Project : Tangguh Expansion Project

Pipe Sleeper Infrastructure Area


Middle Road to Camp
SL-1,SL-2, SL-3

QUANTITY TAKEOFF - SUMMARY

No Unit QTY Remarks


Coating for Embedded Plate
a Prepare m2 - SA 2 ½ (sandblasting)

Zinc Rich Epoxy / Inorganic


b Primer ltr -
Zinc Silicate - 1 x 60 mikron

Mio 2 pack epoxy – 1 x 115


c Midcoat ltr -
mikron

Acylic Modified 2 pack


polyurethane – 1 x 50
mikron
d Finish ltr - Total thickness DFT 225
mickron

Application for Primer &


e Thinner 08450 ltr 1.00
Midcoat

f Thinner 08080 ltr 1.00 Application for Finishcoat

Note:
*Reff. Drawing No : TEP-900-DWG-CV-BP4-0117_Rev.B01
TEP-900-DWG-CV-BP4-0115_Rev.B01
TEP-900-DWG-CV-BP4-0115-001/017_Rev.01
TEP-900-STD-CV-BP4-002_Rev.C02
LEAN CONCRETE F'c = 15 Mpa
Footing Dimension (m)
Total Sleeper
No Area Name of Building Type of Foundation QTY (m3)
Foundation (set)
Length Width High

A INFRA

1 INFRA Sleeper SL 1 1300x1000x50 100 1.5 1.2 0.05 4.67


2 INFRA Sleeper SL 2 1300x1300x50 20 1.5 1.5 0.05 1.18
3 INFRA Sleeper SL 3 1300x1500x50 360 1.5 1.7 0.05 0.08
Total Lean Concrete 6.00
*

CONCRETE F'c = 21 Mpa


Footing Dimension (m) Pedestal Dimension (m)
No Area Name of Building Type of Footing Total Footing (set) QTY (m3) Type of Pedestal Pedestal QTY (m3)
(Set)
Length Width High Length Width High

A INFRA

1 INFRA Sleeper SL 1 1300x1000x300 100 1.3 1 0.3 56.09 300x1000x1200 100 1 0.3 1.2 9.17
2 INFRA Sleeper SL 2 1300x1300x300 20 1.3 1.3 0.3 14.21 300x1300x1200 20 1.3 0.3 1.2 2.07
3 INFRA Sleeper SL 3 1300x1500x300 360 1.3 1.5 0.3 4.22 300x1500x1200 360 1.5 0.3 1.2 3.99
75.00 16.00
Total Concrete 91.00

FORMWORK
Footing Dimension (m) Pedestal Dimension (m)
Pedestal
No Area Name of Building Type of Footing Total Footing (set) QTY (m2) Type of Pedestal QTY (m2)
(Set)
Length Width High Length Width High

A INFRA

1 INFRA Sleeper SL 1 Footing 0 0 0 0 - PD 1 (850x650) 0 0.65 0.85 0.75 9.00


2 INFRA Sleeper SL 2 Footing 0 0 0 0 - Pedestal 0 0 0 0 -
3 INFRA Sleeper SL 3 Footing 0 0 0 0 - Pedestal 0 0 0 0 -
- 9.00
Total Formwork 9.00

Steel Plate 16mm THK SS400 @2400x1200


Footing Dimension (m)
No Area Name of Building Type of Plate Total Plate (set) QTY (m2) QTY (Kg)
Length Width High

A INFRA

1 INFRA Sleeper SL 1 Plate 900x200x16 0 0.9 0.2 0.016 18.00 2,260.80


2 INFRA Sleeper SL 2 Plate 1200x200x16 0 1.2 0.2 0.016 4.80 602.88
3 INFRA Sleeper SL 3 Plate 1400x200x16 0 1.4 0.2 0.016 100.80 12,660.48
Total Plate Embedded 135.96 15,524.16

Coating for Embedded Plate


Footing Dimension (m)
No Area Name of Building Type of Plate Total Plate (set) QTY (m2) Remark
Length Width side

A INFRA

1 INFRA Sleeper SL 1 Plate 900x200x16 0 0.95 0.25 1 -


2 INFRA Sleeper SL 2 Plate 1200x200x16 0 1.25 0.25 1 -
3 INFRA Sleeper SL 3 Plate 1400x200x16 0 1.45 0.25 1 -
Total Coating Plate Embedded -

Chamfer 25x25
Champer Dimension (m)
Total Chamfer
No Area Name of Building Type of Plate QTY (m) Remark
(set)
Length Width Side
A INFRA
1 INFRA Sleeper SL 1 SL 1 300x1000 2 0.3 1 2 5.20 2.00
2 INFRA Sleeper SL 2 SL 2 300x1300 2 0.3 1.3 2 6.40 2.00
3 INFRA Sleeper SL 3 SL 3 300x1500 8 0.3 1.5 2 28.80 8.00
Total Chamfer 25x25 40.40 12.00

Polyethylene Sheet
Dimension (m)
No Area Name of Building Type of Sleeper Total (set) QTY (m) Remark
Length Width Side

A INFRA

1 INFRA Sleeper SL 1 1300x1000x300 100.00 2.30 2.00 2.00 920.00


2 INFRA Sleeper SL 2 1300x1300x300 20.00 2.30 2.30 2.00 211.60
3 INFRA Sleeper SL 3 1300x1500x300 360.00 2.30 2.50 2.00 4,140.00
Total Polyethylene Sheet 6,063.00

Concrete Coating
Footing Dimension (m) Pedestal Dimension (m)
Pedestal
No Area Name of Building Type of Footing Total Footing (set) QTY (m2) Type of Pedestal QTY (m2)
(Set)
Length Width High Length Width High

A INFRA

A INFRA Sleeper SL 1 1300x1000x300 100 1.3 1 0.3 238.00 300x1000x1200 100 1 0.3 1.2 312.00
1 INFRA Sleeper SL 2 1300x1300x300 20 1.3 1.3 0.3 57.20 300x1300x1200 20 1.3 0.3 1.2 76.80
2 INFRA Sleeper SL 3 1300x1500x300 360 1.3 1.5 0.3 1,144.80 300x1500x1200 360 1.5 0.3 1.2 1,555.20
1,440.00 1,944.00
Total Concrete Coating 3,384.00
SLEEPER Identification
Footing Dimension (m) Pedestal Dimension (m)
Total
No Area Name of Building Type of Footing QTY (m2) Type of Pedestal Pedestal (Set) QTY (m2)
Footing
Length Width High Length Width High

A INFRA

1 INFRA PIPE BRIDGE 017-BRG-31002 FO Footing - - - - - PD 1 (850x650) - 0.65 0.85 0.75 9.00

2 INFRA PIPE BRIDGE 017-BRG-31002 FO Footing - - - - - Pedestal - - - - -

3 INFRA OPERATION PLATFORM 017-PLF- Footing - - - - - Pedestal - - - - -

- 9.00
Total Formwork 9.00

Total Footing Dimension (m) QTY (m2) Type of Panel Dimension (mm) Set
No Area Name of Building Type of Footing Footing Total QTY
Length Width High Length High pcs Side

