minimum which will prevent falls. All forms of portable and
movable work platforms shall conform to relevant approved design standards. Personnel in the
work platforms shall each wear a correctly fitted harness attached by a lanyard to a suitable
anchor point.
Scaffold to be inspected daily & tagged accordingly by a competent person. The scaffold will only be
used when it is completely safe, with toe-boards, secure platforms, guard rails, stair case with trap door,
secure base jacks and locked wheels. Personnel working at heights must go for working at heights training
before work commences. No one shall be allowed to work at height under the influence of alcohol &
drugs. In addition to safety belts, safety helmets with chin straps must be worn. There must be adequate
warning signage and work area barricaded.
10
Use of mobile equipment to Provision of Crane Truck and Adhere to FRCS (2 (Surface Mobile
transport spares to laydown tele-handler to transport Equipment) Operator will be authorised
area components to site by Mine Training to operate Crane
Truck and mobile lift inside mine lease
area. Checklists will be provided to do
daily checks on the machine.
Taking of material and We will use crane truck to hoist Adhere to FRCS -8 (lifting
Equipment to site equipment and material to Operations)legal appointed riggers will
designated work areas e.g. be assigned to carry out all rigging
shells, liners, gas bottles activities, Equipment used will be color
coded and approved safe for use before
any lifting takes place.
Removal of scrap We will use LDV to remove Adhere to FRCS- separation of waste at
scrap metal and dispose at source and disposing it accordingly.
designated areas
Staff Connect (Pty) Ltd goal will ensure the successful completion of this project.
To prevent outbreak of fires during Project Execution
To achieve zero fatalities resulting from falling from heights by training all employees for
working at Heights before execution of the Project.
Prevent Induced Hearing loss during Project Execution.
To achieve 100% medical examination surveillance compliance
TABLE NO. 2 Below shows objectives & targets of Staff Connect this project and management
programmes:
Objecti Objectiv Manageme Action Resource Who When Stat Lin
ve e nt plans s us k to
Numbe Programm (Persons, BR
r es/ Budget, A
Projects Equipmen
t required)
STFC- To To provide 80% Training Site 30 On
OBJ- prevent all closure of of manager/Superv Octob goin
001 outbreak firefighting findings personnel, isor er g
of fires equipment for the briefs on 2018
12
during in areas week Emergenc
Project where hot within 2 y
Executio work is days of Preparedn
n taking being ess
Place reported
,Inspection
s
STFC- To Trainings, PTO,s to Awarenes Supervisor 30 On
OBJ- achieve Inspection be s to Octob goin
002 zero of safety conducted personnel, er g
fatalities harness during Briefs on 2018
resulting daily, Project Procedure
from Briefs on Execution s
falling Procedures to enforce
from and complianc
heights Policies e
STFC- To Medical 100%medi Medical Manager 30 On
OBJ- achieve examinatio cal awareness Octob goin
003 at least ns are certificate er g
90% conducted 2018
medical periodicall
surveilla y to all
nce by employees.
end of
Decembe
r 2018
STFC- Prevent Risk based 100% Medical Manager 30
OBJ- induced medicals Medical Awarenes Octob
004 hearing certificate s er
loss 2018
during
Project
Executio
n
DATE:
SIGN:
13
D. SAFETY LEADERSHIP
SHE standards by participating in the Remmogo SHE programme, through our monthly SHE
meetings and site walkabouts, VFLs done on site will be communicated and findings shared with
the client for logging in Isometrix.
a) Legal Requirements
The following acts govern activities of the project and the relevant sections of the acts are
detailed in the Baseline risk assessment (BRA):
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 319
Drivers to ensure that vehicles have necessary safety requirements
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 77&79
Protective Equipment
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 149 &150
Fire prevention
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 477
Welding
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 30
Responsibility of employees
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 39
First aid provision
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 276
Housekeeping
Wildlife Conservation and National Parks Act 28 of 1992 Chapter 38:01 Regulation 17
Protected game animals
Control of Smoking (Chapter 65:04) Act 28 of 2004 Regulation 4 and 6
Waste Management Act 15 of 1998 Regulation 34 Prohibition to litter
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 185
Protection of Persons and apparatus
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 186
Inspection examination and testing of apparatus
Road Traffic (Chapter60:01) Act Regulation 30 Drivers to be licensed.
