BILL NO.

3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 1A : Work Below Lowest Floor Finish ( All Provisional )

A Excavate oversite to reduce level average 200mm deep


commencing from formation level, get out, load and cart
away from site including levelling grading and ramming
bottom of excavation 83 M² 4.00 332.00

B Excavate trench for ground beam not exceeding 1.50m


deep, commencing from formation level, get out, part
return, fill in, well rammed and remainder load and cart
away from site 9 M³ 13.20 118.80

Hardcore bed as specified

C 150mm Thick under floor slab 83 M² 12.54 1,040.82

Lean concrete (Grade 15) blinding as specified

D 50mm Thick under ground beam 6 M² 13.86 83.16

E 50mm Thick under floor slab 83 M² 13.86 1,150.38

Vibrated reinforced concrete as specified :-

F Ground beam (Grade 25) 6 M³ 228.80 1,372.80

G 200mm Thick floor slab (Grade 25) 83 M² 28.60 2,373.80

H 200mm Thick ramp (Grade 25) 16 M² 28.60 457.60

Mild steel bar reinforcement as specified :-

Ground Beam

J 10mm Diameter bar as links 143 Kg 3.50 500.50

K 12mm Diameter bar as links 311 Kg 3.50 1,088.50

High tensile bar reinforcement as specified :-

Ground Beam

L 12mm Diameter bar 34 Kg 3.50 119.00

M 16mm Diameter bar 64 Kg 3.50 224.00

N 25mm Diameter bar 1,142 Kg 3.50 3,997.00

Ground Slab

P 10mm diameter bar 1,712 Kg

B3/1A/1
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Collection RM 12,858.36

Element 1A : Work Below Lowest Floor Finish (All Provisional) (Cont'd)

One layer of fabric reinforcement as described well lapped


at joints and embedded ( measured nett - no allowance for
laps ) to ground slab type

A Reference No. BRC A6 to ground slab 83 M² 12.32 1,022.56

B Reference No. BRC A6 to ramp 16 M² 12.32 197.12

Sawn formwork as specified : -

C Sides of ground beam 69 M² 45.00 3,105.00

D Edge of floor slab exceeding 100mm but not exceeding 200mm 40 M 10.00 400.00

---------------------------------

E Layer of polythene or other equal and approved damp


proof membrane, well lapped at joints and laid on lean
concrete (measured nett-no allowance made for laps) to 83 M² 2.75 228.25
ground slab

F Ditto; to ramp 16 M² 2.75 44.00

B3/1A/2
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Collection RM 4,996.93

Element 1A : Work Below Lowest Floor Finish (All Provisional) (Cont'd)

COLLECTION

B3/1A/1 12,858.36

B3/1A/2 4,996.93

B3/1A/3
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Summary RM 17,855.29

B3/1A/4
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 1B : Apron And Perimeter Drain

A Excavate oversite to reduce level average 200mm deep


commencing from formation level, get out, load and cart
away from site including levelling grading and ramming
bottom of excavation 22 M² 4.00 88.00

Hardcore as specified

B 100mm Thick under apron slab 22 M² 6.05 133.10

Lean concrete (Grade 15) blinding as specified

C 50mm Thick under apron slab 22 M² 13.86 304.92

Vibrated reinforced concrete (Grade 25) as specified

D 125mm Thick apron slab, laid to fall 22 M² 28.60 629.20


---------------------------------------

E Layer of steel fabric reinforcement reference No. A6 (M.S.


193) well lapped at joints and embedded in apron slab
(measured nett-no allowance made for laps) 22 M² 12.32 271.04

Sawn formwork as specified

F To edge of apron slab, exceeding 100mm and not


exceeding 200mm high 100 M 10.00 1,000.00

----------------------------------------------
G Layer of polythene or other equal and approved damp
proof membrane, well lapped at joints and laid on lean
concrete (measured nett-no allowance made for laps) to
apron slab 22 M² 2.75 60.50

B3/1B/5
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Collection RM 2,486.76

Element 1B : Apron And Perimeter Drain


(Cont'd)

Ramp

A Excavate oversite to reduce level average 300mm deep


commencing from formation level, get out, load and cart
away from site including levelling grading and ramming
bottom of excavation 16 M² 4.40 70.40

Hardcore as specified

B 100mm Thick under ramp slab 16 M² 6.05 96.80

Lean concrete (Grade 15) blinding as specified

C 50mm Thick under ramp slab 16 M² 13.86 221.76

Vibrated reinforced concrete (Grade 25) as specified

D 300mm Thick ramp slab, laid to fall 16 M² 68.64 1,098.24


---------------------------------------

E Layer of steel fabric reinforcement reference No. A6 (M.S.