A INFRA

1 INFRA PIPE BRIDGE 017-BRG-31002 FO Footing 12.00 - - - - Euro Panel 300x1200 1,000.00 300.00 1.00 2.00 24.00
Euro Panel 300x1500 1,300.00 300.00 1.00 2.00 24.00
PD 1 (850x650) 12.00 0.65 0.85 0.75 9.00 Euro Panel 300x1200 300.00 1,200.00 1.00 2.00 24.00
500x1200 1,000.00 1,200.00 2.00 2.00 48.00
O/C Angle 65x65x1200 65.00 1,200.00 1.00 4.00 48.00
2 INFRA PIPE BRIDGE 017-BRG-31002 FO Footing 6.00 - - - - Euro Panel 300x1500 1,300.00 300.00 1.00 4.00 24.00
Pedestal 6.00 - - - - Euro Panel 300x1200 300.00 1,200.00 1.00 2.00 12.00
600x1500 1,300.00 1,200.00 2.00 2.00 24.00
O/C Angle 65x65x1200 65.00 1,200.00 1.00 2.00 12.00
3 INFRA OPERATION PLATFORM 017-PLF- Footing 22.00 - - - - Euro Panel 300x1500 1,300.00 300.00 1.00 2.00 44.00
Euro Panel 300x1500 1,500.00 300.00 1.00 2.00 44.00
Pedestal 22.00 - - - - Euro Panel 300x1200 300.00 1,200.00 1.00 2.00 44.00
Euro Panel 600x1500 1,500.00 1,200.00 1.00 2.00 44.00
O/C Angle 65x65x1200 65.00 1,200.00 1.00 4.00 88.00
Euro Panel 300x1200 104
Euro Panel 300x1500 136
Total Formwork Euro Panel 500x1200 48
Euro Panel 600x1500 68
O/C Angle 65x65x1200 148
SLEEPER Identification
Footing Dimension (m) Pedestal Dimension (m)
No Area Name of Building Type of Footing Total QTY (m2) Type of Pedestal Pedestal (Set) QTY (m2)
Footing
Length Width High Length Width High

A INFRA

1 INFRA PIPE BRIDGE 017-BRG-31002 Footing - - - - - PD 1 (850x650) - 0.65 0.85 0.75 9.00

2 INFRA PIPE BRIDGE 017-BRG-31002 Footing - - - - - Pedestal - - - - -

3 INFRA OPERATION PLATFORM 017-PL Footing - - - - - Pedestal - - - - -

- 9.00
Total Formwork 9.00
Footing Dimension (m) Dimension (m) Set Weigth
No Area Name of Building Type of Footing Set QTY (m2) Type of Panel Total QTY Remark
(Kg)
Length Width High Length High THK pcs Side

A INFRA

1 INFRA OPERATION PLATFORM 017-PLFooting 8.00 - - - 1.68 Steel Plate THK 2 1.56 0.30 0.002 1.00 1.00 58.93 3.80 m2
Frame Horz.Support L 30x30x3 1.56 2.00 1.00 33.78 25.10 m
Frame Vert.Support L 30x30x3 0.30 5.00 1.00 16.20 12.00 m
Stopper L 30x30x3 0.32 2.00 1.00 6.91 5.20 m Total Length
Bracing L 30x30x3 0.39 2.00 1.00 8.34 6.20 m 48.50
Total 8 Set 124.16 48.50
Footing 8.00 - - - 1.68 Steel Plate THK 2 1.30 0.30 0.002 1.00 1.00 48.98 3.20 m2
Frame Horz.Support L 30x30x3 1.30 2.00 1.00 28.08 20.80 m
Frame Vert.Support L 30x30x3 0.30 5.00 1.00 16.20 12.00 m
Stopper L 30x30x3 0.32 2.00 1.00 6.91 5.20 m Total Length
Bracing L 30x30x3 0.40 2.00 1.00 8.58 6.40 m 44.40
Total 8 Set 108.75 44.40
Pedestal 8.00 - - - 4.32 Steel Plate THK 2 1.56 1.18 0.002 1.00 1.00 232.58 14.90 m2
1.56 0.20 0.002 1.00 1.00 39.19 2.50 m2
Frame Horz.Support L 30x30x3 1.56 6.00 1.00 101.35 75.10 m
Frame Vert.Support L 30x30x3 1.18 5.00 1.00 63.94 47.40 m
Bracing L 30x30x3 0.36 2.00 1.00 7.84 5.90 m Total Length
Bracing L 30x30x3 1.00 2.00 1.00 21.60 16.00 m 144.40
Total 8 Set 444.89 144.40
Pedestal 8.00 - - - 4.32 Steel Plate THK 2 0.30 1.18 0.002 1.00 1.00 44.46 2.90 m2
Frame Horz.Support L 30x30x3 0.30 3.00 1.00 9.72 7.20 m Total Length
Frame Vert.Support L 30x30x3 1.18 2.00 1.00 25.57 19.00 m 26.20
Total 8 Set 79.76 26.20 263.50
Footing Dimension (m) Dimension (m) Set Weigth
No Area Name of Building Type of Footing Set QTY (m2) Type of Panel Total QTY Remark
(Kg)
Length Width High Length High THK pcs Side

A INFRA

1 INFRA PIPE BRIDGE 017-BRG-31002 Footing 2.00 1.30 1.30 0.30 1.56 Steel Plate THK 2 1.36 0.30 0.002 1.00 2.00 25.70 1.70 m2
Frame Horz.Support L 30x30x3 1.36 2.00 2.00 14.73 11.00 m
Frame Vert.Support L 30x30x3 0.30 5.00 2.00 8.10 6.00 m
Stopper L 30x30x3 0.32 2.00 2.00 3.46 2.60 m Total Length
Bracing L 30x30x3 0.39 2.00 2.00 4.17 3.10 m 22.70
Total 2 Set 56.15 22.70
Footing 2.00 1.30 1.30 0.30 1.56 Steel Plate THK 2 1.30 0.30 0.002 1.00 2.00 24.49 1.60 m2
Frame Horz.Support L 30x30x3 1.30 2.00 2.00 14.04 10.40 m
Frame Vert.Support L 30x30x3 0.30 5.00 2.00 8.10 6.00 m
Stopper L 30x30x3 0.32 2.00 2.00 3.46 2.60 m Total Length
Bracing L 30x30x3 0.40 2.00 2.00 4.29 3.20 m 22.20
Total 2 Set 54.38 22.20
Pedestal 2.00 1.30 0.30 1.20 3.84 Steel Plate THK 2 1.36 1.18 0.002 1.00 2.00 101.42 6.50 m2
1.36 0.20 0.002 1.00 2.00 17.13 1.10 m2
Frame Horz.Support L 30x30x3 1.30 6.00 2.00 42.12 31.20 m
Frame Vert.Support L 30x30x3 1.18 5.00 2.00 31.97 23.70 m
Bracing L 30x30x3 0.36 2.00 2.00 3.92 3.00 m Total Length
Bracing L 30x30x3 1.00 2.00 2.00 10.80 8.00 m 65.90
Total 2 Set 196.56 65.90
Pedestal 2.00 1.30 - - 3.84 Steel Plate THK 2 0.30 1.18 0.002 1.00 2.00 22.23 1.50 m2
Frame Horz.Support L 30x30x3 0.30 3.00 2.00 4.86 3.60 m Total Length
Frame Vert.Support L 30x30x3 1.18 2.00 2.00 12.79 9.50 m 13.10
Total 2 Set 39.88 13.10 123.90
Footing Dimension (m) Dimension (m) Set Weigth
No Area Name of Building Type of Footing Set QTY (m2) Type of Panel Total QTY Remark
(Kg)
Length Width High Length High THK pcs Side

