Scheduled receipts Projected on hand 100 on hand =100 Net requirements 900 Planned-order receipts 900 Planned-order releases 900 housing Gross requirements 900 lead time=1 Scheduled receipts Projected on hand 100 Net requirements 800 on hand =100 Planned-order receipts 800 Planned-order releases 800 Frame Gross requirements 800 Scheduled receipts lead time=2 Projected on hand 0 Net requirements 800 on hand =0 Planned-order receipts 800 Planned-order releases 800 Supports x 2 Gross requirements 1600 lead time=1 Scheduled receipts Projected on hand 50 50 50 lot size=100 Net requirements 1550 on hand = 50 Planned-order receipts 1600 Planned-order releases 1600 Handle Gross requirements 800 lead time=1 Scheduled receipts Projected on hand 400 100 100 lot size=500 Net requirements 400 on hand = 400 Planned-order receipts 500 Planned-order releases 500
Grills x 2 Gross requirements 1800
lead time=2 Scheduled receipts on hand =200 Projected on hand 200 400 Net requirements 1600 lot size=500 Planned-order receipts 2000 Planned-order releases 2000
Fan Assembly Gross requirements 900
lead time=3 Scheduled receipts on hand =150 Projected on hand 150 Net requirements 750 Planned-order receipts 750 Planned-order releases 750 Hub Gross requirements 750 lead time=1 Scheduled receipts on hand =0 Projected on hand 0 Net requirements 750 Planned-order receipts 750 Planned-order releases 750 Blades X 5 Gross requirements 3750 lead time=2 Scheduled receipts on hand =0 Projected on hand 0 50 50 50 50 Net requirements 3750 lot size=100 Planned-order receipts 3800 Planned-order releases 3800
Electrical Unit Gross requirements 900
lead time=1 Scheduled receipts on hand =0 Projected on hand 0 Net requirements 900 Planned-order receipts 900 Planned-order releases 900 Motor Gross requirements 900 lead time=1 Scheduled receipts on hand =0 Projected on hand 0 Net requirements 900 Planned-order receipts 900 Planned-order releases 900 Switch Gross requirements 900 lead time=1 Scheduled receipts on hand = 20 Projected on hand 20 8 8 Net requirements 880 Lot Size=12 Planned-order receipts 888 Planned-order releases 888 Knob Gross requirements 900 lead time=1 Scheduled receipts 200 on hand = 0 Projected on hand 200 200 200 200 0 0 Sche re=200 Net requirements 700 Lot Size=25 Planned-order receipts 700 Planned-order releases 700