Road Traffic (Chapter60:01) Act Regulation 44 Speed limit
Employment Act of 1982 Part VIII-Regulation 96 Hours of work
Water Act CHAPTER 34:01 Regulation 4 Use of public water and construction of
works Cap 34:03
Mines, Quarries, Works and Machinery Act 20 of 1973: cap 44:02 Regulation 480 Gas
cylinders
14
Botswana Factories Act (Chapter 44:01) Regulation 32 Cranes and other lifting
machines
b) Other Requirements
Debswana Site Rules and Regulations
Debswana Incident Notification and Investigation
Botswana Chamber of Mine Classification of Incidents
Fatal Risk Control Standards
Botswana National Policy on HIV & AIDS of 2012
Remmogo SHE Programme
C) Internal Appointments
Staff Connect (Pty) Ltd will ensure the appointments for the following personnel:
The appointee shall be nominated from site and must be familiar with the site rules and
Regulations
First Aiders shall be briefed on First Aid Procedure no: PR-HR-TRN-06, and shall under go
first aid training (Advanced)
d) Legal Appointments
The project hazards and risks, the adopted legal structure applicable to this project is:
Site Supervisor will be appointed under regulation 14.2 (1) Mechanic in Charge as per Mines,
Quarries, Works and Machinery act 20 of 1973, Cap 44:02.
Boilermaker will be appointed under regulation 14.2 (b) Boilermaker as per Mines, Quarries,
Works and Machinery act 20 of 1973, Cap 44:02.
15
ORGANOGRAM
OPERATIONS
MANAGER
MR MONTWEDI
MAKABEA
ASSISTANT ASSISTANT
PHAKEDI KITSO
PHOKOJE KETSHABILE
The risks identified, will be assessed as to their potential severity of loss and to the probability of
occurrence. The following are safety risks that have been identified, refer to Appendix 006.
16
SAFETY RISK
Activity Hazard Risk Mitigation
Site Preparation Baboons Attacks from baboons Briefs from conservation
interfering department/baboon awareness
with people and first aid kit, Human animal
interaction presentation
Transportation of road Road accidents Road traffic act, FRCS 1-Light
material to site vehicles
Off-loading of Slips, trips Falling resulting in Compliance to 5S,House
material on site injuries i.e. Fractures keeping
Cutting of liners Ergonomics Muscular skeletal Medical Exams, Short breaks
from outside disorders
Prevalent occupational health risks that have been observed at the Heavy vehicles workshop-
Green area;
18
The following steps will be followed when conducting a job safety analysis:
Take a blank job safety analysis form to the job/task site.
Write the title of the job/task on the job safety analysis form.
Walk the work site to be familiar with the workplace and environmental conditions.
Write steps of performing the task in a sequential manner.
List all possible hazards and aspects involved in each step.
Identify who might be harmed. This includes people who may be sharing the workplace
with you and passers-by.
Complete the job safety analysis form using the checklist at the back including stating
actions to be taken to control the hazards/aspects and prevent injury/environmental
impact.
Make sure that mitigation measures follow the ‘Hierarchy of Controls’.
To complete the job safety analysis, the form must be signed by all team members.
The supervisor shall counter-sign the job safety analysis form
ENVIRONMENTAL RISKS
Prevalent environmental risk that has been identified on this project;
20
6. FRCS- 8. Lifting operations:
All lifting equipment shall be maintained in good condition with inspection maintenance log
books. The lifting equipment shall have a clearly marked safe working load (SWL) and it shall
not be exceeded.
a) TRAFFIC MANAGEMENT
VEHICLE OPERATION
Employees operating a company vehicle on any Mine road must always drive to the conditions
and practise due care and act in compliance to the Fatal Risk Control Standards 1. Drivers will
ensure that vehicles are fit for operation and report immediately any defects to Supervisors.