A INFRA

1 INFRA PIPE BRIDGE 017-BRG-31002 Footing 2.00 1.00 1.30 0.30 1.38 Steel Plate THK 2 1.06 0.30 0.002 1.00 2.00 20.05 1.30 m2
Frame Horz.Support L 30x30x3 1.06 2.00 2.00 11.45 8.50 m
Frame Vert.Support L 30x30x3 0.30 5.00 2.00 8.10 6.00 m
Stopper L 30x30x3 0.32 2.00 2.00 3.46 2.60 m Total Length
Bracing L 30x30x3 0.39 2.00 2.00 4.17 3.10 m 20.20
Total 2 Set 47.22 20.20
Footing 2.00 1.00 1.30 0.30 1.38 Steel Plate THK 2 1.30 0.30 0.002 1.00 2.00 24.49 1.60 m2
Frame Horz.Support L 30x30x3 1.30 2.00 2.00 14.04 10.40 m
Frame Vert.Support L 30x30x3 0.30 5.00 2.00 8.10 6.00 m
Stopper L 30x30x3 0.32 2.00 2.00 3.46 2.60 m Total Length
Bracing L 30x30x3 0.40 2.00 2.00 4.29 3.20 m 22.20
Total 2 Set 54.38 22.20
PD 1 (850x650) 2.00 1.00 0.30 1.20 3.12 Steel Plate THK 2 1.06 1.18 0.002 1.00 2.00 79.11 5.10 m2
1.06 0.20 0.002 1.00 2.00 13.36 0.90 m2
Frame Horz.Support L 30x30x3 1.00 6.00 2.00 32.40 24.00 m
Frame Vert.Support L 30x30x3 1.18 5.00 2.00 31.97 23.70 m
Bracing L 30x30x3 0.36 2.00 2.00 3.92 3.00 m Total Length
Bracing L 30x30x3 1.00 2.00 2.00 10.80 8.00 m 58.70
Total 2 Set 160.77 58.70
PD 1 (850x650) 2.00 1.00 - - 3.12 Steel Plate THK 2 0.30 1.18 0.002 1.00 2.00 22.23 1.50 m2
Frame Horz.Support L 30x30x3 0.30 3.00 2.00 4.86 3.60 m Total Length
Frame Vert.Support L 30x30x3 1.18 2.00 2.00 12.79 9.50 m 13.10
Total 2 Set 39.88 13.10 114.20
QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : Infrastructure
Name of Building : PIPE BRIDGE 017-BRG-31002 FOUNDATION PLAN SHEET-01
Drawing No : TEP-017-DWG-CV-BP4-0007
Work Description : Foundation

Length Width High Circumfere QTY


Nos nce Remarks
No Description/ BQ Iteams (m) (m) (m) (m) (m2)

a b c d e=2x(b+c) f=axdxe
Foundation
TEP-017-DWG-CV-BP4-0007
A Footing
1 F1 (5700 x 8200) 1.00 5.70 8.20 0.60 27.80 16.68
B Pedestal
1 PD 1 (850x650) 4.00 0.65 0.85 0.75 3.00 9.00

Total of Foundation 25.68 m2


QUANTITY TAKEOFF - CALCULATION

Project : Tangguh Expansion Project


Area : Infrastructure
Name of Building : PIPE BRIDGE 017-BRG-31002 FOUNDATION PLAN SHEET-01
Drawing No : TEP-017-DWG-CV-BP4-0008
Work Description : Foundation

Length Width High Circumfere QTY


Nos (m) (m) (m) nce (m2) Remarks
No Description/ BQ Iteams (m)
a b c d e=2x(b+c) f=axdxe
Foundation
TEP-017-DWG-CV-BP4-0008
A Footing
1 F1 (3200 x 7400) 1.00 3.20 7.40 0.60 21.20 12.72
2 F2 (5000 x 7400) 2.00 5.00 7.40 0.60 24.80 29.76
B Pedestal
1 PD 1 (850x650) 2.00 0.90 0.90 1.28 3.60 9.18
2 PD 2 (850x650) 8.00 0.60 0.75 0.75 2.68 16.05
-

TIE BEAM 400X400 (4.00) 0.40 0.40 (0.64)

Total of Foundation 67.07 m2


QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : Infrastructure
Name of Building : OPERATION PLATFORM 017-PLF-31010/31011A/31011B FOUNDATION PLAN SHEET-02
Drawing No : TEP-017-DWG-CV-BP4-0010
Work Description : Foundation

Length Width High Circumfere QTY


Nos nce Remarks
No Description/ BQ Iteams (m) (m) (m) (m) (m2)

a b c d e=2x(b+c) f=axdxe
Foundation
TEP-017-DWG-CV-BP4-0010
A Footing
1 F1 (3700 x 1900) 1.00 3.70 1.90 0.60 11.20 6.72
2 F2 (7200 x 8200) 1.00 8.20 7.20 0.60 30.80 18.48
B Pedestal
1 PD 1 (1050x800) 2.00 1.05 0.80 2.38 3.70 17.58
2 PD 2 (800x650) 2.00 0.80 0.65 2.38 2.675 12.71
PD 3 (1300x1000) 4.00 1.30 1.00 2.38 2.675 25.41
3 TIE BIEM ( 550 x 550 ) 4.00 3.34 0.55 7.34

TIE BEAM 550X550 (4.00) 0.55 0.55 (1.21)

Total of Foundation 87.03 m2


QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : Infrastructure
Name of Building : Polyethylene Sheet
Drawing No : TEP-900-DWG-CV-BP4-0117
Work Description : Polyethylene Sheet