193) well lapped at joints and embedded in apron slab
(measured nett-no allowance made for laps) 16 M² 12.32 197.12

Sawn formwork as specified

F Edges of ramp slab excceding 200mm and not exceeding


300mm high 13 M 10.00 130.00

G Extra For 15mm x 20mm fillet to form groove line 100 M 5.50 550.00

----------------------------

H Layer of polythene or other equal and approved damp


proof membrane, well lapped at joints and laid on lean
concrete (measured nett-no allowance made for laps) to
ground slab 16 M² 2.75 44.00

B3/1B/6
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Collection RM 2,408.32

Element 1B : Apron And Perimeter Drain


(Cont'd)

COLLECTION

B3/1B/1 2,486.76

B3/1B/2 2,408.32

B3/1B/7
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Summary RM 4,895.08

B3/1B/8
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 2A : Frame

Vibrated reinforced concrete (Grade 25) as specified

A Column 5 M³ 228.80 1,144.00

B Stiffener 1 M³ 228.80 228.80

C Roof beam 6 M³ 228.80 1,372.80

Mild steel bar reinforcement as specified

Column

D 10mm Diameter bar 253 Kg 3.50 885.50

Stiffener

E 8mm Diameter bar 34 Kg 3.50 119.00

Roof beam

F 10mm Diameter bar 201 Kg 3.50 703.50

High tensile bar reinforcement as specified

Column

G 16mm Diameter bar 345 Kg 3.50 1,207.50

Stiffener

H 16mm Diameter bar 167 Kg 3.50 584.50

Roof beam

J 12mm Diameter bar 99 Kg 3.50 346.50

K 16mm Diameter bar 119 Kg 3.50 416.50

L 25mm Diameter bar 373 Kg 3.50 1,305.50

Sawn formwork as specified

M Sides of column 63 M² 40.00 2,520.00

N Sides of stiffener 16 M² 40.00 640.00

P Sides and soffit of roof beam 51 M² 40.00 2,040.00

B3/2A/9
To Summary RM 13,514.10

B3/2A/10
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 2B : Roof

Vibrated reinforced concrete (Grade 25) as specified

A 150mm Thick parapet walls 25 M

B 150mm Thick Overall size 230mm x 25mm gutter 33 M 60.00 1,980.00

C 150mm Thick roof slab, laid to fall 126 M² 26.62 3,354.12

Mild steel bar reinforcement as specified

D 10mm Diameter bar to gutter 108 Kg 3.50 378.00

High tensile bar reinforcement as specified

F 10mm Diameter bar to parapet wall 621 Kg 3.50 2,173.50

G 10mm Diameter bar to roof slab 2,664 Kg 3.50 9,324.00

H 10mm Diameter bar to gutter 193 Kg 3.50 675.50

Sawn formwork as specified

J Sides and soffit parapet wall 58 M²

K Sides and soffit of roof slab 84 M² 40.00 3,360.00

L Sides and soffit of gutter 107 M² 40.00 4,280.00


-------------------------------------

M Layer of steel fabric reinforcement reference No. A10 (M.S.


193) well lapped at joints and embedded in roof slab
(measured nett-no allowance made for laps) 126 M²

N Supply and lay 'Flinkote' waterproofing membrane system


with and including 50mm thick concrete topping and
Durafiber at 1.5 lb/cu. td. of concrete and 45 degree angle
mortar coving, all in accordance to Engineer's instructions
and manufacturer's recommendation, laid to fall to roof slab 126 M² 33.00 4,158.00

P Ditto to gutter 8 M² 33.00 264.00

Unplasticised P.V.C. rainwater downpipe with solvent


cement joints in the running lengths elbows, bend,
diminishing piece, plugs and the like

Q 75mm Diameter pipe, fixed to brickwall 6 M 27.50 165.00

R 75mm Diameter rainwater outlet 4 NO 16.50 66.00

S Extra For bend 8 NO 16.50 132.00

T Extra For shoe 4 NO 16.50 66.00

B3/2B/11
To Summary RM 30,376.12

B3/2B/12
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 2C : External Wall

Brickwork in common clay bricks in cement and sand (1:3)


mortar with an approved plasticiser reinforced with and
including `EXMET' or approved equivalent expanded fabric
reinforcement at every fourth course include bonding tie as
described :-
A 150mm Thick brickwall 98 M² 59.40 5,821.20

B 300mm Thick brickwall 50 M² 59.40 2,970.00

Damp proof course as described (measured nett-no


allowance made for laps) laid on brickwall

C 150mm wide 16 M 1.65 26.40

D 300mm wide 16 M 1.65 26.40


---------------------------
Lintol precast reinforced concrete (Grade 25) lintol,
reinforced with and including 4 Nos. 10mm Diameter high
tensile bar reinforcement and 6mm diameter mild steel
stirrups including all moulds and finished fair on all exposed
surfaces as described:-

E 150mm x 150mm 5 M

F 150mm x 230mm 13 M

G 300mm x 230mm 11 M

B3/2C/13
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Summary RM 8,844.00

B3/2C/14
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 2D : External Door

External Door

Supply and install the following FRP composite doors with


and including anti vermin wire netting type SWG 23 mesh
10 fixed inside the doors with 100mm x 50mm x 0.5mm
mild steel hot dip composite frames, and including
ironmongery and other accessories for the proper
installation of the works all as per manufacturer's
instruction and recommendation

