Professional Documents
Culture Documents
1 Introduction.................................................... 2
2 Conflicts with Mandatory Standards.............. 2
3 References.................................................... 2
4 General.......................................................... 2
5 Pipeline Wall Thickness for
the Internal Design Pressure.................. 3
6 Corrosion Allowance and Mill Tolerance........ 5
7 Traffic and Soil Loads over Buried Pipeline... 5
8 Typical Mistakes in
Wall Thickness Selection....................... 6
1 Introduction
In the event of a conflict between this Best Practice and other Mandatory Saudi Aramco
Engineering Requirement, the Mandatory Saudi Aramco Engineering Requirement shall
govern.
3 References
This Best Practice is based on the latest edition of the references below, unless
otherwise noted.
4 General
4.1 The pipe wall thickness is calculated by using the equation for internal pressure
thickness (Barlows Equation).
Page 2 of 6
Document Responsibility: Piping Standards Committee SABP-L-001
Issue Date: 28 January 2007 Wall Thickness Selection
Next Planned Update: 28 January 2012 of Transportation Pipelines
4.2 The allowances, if required, are added to the calcualted wall thickness for
internal pressure.
4.3 The wall thickness calculated based on internal pressure must be checked to be
adequate for external loads as well as structual rigidity.
4.4 The wall thickness selected shall be either the next higher standard size of
ANSI/API standard wall thicknesses or the exact calculated thickness.
Commentary Note:
Selection of the exact calculated wall thickness will reduce the steel tonnage and
result in cost savings if the quantity of pipe ordered is significant (large diameter
long pipelines). The project engineer shall evaluate the cost of both options as
early as possible in the design stage and before material procurement.
5.1 Saudi Aramco Standard calls for applying the design factor formula of ASME
B31.8 for all transportation piping systems regardless of the nature of the
service. The differences will be in the design factors and de-rating factors as
discussed below.
PD
t=
2SETF (Eq. 1)
where:
t = Internal pressure design wall thickness, inches.
P = Design pressure, psig.
D = Outside diameter of pipe, inches.
S = Specified Minimum Yield Strength (SMYS), psi.
E = Longitudinal-joint quality factor.
T = Temperature derating factor.
F = Design factor.
5.2 The design pressure [P] should be selected to match process needs and will
normally be equal to the Maximum Allowable Operating Pressure (MAOP).
Selecting a design pressure higher than the required operating pressure increases
the required pipe wall thickness, and thus, increases the capital cost
considerably.
Page 3 of 6
Document Responsibility: Piping Standards Committee SABP-L-001
Issue Date: 28 January 2007 Wall Thickness Selection
Next Planned Update: 28 January 2012 of Transportation Pipelines
install surge relief systems, then increasing the wall thickness of the line
to withstand these pressure surges is required.
The ASME B31.4, paragraph 402.2.4 states that the MATP, maximum
allowable transient pressure due to the pressure surges, shall not exceed
110% of the design pressure (MAOP) in the line.
5.3 The parameter [S] is the Specified Minimum Yield Strength (SMYS) of the
material. The ASME codes B31.4 & B31.8 specify the acceptable materials
together with their SMYS. Using high strength steel decreases the required pipe
wall thickness and steel tonnage, and thus the overall project cost. However,
economical and technical evaluation must be conducted before making the final
wall thickness selection.
Commentary Note:
Higher grade steels (X 70 and higher) are not suitable for sour services because
hardness values in the field welds may exceed those permitted by NACE to avoid
sulfide stress cracking.
5.3.1 The lower thickness resulting from using higher strenght steel must be
sufficient to withstand other failure criteria like buckling. Saudi Aramco
Standards require that the minimum thickness be greater than
diameter/135.
5.3.2 Higher strength steel requires special welding procedures which are
usually more expensive and technically more difficult compared to lower
grade.
5.4 The temperature derating factor [T] accounts for the fact that the yield strength
of materials is reduced as the metal temperature increases. This factor is only
applicable for pipelines designed to ASME B31.8 with design temperature more
than 250ºF.
5.5 The design factor [F], sometimes called DF, is a safety factor that accounts for
the relative hazard created by the presence of the pipeline to the surrounding
population, environment, and facilities. This design factor is selected based on
area classification shown in Table 1 (refer to SAES-B-064 for more details).
Page 4 of 6
Document Responsibility: Piping Standards Committee SABP-L-001
Issue Date: 28 January 2007 Wall Thickness Selection
Next Planned Update: 28 January 2012 of Transportation Pipelines
6.1 Additional pipe wall thickness to allow for metal loss due to internal or external
corrosion is not normally applicable for cross country pipelines.
Commentary note:
7.1 The required thickness of the buried sections of pipelines should be checked for
soil and traffic loads, in addition to the design pressure. These loads cause a
circumferential bending stress in the pipe.
7.2 If analysis shows that pipeline thickness must be increased under road crossing,
the wall thickness of the pipe under the road crossing shall be increased NOT
the whole pipeline.
7.3 Casing shall be used for rail road crossing, as required by the Saudi Arabian
Government, instead of increasing the pipe thickness.
7.4 Installation of concrete slab over the pipe to redistribute the stresses is an
alternative to increasing the pipe thickness, if needed, under road crossing.
Page 5 of 6
Document Responsibility: Piping Standards Committee SABP-L-001
Issue Date: 28 January 2007 Wall Thickness Selection
Next Planned Update: 28 January 2012 of Transportation Pipelines
Commentary Note:
Even though the calculation for wall thickness is relatively simple and straight forward,
unintentional mistakes and/or inappropriate assumptions cost the company more capital
investment than necessary. These typical mistakes are summarized but not limited to
the following:
8.1 Specifying a design pressure that is higher than what is required to fulfil the
operational requirement.
8.2 Selecting the higher wall thickness to match the flange pressure rating. The wall
thickness of the pipeline might be less than of the mating flange.
8.3 Setting the design pressure based on a pre-selected or existing flange rating that
exceeds the MAOP required for operation.
8.6 Adding the manufacturer mill tolerance to the caculated wall thickness.
8.8 Selecting exact calculated wall thickness rather than standard ANSI/API pipe
thickness to reduce the cost of steel tonnage, but on the expense of extra cost of
special manufacturing.
8.9 Selecting higher grade of pipe material to reduce the cost of steel tonnage, but
on the expense of handling and installation cost.
8.10 Overestimating of the RER/PDI, and thus, increasing the area classification.
Revision Summary
28 January 2007 New Saudi Aramco Best Practice.
Page 6 of 6