Length Width QTY


Nos (m) (m) Sheet/Unit (m2) Remarks
No Description/ BQ Iteams
a b c d e=axbxcxd
A Polyethylene Sheet
1 SL 1 1300x1000x300 100.00 2.30 2.00 2.00 920.00
2 SL 2 1300x1300x300 20.00 2.30 2.30 2.00 211.60
3 SL 3 1300x1500x300 360.00 2.30 2.50 2.00 4,140.00

Total of Polyethylene Sheet 6,063.00


QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : Infrastructure
Name of Building : Coating
Drawing No : TEP-900-DWG-CV-BP4-0117
Work Description : Coating

Length Width QTY


Nos (m) (m) Side (m2) Remarks
No Description/ BQ Iteams
a b c d d=axbxc
Coating
A SL 1 1300x1000
1 Footing 100.00 1.30 1.00 130.00
(100.00) 0.30 1.00 (30.00)
2 Side 100.00 1.30 0.30 2.00 78.00
100.00 1.00 0.30 2.00 60.00
238.00
3 pedestal 100.00 0.30 1.20 2.00 72.00
100.00 1.00 1.20 2.00 240.00
312.00
B SL 2 1300x1300
1 Footing 20.00 1.30 1.30 33.80
(20.00) 0.30 1.30 (7.80)
2 Side 20.00 1.30 0.30 4.00 31.20
57.20
3 pedestal 20.00 0.30 1.20 2.00 14.40
20.00 1.30 1.20 2.00 62.40
76.80
C SL 3 1300x1500
1 Footing 360.00 1.30 1.50 702.00
(360.00) 0.30 1.50 (162.00)
2 Side 360.00 1.30 0.30 2.00 280.80
360.00 1.50 0.30 2.00 324.00
1,144.80
3 pedestal 360.00 0.30 1.20 2.00 259.20
360.00 1.50 1.20 2.00 1,296.00
1,555.20
Total of Coating 3,384.00

1,353.60 67.68
77.83
QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : Infrastructure
Name of Building : Pipe Sleeper Infrastructure Area SL1, SL2 SL3
Drawing No : TEP-900-DWG-CV-BP4-0117
Work Description : Pipe Sleeper Infrastructure Area SL1, SL2 SL3

Length Width High QTY Steel QTY


Nos (m) (m) (m) (m2) Density (Kg)
No Description/ BQ Iteams (kg/m3)
a b c d e=axbxc e f=axbxcxdxe
A Pipe Sleeper Infrastructure Area SL1, SL2 SL3
1 Plate 900x200x16 100.00 0.90 0.20 0.016 18.00 7,850.00 2,260.80
2 Plate 1200x200x16 20.00 1.20 0.20 0.016 4.80 7,850.00 602.88
3 Plate 1400x200x16 360.00 1.40 0.20 0.016 100.80 7,850.00 12,660.48

Total of Pipe Sleeper Infrastructure Area SL1, SL2 SL3 135.96 15,524.16
Remarks
QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : ORF
Name of Building : Pipe Rack
Drawing No : TEP-017-DWG-CV-BP4-0007
Work Description : Pipe Rack

Nos Length Width High QTY


No Description/ BQ Iteams (m) (m) (m) (m3)
a b c d e=axbxcxd
A Pipe Rack
Footing
1 F1 5700x8200x600 2.00 8.20 5.70 0.60 56.09

Pedestal
1 PD 1 850x650x2075 8.00 0.85 0.65 2.08 9.17

Total of Pipe Rack 5700x8200x600 65.30

QUANTITY TAKEOFF - CALCULATION


Project : Tangguh Expansion Project
Area : ORF
Name of Building : Pipe Rack
Drawing No : TEP-017-DWG-CV-BP4-0008
Work Description : Pipe Rack

Nos Length Width High QTY


No Description/ BQ Iteams (m) (m) (m) (m3)
a b c d e=axbxcxd
A Pipe Rack
Footing
1 F1 7400x3200x600 1.00 7.40 3.20 0.60 14.21
2 F2 7400x5000x600 2.00 7.40 5.00 0.60 44.40

Pedestal
1 PD 1 900x900x1275 2.00 0.90 0.90 1.28 2.07
2 PD 2 750x600x1275 8.00 0.75 0.60 2.68 9.63

Tie Beam
1 TB1 400x400x3850 2.00 3.85 0.40 0.40 1.23

Total Pipe Rack 7400x3200x600 71.54

QUANTITY TAKEOFF - CALCULATION


Project : Tangguh Expansion Project
Area : ORF
Name of Building : Pipe Rack
Drawing No : TEP-017-DWG-CV-BP4-0010
Work Description : Pipe Rack

Nos Length Width High QTY


No Description/ BQ Iteams (m) (m) (m) (m3)
a b c d e=axbxcxd
A Pipe Rack
Footing
1 F1 3700x1900x600 1.00 3.70 1.90 0.60 4.22
2 F2 8200x7200x600 1.00 8.20 7.20 0.60 35.42

Pedestal
1 PD 1 1050x800x2375 2.00 1.05 0.80 2.38 3.99
2 PD 2 800x600x2375 2.00 0.80 0.65 2.38 2.47
3 PD 3 1300x1000x2375 4.00 1.30 1.00 2.38 12.35

Tie Bem
TB 3337x400x400 2.00 3.34 0.40 0.40 1.07

Total of Pipe Rack 700x700x300 44.00

QUANTITY TAKEOFF - CALCULATION


Project : Tangguh Expansion Project
Area : ORF
Name of Building : Pipe Rack
Drawing No : TEP-017-DWG-CV-BP4-0007 ,0008, 0010
Work Description : Lean Concrete THK 50mm

Nos Length Width High QTY


No Description/ BQ Iteams (m) (m) (m) (m3)
a b c d e=axbxcxd
A Lean Concrete THK 50mm
1 PR1 8200x5700x50 2.00 8.20 5.70 0.05 4.67
2 PR2 7400x3200x50 1.00 7.40 3.20 0.05 1.18
3 PR3 7400x3200x50 2.00 0.90 0.90 0.05 0.08

Total of Sleeper 700x700x300 5.94


Remarks

m3

Remarks

m3
Remarks

22275
2375

m3

Remarks

m2
QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : ORF
Name of Building : Pipe Rack
Drawing No : TEP-017-DWG-CV-BP4-0007
TEP-017-DWG-CV-BP4-0008
TEP-017-DWG-CV-BP4-0010
Work Description : Pipe Rack

Dimension Total
No Type Length Width High quantity
l w h
TEP-017-DWG-CV-BP4-0007
1 Footing 8200 5700 600 2
Pedestal 850 650 2075 8

