Critical Path Method (CPM) PDF
Critical Path Method (CPM) PDF
Activity/Task A B C D E F G H
Predecessor - A A B C C D,E F,G
Duration(days) 3 4 2 5 1 2 4 3
Solution:
A B D G H ⇒ 3+4+5+4+3 =19
A C E G H ⇒ 3+2+1+4+3 =13
A C F H ⇒ 3+2+2+3 = 10
Maximum value indicates is the project duration.
Project duration = 19 (ans)
Critical path: A B D G H
2. Calculate the total float (total slack) and free float (free slack) for the following
activity of a project.
Activity/Task A B C D E F
Predecessor - A A B C D,E
Duration(days) 3 4 2 5 1 2
Solution: