Supply and filling with Crusher dust from approved quarry

including cost and conveyaance, watering, tamping including all


RBR-FNDN-2 labour charges
II crusher dust
Unit = cum
Taking output = 6 cum
a)  Labour
Mate day -
Mazdoor (Uday 0.31 460 142.6
b) MaterialCum 1 835.6 835.6
978.2
Overheads 13.62% 133.19
Cost for 6 cum = a+b+c Total 1111.39
MA @ 40% 142.6 57.04
Rate per cum = (a+b+c) 1168.43

Rate per cum Total 1168.43


Rs.1168.43/1 cum
EARTH WORK DATA
Index- Descript Amount
S. No Unit Quantity Rate Rs.
code ion Rs.
1 2 3 4 5.00 6
Excavati
on for
RBR-FNDN-1 Structur
es
1 Earthwor
k in
excavatio
n for
structure
s as per
drawing
and
technical
specificat
ions
Clause
305.1
including
setting
out,
construct
ion of
shoring
and
bracing,
removal
of
stumps
and other
deleterio
us
material
and
disposal
upto a
Note :
Classific
ations of
Earth
Work
Specifica
tion are
as per
302.2.1(a
) of
MORD
and
301.2.1
of
MORT&
H

Depth
upto 3 m
(I) Ordinary
soil
(A) Manual
Means
(i) Upto 3 m
depth
Unit =
cum
Taking
output =
10 cum
a)  Labou
r
Mate day -
Mazdoor 1674.40
(Unskille day 3.64 460.00
d)
Sub 1674.40
Total
b&c) 227.97
Overhea
ds & 0.13615
Contract
ors Profit
Cost for 1902.37
10 cum =
a+b+c
Rate per 190.24
cum =
(a+b+c)/
10
Total 190.24
add extra 66.976
at 40%
Rate for 257.22
1 Cum

Depth 3
m to 6 m
a)  Labou
r
Mate day -
Mazdoor 2152.80
(Unskille day 4.68 460.00
d)
Sub 2152.80
Total
b&c) 293.10
Overhea
ds & 0.13615
Contract
ors Profit

Cost for 2445.90


10 cum =
a+b+c
Rate per 244.59
cum =
(a+b+c)/
10
Total 244.59
add extra 86.112
at 40%
Rate for 330.70
1 Cum
Depth
above 6
m
a)  Labou
r
Mate day -
Mazdoor 2870.40
(Unskille day 6.24 460.00
d)
Sub 2870.40
Total
b&c) 390.80
Overhea
ds & 0.13615
Contract
ors Profit

Cost for 3261.20


10 cum =
a+b+c
Rate per 326.12
cum =
(a+b+c)/
10
Total 326.12
add extra 114.816
at 40%
Rate for 440.94
1 Cum

(B) Mechani
cal
Means
i Upto 3
m depth
Unit =
cum
Taking
output =
240 cum
a)  Labo
ur
Mate day -
Mazdoor day 8.32 3827.20
(Unskille
d) 460.00
b)
Machine
ry
Hydrauli hour 6.00 17672.40
c
Excavato
r 1 cum
bucket
capacity
2945.40
21499.60
c&d) Overheads & Contractors Profit 2927.17
Add MA @ 40% 1530.88
Cost for 25957.65
240 cum
=
a+b+c+d
Rate per 108.16
cum =
(a+b+c+
d)/240

Cost of dewatering upto 5 per cent of (a+b)


i may be added,
Depth 3 where required. Assessment
m to 6 m
Unit =
cum
Taking
output =
210 cum
a)  Labo
ur
Mate day -
Mazdoor day 8.32 3827.20
(Unskille
d) 460.00
b)
Machine
ry
Hydrauli hour 6.00 17672.40
c
Excavato
r 1 cum
bucket
capacity
2945.40
21499.60
c&d) Overheads & Contractors Profit 2927.17
Add MA @ 40% 1530.88
Cost for 25957.65
240 cum
=
a+b+c+d
Rate per 123.61
cum =
(a+b+c+
d)/210