TEP-017-DWG-CV-BP4-0008
1 Footing 7400 3200 600 1
Pedestal 900 900 1275 2
2 Footing 7400 5000 600 2
Pedestal 750 600 2675 8
3 Tie Beam 3850 400 400 2
TEP-017-DWG-CV-BP4-0010
1 Footing 3700 1900 600 1
Pedestal 1050 800 2375 2
2 Footing 8200 7200 600 1
Pedestal 1 800 650 2375 2
Pedestal 2 1300 1000 2375 4
Pedestal 3 800 650 2375 2
3 Tie Beam 3337 400 400 2
1975
1.975
19.75
39.5
QUANTITY TAKEOFF - CALCULATION
Project : Tangguh Expansion Project
Area : ORF
Name of Building : Pipe Rack
Drawing No : TEP-017-DWG-CV-BP4-0007
Work Description : Pipe Rack

Dimension Total
No Type Length Width High quantity
l w h
1 Footing 8200 5700 600 2
Pedestal 850 650 2075 4
QUANTITY TAKEOFF - CALCULATION
Project Tangguh Expansion Project
Area Infrastructure
Name of Building Rebar Arragement
Drawing No TEP-900-STD-CV-BP4-0027-001s/d004
Work Description Rebar Arragement

Table 3. Concrete Protection for Reinforcement Schedule

Not Expose to
Expose to Weather,
Weather or in Water or Soil
No Description
Contact with (Internal
Ground Protected
Faces)

1 Beam & Columns 50 40


2 Slabs, Walls & Joists 50 20
3 Other Member 50 -

Pre-Cast Concrete (Manufactured Under Plant Control Condition)

Concrete not
Concrete
Exposed to
No Description Exposed to Weather or in
Earth or
Contact with
Weather
Ground

1 Beam & Columns 40 25/40


2 Slabs, Walls & Joists 25 20
3 Other Member 40 -

Table 4. Compression Development (Ldc) and Lap splice lengths for Reinforcing Bars
Bar Size Development Length (Ldc) mm
Lap Splice
No
Length
21 Mpa 32 Mpa 35 Mpa
1 D10 205 200 200 300
2 D13 270 220 220 360
3 D16 330 270 270 445
4 D19 390 320 320 530
5 D22 450 370 370 610
6 D25 515 420 420 695
7 D29 595 490 490 805
8 D32 655 540 540 890
9 D36 740 605 605 1000

Table 5. Tension Development (Ld) and Lap splice lengths for Reinforcing Bars
21 Mpa 32 Mpa
No Bar Size Lap Class
Other Than
Top Bar Top Bar
Top Bar

1 D10 A 530 410 430


2 D13 A 685 530 555
3 D16 A 845 650 685
4 D19 A 1005 770 815
5 D22 A 1435 1105 1160
6 D25 A 1630 1255 1320
7 D29 A 1890 1455 1530
8 D32 A 2085 1605 1690
9 D36 A 2345 1805 1900

21 Mpa 32 Mpa

No Bar Size Lap Class Other Than


Top Bar Top Bar
Top Bar

1 D10 B 685 530 555


2 D13 B 895 685 725
3 D16 B 1100 845 890
4 D19 B 1305 1005 1095
5 D22 B 1865 1435 1510
6 D25 B 2120 1630 1715
7 D29 B 2460 1890 1990
8 D32 B 2710 2085 2195
9 D36 B 3050 2345 2470

Table 6. Tension Development Length (Ldh) for Standard Hooks


Development Length (Ldc) mm
No Bar Size
21 Mpa 32 Mpa 35 Mpa

1 D10 205 170 160


2 D13 270 220 210
3 D16 330 265 255
4 D19 390 315 305
5 D22 450 365 35
6 D25 515 415 400
7 D29 595 480 460
8 D32 655 530 510
9 D36 740 600 570

Table 7. Standard Hooks & Seismic Hooks for Main Reinforcement


Min. Bending
Bar Diameter 180 Degree 90 Degree
No Description Diameter
db (mm) Hook Hook
(mm)
D10 60 65 120
D13 78 65 156
D16 96 65 192
D19 114 76 228
D22 132 88 264
D25 150 100 300
D29 232 116 348
D32 256 128 384
D36 288 144 432

Table 8. Standards Hooks & Seismic Hooks for Stirrups & Ties
Min. Bending
Bar Diameter 135 Degree 90 Degree
No Description Diameter
db (mm) (mm) Hook Hook

D10 40 75 75
D13 52 78 78
D16 64 96 96
D19 114 114 228
D22 132 132 264
D25 150 150 300
CULATION
32 Mpa 35 Mpa

Other Than Other Than


Top Bar
Top Bar Top Bar

330 410 315


430 535 410
530 655 505
625 780 600
895 1110 855
1015 1265 970
1180 1465 1125
1300 1615 1245
1460 1815 1400

32 Mpa 35 Mpa

Other Than Other Than


Top Bar
Top Bar Top Bar

430 535 410


555 690 535
685 850 655 1110
815 1010 780 156 26
1160 1445 1110 130
1320 1640 1265 1396
1530 1905 1465 1.396
1690 2100 1615 14.2
1900 2360 1815 16.2
31.796
7.796

4.204
1656
30496
32152
32.152
8.2
3.8
Hook 390
456

156
Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00

TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal D22 11003.83 306.68 458.00
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01


TEP-900-DWG-CV-BP4-0024_Abbrevation And Symbol For Civil Work

TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)
1. PR-1 DWG No : TEP-017-DWG-CV-BP4-0007
a. Footing 8200x5700, Sheet-01

T1 D22 A a 55 2 110 2 264.00 1 5468.00 2 103.62 6203.24 2.99 2040.25 56.86 12000 110 110

a
B1 D22 A
b 55 2 110 2 264.00 2 268.00 1 5442.00 4 103.62 6920.48 2.99 2276.15 63.44 12000 110 110

c
b

T1 D22 B a 38 2 76 2 264.00 1 7968.00 2 103.62 8703.24 2.99 1977.72 55.12 12000 76 76

a
B1 D22 B b 38 2 76 2 264.00 2 268.00 1 7942.00 4 103.62 9420.48 2.99 2140.71 59.66 12000 76 76

c
b
a

c
S1 D13 B 2 2 4 2 78.00 1 5522.00 1 6277.48 2 61.23 12077.94 1.05 50.73 4.03 24000 4 8

A
S2 D13 B C 2 2 4 1 4089.50 1 5522.00 1 2266.04 2 61.23 12000 1.05 50.40 4 12000 4 4

b
S3 D13 B 2 2 4 2 78.00 1 3932.56 1 61.23 4149.79 1.05 17.43 1.38 6000 4 2

b. Pedestal 850x650, Sheet-01,02

H1 D16 A 1 8 8 2 96.00 2 454.00 2 654.00 5 75.36 2784.8 1.58 35.20 1.86 3000 8 2

H1 D10 A 19 8 152 2 75.00 2 490.00 2 690.00 5 47.10 2745.5 0.62 258.74 34.78 3000 152 38

b
H2 D10 A
a c 40 8 320 1 75.00 1 490.00 1 75.00 2 47.10 734.2 0.62 145.67 19.58 1000 320 27