SIGNS
Signs will meet the following requirements:
Give clear direction
Be visible and not obscured
Be reviewed regularly for relevance
b) SHE OFFICER
All personnel comply with their individual SHE responsibilities as prescribed by the
company and Debswana (Client).
Communicate clear instructions to personnel under their control, to ensure correct and
safe work method
Adequate provision for dealing with emergencies at any work site
SHE file is up to date
Updating of the SHE notice board.
c) PROJECT WORKERS
Be familiar with and comply with SHE rules established for the project.
Trainings and inductions to be attended as required.
Stop, correct and report any work that, in their opinion, is unsafe.
Attend and participate in toolbox talks and other meetings.
Avoid shorts cuts.
21
Comply with all permits requirements.
Practice good housekeeping is maintained and any waste generated is segregated and
disposed on the correct containers
Wear risk based personal protective equipment (PPE) required.
Report all accidents and near misses in which they have been involved or witnessed.
Debswana Security and SHE induction All Employees As and when you
enter the mine
9. SHE INDUCTION
All our employees will undergo to all inductions before commencement of all work on
the site. The induction will be in addition to any specific security or other induction
required at the Debswana mine or other site. This will include the following:
SHE induction and Security Induction
Site specific induction including FRCS INDUCTION
• SHE stand-down: We shall comply with all SHE stand-downs which will be held within our
area of work in Debswana Jwaneng Mine.
• SHE notice boards: All information which is shared in Debswana Jwaneng Mine, we will
share it with our employees and put them on the SHE notice boards for everyone to access.
• SHE bulletins: SHE communiqué and SHE topics as communicated by the client will be
shared with employees and posted on notice board
23
PROJECT SHE MANAGEMENT SYSTEM
We shall adhere and comply with all Debswana procedures and develop their own procedures to
add to the existing ones in order to achieve zero harm. (Refer to method statement appendix 007
a) If an employees falls from height, there shall be a trained rescue team that shall assist the victim.
The incident scene shall be cleared of all other employees and area barricaded. Two members of
the rescue team accompanied with their rescue kit, shall use a 20M extension ladders to reach the
suspended employee, lower them into the scaffolding and detatch his/her lanyad from the
guardrails. Upon reaching the ground level, an appointed first aider shall administer first aid and
then the victim shall be rushed to the mine township area hospital. Trained mine rescue team shall
be notified to assist employee working at height, then incident to be logged on the Isometrix and
further investigations conducted thereafter.
c) FALLING OF LOADS:
If an employee is hit by any falling object, a rescue team will be notified, area barricaded and
victim and first aider called in to the scene to administer first aid, if the injury is severe then the
ambulance will be called and the injured sent to the hospital, Incident will be logged in Isometrix.
All workers shall cease work, a rescue team called in to the scene, area barricaded and while
investigations are ongoing of what could have caused fire, she officers on site will take roll call
registers to ensure no one is left behind.
e) ELECTRICITY: Rescue team will be called in to the scene, area barricaded and first aid
administered to the injured person, but if electrocuted person looks severe he /she will be taken
to the hospital for further treatment.
f)FALLING OF LOADS: The rescue team will be notified in the event where loads can fall
during loading and hoisting, the area will be barricaded and workers cleared from the scene,
investigations will take place to find out root causes, Incident will be logged in isometrix
g) BUMPING AGAINST STRUCTURE: The area will be barricaded, rescue team notified and
investigations will take place, incident will then be logged in to isometrix.