A FRP composite door overall size 1320mm x 2816mm high


consisting of two equally sized leaves 2 NO 2,200.00 4,400.00

B Ditto overall size 2426mm x 2816mm high ditto 2 NO 2,750.00 5,500.00

Supply and install the following FRP composite windows


with and including anti vermin wire netting type SWG 23
mesh 10 fixed inside the doors with 100mm x 50mm x
0.5mm mild steel hot dip composite frames, and including
ironmongery and other accessories for the proper
installation of the works all as per manufacturer's
instruction and recommendation

C FRP composite door overall size 1225mm x 600mm high


consisting of two equally sized leaves 1 NO

D Ditto overall size 2400mm x 600mm high ditto 7 NO

B3/2D/15
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

To Summary RM 9,900.00

B3/2D/16
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 2E : Internal Wall

Brickwork in common clay bricks in cement and sand (1:3)


mortar with an approved plasticiser reinforced with and
including `EXMET' or approved equivalent expanded fabric
reinforcement at every fourth course as described :-

A 150mm Thick brickwall 58 M² 59.40 3,445.20

B 300mm Thick brickwall 29 M² 59.40 1,722.60

horizontal damp proof course as described (measured nett-


no allowance made for laps) laid on brickwall

C 150mm wide 12 M 1.65 19.80

B 300mm wide 6 M 1.65 9.90

B3/2E/17
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount


To Summary RM 5,197.50

B3/2E/18
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 3A : Wall Finishes

The quantities in these Bills for different types of


colours and finishes are measured nett from the
Drawings in accordance with the Standard Method
of Measurement. The Contractor is to conform to the
specified colours as instructed by the S.O.

INTERNAL WALL FINISHES

Cement and sand (1:6) mixed with an approved plasticiser


internally as described:-

A 20mm Thick plaster to wall and column 368 M² 16.50 6,072.00

Prepare and apply three coats of distemper and two coats


of 'ICI' or approved equivalent paint as described internally
on:-

B Plastered wall and column 368 M² 11.00 4,048.00

EXTERNAL WALL FINISHES

Cement and sand (1:6) mixed with an approved plasticiser


internally as described:-

C 20mm Thick plaster to wall and column 222 M² 16.50 3,663.00

Prepare and apply three coats of snowcem, one coat of


driwal and two coats of 'ICI' or approved equivalent paint
as described externally on:-

D Plastered wall and column 222 M² 20.00 4,440.00


----------------------------------------------

E Painting of Tenaga Nasional Berhad's logo as per drawing


no. PAF174/M&E/PE-010 LS 500.00

B3/3A/19
To Summary RM 18,723.00

B3/3A/20
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 3B : Floor Finishes

INTERNAL FLOOR FINISHES

Cement and sand (1:3) screed trowelled hard and smooth


as described:-

A 25mm Thick paving to floor 73 M² 13.20 963.60

EXTERNAL FLOOR FINISHES

Cement and sand (1:3) screed trowelled hard and smooth


as described:-

B 25mm Thick to floor laid to fall 22 M² 13.20 290.40

B3/3B/21
To Summary RM 1,254.00

B3/3B/22
BILL NO. 3 TNB SUB STATION

Item Description Qty Unit Rate Amount

Element 3A : Ceiling Finishes

INTERNAL CEILING FINISHES

Cement based skim coat plaster system, trowelled smooth


internally all accordance with manufacturer's specifications
and instructions :-

A 6mm Thick to soffit of roof slab 83 M² 6.50 539.50

Prepare and apply three coats of distemper and two coats


of 'ICI' or approved equivalent paint as described internally
on:-

B Plastered of roof slab 83 M² 11.00 913.00

EXTERNAL CEILING FINISHES

Cement based skim coat plaster system, trowelled smooth


internally all accordance with manufacturer's specifications
and instructions :-

C 6mm Thick to soffit of gutter 22 M² 6.50 143.00

Prepare and apply three coats of snowcem, one coat of


driwal and two coats of 'ICI' or approved equivalent paint
as described externally on:-

D Plastered gutter 22 M² 11.00 242.00

B3/3C/23
To Summary RM 1,837.50

B3/3C/24
BILL NO. 3 Summary TNB SUB STATION

Item Description Qty Unit Rate Amount

Summary

1A Work Below Lowest Floor Finish B3/1A/4 17,855.29

1B Apron And Perimeter Drain B3/1B/3 4,895.08

2A Frame B3/2A/1 13,514.10

2B Roof B3/2B/1 30,376.12

2C External Wall B3/2C/1 8,844.00

2D Window And External Door B3/2D/1 9,900.00

2E Internal Wall B3/2A/1 5,197.50

3A Wall Finishes B3/3A/1 18,723.00

3B Floor Finishes B3/3B/1 1,254.00

3C Ceiling Finishes B3/3C/1 1,837.50

B3/25
Summary
TOTAL CARRIED TO FINAL SUMMARY RM 112,396.59