P D22 A a a' 16 8 128 2 264.00 1 2299.00 2 103.62 3034.24 2.99 1161.26 32.37 4000 128 43
b
Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00

TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal D22 11003.83 306.68 458.00
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01


TEP-900-DWG-CV-BP4-0024_Abbrevation And Symbol For Civil Work

TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)

QTY QTY Dimension (mm) Total Need for Order


Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)
2. PR-1 DWG No : TEP-017-DWG-CV-BP4-0008
a. Footing 7400x3200x600, Sheet-02

T1 D19 A a 22 1 22 2 228.00 1 7186.00 2 89.49 7820.98 2.23 383.70 14.34 12000 22 22

a
B1 D19 A
b 22 1 22 2 228.00 2 286.00 1 7160.00 4 89.49 8545.96 2.23 419.26 15.67 12000 22 22

c
b

T1 D19 B a 50 1 50 2 228.00 1 2960.00 2 89.49 3594.98 2.23 400.84 14.98 4000 50 17

a
B1 D19 B b 50 1 50 2 228.00 2 286.00 1.00 2960.00 4 89.49 4345.96 2.23 484.57 18.11 6000 50 25

c
c

S1 D13 A b 2 2 4 1 78.00 1 7222.00 1 2082.69 2 61.23 9505.15 1.05 39.92 3.17 12000 4 4

a
d

S1 D13 A 2 2 4 1 78.00 1 3022.00 1 7222.00 1 1494.31 3 61.23 12000 1.05 50.40 4 12000 4 4

a
b

2. Footing 7400x5000x600, Pipe Bridge 017-BRG-31003 Foundation Plan Sheet-02

a
T2 D19 A 50 2 100 2 228.00 1 4786.00 2 89.49 5420.98 2.23 1208.88 45.17 6000 100 50

a
b
B2 D19 A 50 2 100 2 228.00 2 286.00 1 4760.00 4 89.49 6145.96 2.23 1370.55 51.22 12000 100 100

c
b

T2 D19 B 34 2 68 2 228.00 1 7160.00 2 89.49 7794.98 2.23 1182.03 44.17 12000 68 68


a

a
b
B2 D19 B 34 2 68 2 228.00 2 286.00 1.00 7160.00 4 89.49 8545.96 2.23 1295.91 48.43 12000 68 68

b a

S1 D13 B 2 2 4 1 78.00 1 4822.00 1 6977.54 2 61.23 12000 1.05 50.40 4 12000 4 4


c
Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00
b
TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal
a
D22 11003.83 306.68 458.00
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01


TEP-900-DWG-CV-BP4-0024_Abbrevation And Symbol For Civil Work
c
TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)

S1 D13 B
b 2 2 4 1 78.00 1 7222.00 1 4577.54 2 61.23 12000 1.05 50.40 4 12000 4 4

S1 D13 B
a 2 2 4 1 721.46 1 799.46 1 61.23 1582.15 1.05 6.65 0.53 2000 4 1

b. Pedestal 900x900x1275, Pipe Bridge 017-BRG-31003 Foundation Plan Sheet-03

P1 D25 A 20 2 40 2 300.00 1 1525.00 2 117.75 2360.5 3.86 364.46 7.87 3000 40 10


b

P1 D19 B 1 2 2 2 114.00 2 686.00 2 686.00 5 89.49 3419.45 2.23 15.25 0.57 4000 2 1

P1 D10 C 12 2 24 2 75.00 2 740.00 2 740.00 5 47.10 3345.5 0.62 49.78 6.69 4000 24 8

P1 D10 D 16 2 32 1 75.00 1 740.00 1 75.00 2 47.10 984.2 0.62 19.53 2.62 1000 32 3
b

C. Pedestal 750x600x2675, Pipe Bridge 017-BRG-31003 Foundation Plan Sheet-03

P2 D22 A b 16 8 128 2 264.00 1 2943.00 2 103.62 3678.24 2.99 1407.74 39.23 4000 128 43

P2 D16 B 1 8 8 2 96.00 2 404.00 2 554.00 5 75.36 2484.8 1.58 31.41 1.66 3000 8 2

b
Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00

TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal D22 11003.83 306.68 458.00
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01

c And Symbol For Civil Work


TEP-900-DWG-CV-BP4-0024_Abbrevation

TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
a Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
b (kg) (pcs) (mm) (pcs)

c
P2 D10 C 25 8 200 2 75.00 2 440.00 2 554.00 5 47.10 2373.5 0.62 294.31 39.56 3000 200 50

P2 D10 D 52 8 416 1 75.00 2 440.00 2 75.00 2 47.10 1199.2 0.62 309.30 41.57 2000 416 69
b

c. Tie Beam 400x400x3850

b
a
TB1 D10 A c 27 2 54 2 75.00 2 250.00 2 250.00 5 47.10 1385.5 0.62 46.39 6.23 2000 54 9

TB

TB1 D10 B 12 2 24 2 170.00 1 3850.00 4190 0.62 62.35 8.38 6000 24 12


Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00

TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal D22 11003.83 306.68 458.00
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01


TEP-900-DWG-CV-BP4-0024_Abbrevation And Symbol For Civil Work

TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)

3. PR-1 DWG No : TEP-017-DWG-CV-BP4-0010


a. Footing 3700x1900x600, Operation Platform 017-PLF-31010/31011A/31011B Foundation Plan, Sheet-02

T1 D19 A 25 1 25 2 228.00 1 1686.00 2 89.49 2320.98 2.23 129.39 4.84 3000 25 6

B1 D19 A b 25 1 25 2 228.00 2 286.00 1 1660.00 4 89.49 3045.96 2.23 169.81 6.35 4000 25 8

a
T1 D19 B 13 1 13 2 228.00 1 3486.00 2 89.49 4120.98 2.23 119.47 4.46 6000 13 7

a
B1 D19 B b 13 1 13 2 228.00 2 286.00 1 3460.00 4 89.49 4845.96 2.23 140.48 5.25 6000 13 7

b
c
a

c
S1 D13 C 2 1 2 2 78.00 2 1800.00 2 3600.00 5 61.23 11262.15 1.05 23.65 1.88 12000 2 2

b. Footing 8200x7200x600, Operation Platform 017-PLF-31010/31011A/31011B Foundation Plan, Sheet-02

T2 D19 A a 55 1 55 2 228.00 1 6986.00 2 89.49 7620.98 2.23 934.71 34.93 12000 55 55

