FAN Day 1 2 3 4 5 6 7

lead time=1 Gross requirements 1000


Scheduled receipts
Projected on hand 100
on hand =100 Net requirements 900
Planned-order receipts 900
Planned-order releases 900
housing Gross requirements 900
lead time=1 Scheduled receipts
Projected on hand 100
Net requirements 800
on hand =100 Planned-order receipts 800
Planned-order releases 800
Frame Gross requirements 800
Scheduled receipts
lead time=2 Projected on hand 0
Net requirements 800
on hand =0 Planned-order receipts 800
Planned-order releases 800
Supports x 2 Gross requirements 1600
lead time=1 Scheduled receipts
Projected on hand 50 50 50
lot size=100 Net requirements 1550
on hand = 50 Planned-order receipts 1600
Planned-order releases 1600
Handle Gross requirements 800
lead time=1 Scheduled receipts
Projected on hand 400 100 100
lot size=500 Net requirements 400
on hand = 400 Planned-order receipts 500
Planned-order releases 500

Grills x 2 Gross requirements 1800


lead time=2 Scheduled receipts
on hand =200 Projected on hand 200 400
Net requirements 1600
lot size=500 Planned-order receipts 2000
Planned-order releases 2000

Fan Assembly Gross requirements 900


lead time=3 Scheduled receipts
on hand =150 Projected on hand 150
Net requirements 750
Planned-order receipts 750
Planned-order releases 750
Hub Gross requirements 750
lead time=1 Scheduled receipts
on hand =0 Projected on hand 0
Net requirements 750
Planned-order receipts 750
Planned-order releases 750
Blades X 5 Gross requirements 3750
lead time=2 Scheduled receipts
on hand =0 Projected on hand 0 50 50 50 50
Net requirements 3750
lot size=100 Planned-order receipts 3800
Planned-order releases 3800

Electrical Unit Gross requirements 900


lead time=1 Scheduled receipts
on hand =0 Projected on hand 0
Net requirements 900
Planned-order receipts 900
Planned-order releases 900
Motor Gross requirements 900
lead time=1 Scheduled receipts
on hand =0 Projected on hand 0
Net requirements 900
Planned-order receipts 900
Planned-order releases 900
Switch Gross requirements 900
lead time=1 Scheduled receipts
on hand = 20 Projected on hand 20 8 8
Net requirements 880
Lot Size=12 Planned-order receipts 888
Planned-order releases 888
Knob Gross requirements 900
lead time=1 Scheduled receipts 200
on hand = 0 Projected on hand 200 200 200 200 0 0
Sche re=200 Net requirements 700
Lot Size=25 Planned-order receipts 700
Planned-order releases 700