Cost of dewatering upto 5 per cent of (a+b)


may be added, where required. Assessment
i Depth
above 6
m
Unit =
cum
Taking
output =
180 cum
a)  Labo
ur
Mate day -
Mazdoor day 10.40 4784.00
(Unskille
d) 460.00
b)
Machine
ry
Hydrauli hour 6.00 17672.40
c
Excavato
r 1 cum
bucket
capacity
2945.40
22456.40
c&d) Overheads & Contractors Profit 3057.44
Add MA @ 40% 1913.60
Cost for 27427.44
240 cum
=
a+b+c+d
Rate per 152.37
cum =
(a+b+c+
d)/180

Cost of dewatering upto 7.5 per cent of (a+b)


may
Supplybe added, where required. Assessment
and
filling
with
gravel
from
approved
quarry
including
RBR-FNDN-2 cost and
conveyaa
nce,
watering,
tamping
including
all labour
charges

II Gravel
filling
Unit =
cum
Taking
output =
1 cum
a)  Labo
ur
Mate day -
Mazdoor day 0.31 142.6
(Unskille
d) 460.00
b) Cum 1.00 266.10 266.1
Materials
408.7
Overhead13.615% 55.64
Cost for Total 464.34
6 cum =
a+b+c
MA @ 0.40 57.04
40%
Rate per 521.38
cum =
(a+b+c)

Rate per Total 521.38


cum
Rs.521.38/1 cum
Filling in
foundatio
n
trenches
as per
drawing
and
technical
RBR-FNDN-2 specificat
ion
Clause
305.3.9
MORD
& 304
MORTH

I Sand
filling
Unit =
cum
Taking
output =
1 cum
a)  Labou
r
Mate day -
Mazdoor 142.6
(Unskille day 0.31 460.00
d)
b)
Materials
Sand 851.9
(Assumi
ng 20 per Cum 1.00 851.90
cent
voids)

994.5
135.40
Overhea
ds &
Contract
ors Profit 13.615%
@
13.615%

Cost for 1129.90


1 cum = Total
a+b+c
MA @ 57.04
40% 0.40
Rate per 1186.94
cum =
(a+b+c)
Rate per 1186.94
cum Total
Rs.1186.94/1 cum
1 Supply
and
filling
with
quarry
dust
from
approved
quarry
RBR- including
FNDN-2 cost and
conveyaa
nce,
watering,
tamping
including
all labour
charges

II Quarry
dust
Unit =
cum
Taking
output =
6 cum
a)  Labo
ur
Mate day -
Mazdoor day 0.31 142.6
(Unskille
d) 460.00
b) Cum 1.00 835.60 835.6
Materials
978.2
Overhead13.615% 133.18
MA @ 142.60 57.04
40%
Cost for Total 1168.42
6 cum =
a+b+c
Rate per 1168.42
cum =
(a+b+c)
Total 1168.42
Rs.1168.42/1 cum
Supply
and
filling
with
Crusher
dust
from
approved
quarry
RBR-FNDN-2 including
cost and
conveyaa
nce,
watering,
tamping
including
all labour
charges

II crusher
dust
Unit =
cum
Taking
output =
6 cum
a)  Labo
ur
Mate day -
Mazdoor day 0.31 142.6
(Unskille
d) 460.00
b) Cum 1.00 835.60 835.6
Material
s
978.2
Overheads13.615% 133.19
Cost for Total 1111.39
6 cum =
a+b+c
MA @ 142.60 57.04
40%
Rate per 1168.43
cum =
(a+b+c)

Rate per Total 1168.43


cum
Rs.1168.43/1 cum
6 Conveya
nce
charges
for the
earth
work/
Dismatli
ed
material
and wet
silt to
lead of
21 KMs
over
intial
lead and
lift
includin
g
loading
unloadin
g and
transpor
ation
charges
etc.,
complete
.

lead up 1 81.10 81.10


to 5km
16 11.70 187.20
additiona
l lead for
6 to
21kms(i.
e 16Kms
upto
Kapulapa
du)

Lead 268.30
Rate for
21 Kms