B2 D19 A
b 55 1 55 2 228.00 2 6960.00 4 89.49 14733.96 2.23 1807.12 67.53 24000 55 110

c
b

T2 D19 B 48 1 48 2 228.00 1 6986.00 2 89.49 7620.98 2.23 815.75 30.48 12000 48 48


a

a
B2 D19 B b 48 1 48 2 228.00 2 286.00 1 7960.00 4 89.49 9345.96 2.23 1000.39 37.38 12000 48 48

a
S2 D13 A
c 2 1 2 1 78.00 1 7022.00 1 4777.54 2 61.23 12000 1.05 25.20 2 12000 2 2

S2 D13 B c 2 1 2 1 1056.08 1 7022.00 1 3799.46 2 61.23 12000 1.05 25.20 2 12000 2 2

a
b
a

S2 D13 C b 2 1 2 1 78.00 1 7529.92 1 61.23 7669.15 1.05 16.11 1.28 12000 2 2


Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00

TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal D22 11003.83 306.68 458.00
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01


TEP-900-DWG-CV-BP4-0024_Abbrevation And Symbol For Civil Work

TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)

QTY QTY Dimension (mm) Total Need for Order


Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
(kg) (pcs) (mm) (pcs)
3. PR-1 DWG No : TEP-017-DWG-CV-BP4-0010
a. Pedestal 1050x800x2375, Operation Platform 017-PLF-3101/31011A/31011B Foundation Plan Sheet- 02 & 04

P1 D25 A b 22 2 44 2 300.00 1 2625.00 2 117.75 3460.5 3.86 587.73 12.69 4000 44 15

P1 D19 B
c 1 2 2 2 114.00 2 586.00 2 836.00 5 89.49 3519.45 2.23 15.70 0.59 4000 2 1

P1 D10 C
c 22 2 44 2 75.00 2 640.00 2 890.00 5 47.10 3445.5 0.62 93.99 12.63 4000 44 15

P1 D10 D
b 46 2 92 1 75.00 2 640.00 1 75.00 2 47.10 1524.2 0.62 86.94 11.69 2000 92 15
a c

P1 D10 E 46 2 92 1 75.00 1 890.00 1 75.00 2 47.10 1134.2 0.62 64.69 8.7 2000 92 15
b

c
b. Pedestal 1300x1000x2375, Operation Platform 017-PLF-31010/31011A/31011B Foundation Plan Sheet-04

P2 D25 A
b 32 4 128 2 300.00 1 2625.00 2 117.75 3460.5 3.86 1709.76 36.91 4000 128 43

P2 D22 B c 1 4 4 2 132.00 2 768.00 2 1068.00 5 103.62 4454.1 2.99 53.27 1.48 6000 4 2

P2 D10 C
c 22 4 88 2 75.00 2 840.00 2 1140.00 5 47.10 4345.5 0.62 237.09 31.87 6000 88 44

P2 D13 D b 2 4 8 2 78.00 1 1122.00 2 39.00 1356 1.05 11.39 0.9 2000 8 1

c
Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work 24.90556
Bar Bending Schedule
Total Need for Order
Summary Bar
Weight Rod Length Rod
Diameter Number
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs) (mm) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 1186.05 159.41 216.00


Reference Drawing : D13 406.48 32.27 39.00

TEP-900-STD-ST-BP4-0010_STANDARD DRAWING COLUMN BASE PLATE (FIXED) CONNECTION D16 66.61 3.52 4.00
TEP-900-STD-CV-BP4-0033_Standar Drawing Anchor Bolts D19 11878.13 443.88 662.00

TEP-900-DWG-CV-BP4-0037_Standard Drawing For Steel Column Pedestal D22 11003.83 306.68 458.00
a
TEP-900-DWG-CV-BP4-0001_Standard Drawing Typical PC Pile Head Detail

TEP-900-DWG-CV-BP4-0027_Standard Drawing Rebar Arrangement


TEP-900-DWG-CV-BP4-0003_Piling Schedule For ORF Area R01

TEP-900-DWG-CV-BP4-0008_Piling Layout ORF Area R01


TEP-900-DWG-CV-BP4-0024_Abbrevation And Symbol For Civil Work

b
TEP-900-DWG-CV-BP4-0025_General Notes for Civil & Concrete Foundation D25 364.46 7.87 10.00
D29 0.00 0.00 0.00
TOTAL 24905.56 953.63 1389.00
QTY QTY Dimension (mm) Total Need for Order
Weight
No Size Type Shape a b c d e f g r Length (mm) Weight Rod Length Rod
(Kg/m)
PCS SET PCS.SET Number
c (kg) (pcs) (mm) (pcs)

b
P2 D10 E
a c 44 4 176 1 75.00 1 840.00 1 75.00 2 47.10 1084.2 0.62 118.31 15.9 2000 176 29

c. Pedestal 800x650x2375, Operation Platform 017-PLF-31010/31011A/31011B Foundation Plan Sheet-04

P3 D22 A
b 16 2 32 2 264.00 1 2643.00 2 103.62 3378.24 2.99 323.23 9.01 4000 32 11

P3 D16 B 1 2 2 2 96.00 2 454.00 2 604.00 5 75.36 2684.8 1.58 8.48 0.45 3000 2 1
c

P3 D10 C 22 2 44 2 75.00 2 490.00 2 640.00 5 47.10 2645.5 0.62 72.17 9.7 3000 44 11
c

b
a c
P3 D10 E 46 2 92 1 75.00 1 490.00 1 75.00 2 47.10 734.2 0.62 41.88 5.63 1000 92 8
Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

