Ground Beam
Ground Beam
Ground Slab
B3/1A/1
BILL NO. 3 TNB SUB STATION
To Collection RM 12,858.36
D Edge of floor slab exceeding 100mm but not exceeding 200mm 40 M 10.00 400.00
---------------------------------
B3/1A/2
BILL NO. 3 TNB SUB STATION
To Collection RM 4,996.93
COLLECTION
B3/1A/1 12,858.36
B3/1A/2 4,996.93
B3/1A/3
BILL NO. 3 TNB SUB STATION
To Summary RM 17,855.29
B3/1A/4
BILL NO. 3 TNB SUB STATION
Hardcore as specified
----------------------------------------------
G Layer of polythene or other equal and approved damp
proof membrane, well lapped at joints and laid on lean
concrete (measured nett-no allowance made for laps) to
apron slab 22 M² 2.75 60.50
B3/1B/5
BILL NO. 3 TNB SUB STATION
To Collection RM 2,486.76
Ramp
Hardcore as specified
G Extra For 15mm x 20mm fillet to form groove line 100 M 5.50 550.00
----------------------------
B3/1B/6
BILL NO. 3 TNB SUB STATION
To Collection RM 2,408.32
COLLECTION
B3/1B/1 2,486.76
B3/1B/2 2,408.32
B3/1B/7
BILL NO. 3 TNB SUB STATION
To Summary RM 4,895.08
B3/1B/8
BILL NO. 3 TNB SUB STATION
Element 2A : Frame
Column
Stiffener
Roof beam
Column
Stiffener
Roof beam
B3/2A/9
To Summary RM 13,514.10
B3/2A/10
BILL NO. 3 TNB SUB STATION
Element 2B : Roof
B3/2B/11
To Summary RM 30,376.12
B3/2B/12
BILL NO. 3 TNB SUB STATION
E 150mm x 150mm 5 M
F 150mm x 230mm 13 M
G 300mm x 230mm 11 M
B3/2C/13
BILL NO. 3 TNB SUB STATION
To Summary RM 8,844.00
B3/2C/14
BILL NO. 3 TNB SUB STATION
External Door
B3/2D/15
BILL NO. 3 TNB SUB STATION
To Summary RM 9,900.00
B3/2D/16
BILL NO. 3 TNB SUB STATION
B3/2E/17
BILL NO. 3 TNB SUB STATION
B3/2E/18
BILL NO. 3 TNB SUB STATION
B3/3A/19
To Summary RM 18,723.00
B3/3A/20
BILL NO. 3 TNB SUB STATION
B3/3B/21
To Summary RM 1,254.00
B3/3B/22
BILL NO. 3 TNB SUB STATION
B3/3C/23
To Summary RM 1,837.50
B3/3C/24
BILL NO. 3 Summary TNB SUB STATION
Summary
B3/25
Summary
TOTAL CARRIED TO FINAL SUMMARY RM 112,396.59
B3/26