2 Friction slab With Crash barrier along the RE Wall 14085

Unit = Linear metre


Taking output = 10 m
a) M 40 grade concrete
M 40 grade concrete cum 10 4511.6 45116
b) Labour -
Mate day 0.04 303 12.12
Mazdoor day 1 286 286
c) Material 0
HYSD steel reinforcement including dowel bars tonne 1 36498 36498
Pre-moulded asphalt filler board sqm 0.32 400 128
d) Overhead charges @ 0.1 on (b+c) 8204.012

e) Contractor's profit @ 0.1 on (b+c+d) 9024.413

Cost for 10 metre = a+b+c+d+e 99268.55


Rate per metre = (a+b+c+d+e)/10 9926.855
say 9927