3946.8 5796.76 1906.55 920.99

3946.8 5079.52 1670.65 707.18

2726.88 3296.76 749.16 205.82

2726.88 2579.52 586.17 126

100.8 11922.06 50.07 49.75

50.4 0 0.00 0

25.2 1850.21 7.77 1.2

37.92 215.2 2.72 0.05

282.72 254.5 23.98 0.51

200.88 265.8 55.21 1.22

1542.84 965.76 381.58 30.71


Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

588.72 4179.02 205.02 71.4

588.72 3454.04 169.46 48.78

454.92 405.02 54.08 1.83

669 1654.04 184.43 25.42

50.4 2494.85 10.48 2.18

50.4 0 0.00 0

1338 579.02 129.12 6.23

2676 5854.04 1305.45 636.85

1819.68 4205.02 637.65 223.44

1819.68 3454.04 523.77 150.76

50.4 0 0.00 0
Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

50.4 0 0.00 0

12.6 417.85 5.95 0.21

463.2 639.5 98.74 5.26

26.76 580.55 11.51 0.56

59.52 654.5 9.74 0.53

22.32 15.8 2.79 0

1542.84 321.76 135.10 3.62

37.92 515.2 6.51 0.28


Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

372 626.5 77.69 4.06

513.36 800.8 204.06 13.62

66.96 614.5 20.57 1.05

89.28 1810 26.93 4.06


Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

160.56 679.02 31.17 1.76

214.08 954.04 44.27 3.52

187.32 1879.02 67.85 10.62

187.32 1154.04 46.84 4.5

25.2 737.85 1.55 0.1

1471.8 4379.02 537.09 195.99

2943.6 9266.04 1136.48 877.56

1284.48 4379.02 468.73 171.05

1284.48 2654.04 284.09 62.83

25.2 0 0.00 0

25.2 0 0.00 0

25.2 4330.85 9.09 3.28


Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

694.8 539.5 107.07 4.81

26.76 480.55 11.06 0.44

111.6 554.5 17.61 0.81

111.6 475.8 24.66 0.98

111.6 865.8 46.91 3.38

1991.76 539.5 282.00 12.68

71.76 1545.9 18.49 2.38

327.36 1654.5 90.27 12.45

12.6 644 1.21 0.06


Order The Waste
Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

1607.04 420.99 25.05


491.40 84.92 56.72

75.84 9.23 0.33


17715.12 5836.99 2493.10

16433.04 5429.21 1994.32

463.20 98.74 5.26


0.00 0.00 0.00

36785.64 11880.08 4574.78

Order The Waste


Weight Length Weigth Rod

(kg) (mm) (kg) (pcs)

215.76 915.8 97.45 7.44

394.68 621.76 71.45 3.7

18.96 315.2 10.48 0.28

81.84 354.5 9.67 0.29

59.52 265.8 17.64 0.39


Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work
Bar Bending Schedule
Total
Summary Bar
Weight Rod
Diameter
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 Err:509 Err:509


Reference Drawing : D13 Err:509 Err:509

TEP-900-STD-CV-BP4-0025_General Note for Civil & Concrete Foundation Rev.02 D16 Err:508 Err:508
TEP-900-STD-CV-BP4-0027-001-004_Standar Drawing Rebar Arrangement Rev. B01 D19 0.00 0.00

TEP-900-DWG-CV-BP4-0117_Foundation Plan & Section Details SL-1, SL-2 & SL-3 Rev.B01 D22 0.00 0.00
TEP-900-DWG-CV-BP4-0115_Sleeper Plan Layout at Infrastructure Area (Middle Road To Camp) Key Plan D25 0.00 0.00
D29 0.00 0.00
TOTAL Err:509 Err:509
QTY QTY Dimension (mm) Total
Weight
No Size Type Shape a b c d e f g Length (mm) Weight Rod
(Kg/m)
PCS SET PCS.SET
(kg) (pcs)
1. SL-1 DWG No : TEP-900-DWG-CV-BP4-0115-001/004_Rev.B01
a. Footing 1000x1300x300

T1 & B1 D13 A 42 2 84 2 500.00 2 5600.00 1 108.00 12308 1.05 1085.57 86.16

T2 & B2 D13 A 29 2 58 2 474.00 2 8100.00 1 108.00 17256 1.05 1050.89 83.4

b. Pedestal 1000x300x1200

L1 D16 B 12 2 24 1 2524.00 1 256.00 2780 1.58 105.42 5.56

S1 D10 C 17 2 34 2 750.00 2 550.00 2 75.00 2750 0.62 57.97 7.79

C1 D10 D 27 2 54 1 105.00 1 552.00 1 75.00 732 0.62 24.51 3.29

QTY QTY Dimension (mm) Total


Weight
No Size Type Shape a b c d e f g Length (mm) Weight Rod
(Kg/m)
PCS SET PCS.SET
(kg) (pcs)
2. SL2 DWG No : TEP-900-DWG-CV-BP4-0115-004/005_Rev.B01
a. Footing 1300x1300x300

T1 & B1 D13 A 0 0 0 2 -100.00 2 -100.00 1 108.00 -292 1.05 0.00 0

T2 & B2 D13 A 0 0 0 2 -126.00 2 -100.00 1 108.00 -344 1.05 0.00 0

b. Pedestal 1300x300x1200

L1 D16 B 116 0 0 1 449.00 1 256.00 705 1.58 0.00 0

S1 D10 C ### 0 Err:508 2 7300.00 2 -100.00 2 75.00 14550 0.62 Err:508 Err:508

C1 D10 D 87 0 0 1 105.00 1 3102.00 1 75.00 3282 0.62 0.00 0

QTY QTY Dimension (mm) Total


Weight
No Size Type Shape a b c d e f g Length (mm) Weight Rod
(Kg/m)
PCS SET PCS.SET
(kg) (pcs)
3. SL 3 DWG No : TEP-900-DWG-CV-BP4-0115-005/017_Rev.B01
a. Footing 1500x1300x300
Tangguh Expansion Project
Pipe Sleeper on Infrastructure Area (X00)
Item of Work : Reinforcement Concrete Work
Bar Bending Schedule
Total
Summary Bar
Weight Rod
Diameter
Reinforcing Steel Bar : SNI-07-2052-2014 (kg) (pcs)

-BJTS 40 Deformed Bar = 390 Mpa D10 Err:509 Err:509


Reference Drawing : D13 Err:509 Err:509

TEP-900-STD-CV-BP4-0025_General Note for Civil & Concrete Foundation Rev.02 D16 Err:508 Err:508
TEP-900-STD-CV-BP4-0027-001-004_Standar Drawing Rebar Arrangement Rev. B01 D19 0.00 0.00

TEP-900-DWG-CV-BP4-0117_Foundation Plan & Section Details SL-1, SL-2 & SL-3 Rev.B01 D22 0.00 0.00
TEP-900-DWG-CV-BP4-0115_Sleeper Plan Layout at Infrastructure Area (Middle Road To Camp) Key Plan D25 0.00 0.00
D29 0.00 0.00
TOTAL Err:509 Err:509
QTY QTY Dimension (mm) Total
Weight
No Size Type Shape a b c d e f g Length (mm) Weight Rod
(Kg/m)
PCS SET PCS.SET
(kg) (pcs)

T1 & B1 D13 A ### ### Err:508 2 Err:509 2 Err:509 1 108.00 Err:509 1.05 Err:509 Err:509

T2 & B2 D13 A ### ### Err:508 2 Err:509 2 Err:509 1 108.00 Err:509 1.05 Err:509 Err:509

b. Pedestal 1500x300x1200

L1 D16 B 24 ### Err:509 1 Err:508 1 256.00 Err:508 1.58 Err:508 Err:508

S1 D10 C ### ### Err:508 2 Err:509 2 Err:509 2 75.00 Err:509 0.62 Err:509 Err:509

C1 D10 D ### ### Err:508 1 105.00 1 Err:509 1 75.00 Err:509 0.62 Err:509 Err:509

4. Anchor Bar DWG No : TEP-900-DWG-CV-BP4-0117_Rev.B01

SL 1 D13 A 3 2 6 2 200.00 1 125.00 525 1.05 3.31 0.26

SL 2 D13 A 3 0 0 2 200.00 1 125.00 525 1.05 0.00 0

SL 3 D13 A 4 ### Err:509 2 200.00 1 125.00 525 1.05 Err:509 Err:509