SIMULATION PLAN
25
SHE-09)
2 Heavy Staff Falling 6 months TBA TBA Falling from Working at Site
vehicles Connect from height height rescue heights Manager
workshop simulation team procedure
(EN-PR-
First aider
32)
C) Environmental Management
Management and Employees of Staff Connect shall comply to Debswana training on
implementation of Environmental Management plan generated from the project environmental
aspects and impacts. Manager will train his/ her subordinates on managing Environmental
Management to reduce or manage work site impacts, conserve material and realize economic
efficiency. The Debswana Procedure PR- SD-SHE-12, A waste management plan is developed
and will be followed as per the landfill times, freight and waste disposed accordingly. (Refer to
waste management plan appendix 008)
26
ii) Air Pollution
When driving it is expected that some fumes will be released to the atmosphere however, these
fumes are as a result of the job processes. The Site Manager will ensure that the cars are serviced
in order to minimize release of excessive fumes into the atmosphere.
D) Health/Hygiene Requirements
a. All work-related buildings on site will be kept clean and in a good state.
b. Any damage to buildings will be reported immediately to the line supervisor/ site
manager
c. No food will be kept in any work areas and eating in these areas is strictly forbidden
d. Storerooms and lay down areas shall be kept in a clean and orderly manner, with
particular attention to stacking of items in such a way that the stacks are stable (comply
to the Remmogo pillar 5 for Housekeeping (5S)
e. All ablutions will be kept in a clean and hygienic condition at all times.
E) Medical Examinations
All employees shall undergo pre-employment and periodic medical examinations to ensure that
they are fit for duty as per MQWMA-Reg. 91
An authorized medical service provider shall issue a medical fitness certificate. Medical
examinations shall be carried out as per the requirements of the site rules and regulations as well
as the Debswana Medical Health Surveillance Procedure.
Debswana Medical Monitoring tool is adopted and used to manage all new entrance, periodic
and exit medicals. (Refer to medical examination records on appendix009)
i) Audits
The implementation of the SHE management programme will be controlled and checked by
periodic audits, monthly reviews of individual areas of documentation and process control shall
be carried out to ensure that the procedures are being followed. The Debswana Jwaneng Mine
Audit procedure PR-SD-SHE-013 guides the process of external and internal audits using
standards checklists.
ii) Inspections
Both the contractor and the client on a daily basis in accordance to the requirement will do safety
inspections. A system audit will be done on a monthly basis as a tool to monitor and maintain our
SHE system. The client representative will be informed of the audit results, which will be audited
again by the client to show the compliance of the contractor.
The following inspections shall become part of the monitoring programme:
I. Housekeeping
II. Equipment inspections
III. Assessment of compliance to Site Rules and Regulations
IV. Legal inspections
V. Personnel protective equipment and Fatal Risk Control Standards
All incidents shall be communicated and reported as per the Debswana-Jwaneng Mine procedure
(PR-SD-SHE-03). All incidents will be investigated and corrective actions will be implemented
as per the requirements from the investigation panel.
Culture of near hit reporting shall be communicated within employees in order to close gaps that
may exist in the SHE management plan. High potential near hits shall be investigated as per the
Debswana Incident Notification and Investigation Standard.
I) Non-Conformance
Non-conformances identified are investigated as per the Debswana Non-conformity and
Corrective and Preventative Actions Procedure PR-SD-SHE-27 corrective actions adopted and
implemented to avoid recurrence.
Non-conformity can be from:
She meetings
Toolbox talk
Visible Felt Leadership and Inspections
Incidents and near hits
Inspections and observations
The identified non-conformities from the above mentioned will be investigated and closed off
28
10. PROJECT CLOSE-OUTS
On project closure, all temporary infrastructures will be dismantled and removed from site.
A clean-up will be conducted on site to remove any material that may cause any harm to the
safety and health of employees, and the environment.
After the clean-up, waste will be collected and disposed at respective disposal sites and the client
will be called for the inspection and hand over of the site. End of contract clearance from shall be
completed and together with the SHE file be returned to the Client or project owner.
SHE records will be archived as per Debswana-Jwaneng Mine Procedure PR-SD-SHE- O1 as
adopted and followed and project close out report will be written using Debswana prescribed
format.
29
REFERENCES
APPENDIXES
30