1 Date: 15/03/2017
1: Technical Specificaions...........................................................................................................3-3
2: Shedules...................................................................................................................................4-7
Schedule 1: Information.........................................................................................................4-4
S1.1 General Information regarding the project.........................................................4-4
S1.2 Scope of Works..................................................................................................4-4
Schedule 2: Performance Specification................................................................................5-5
S2.1 Materials.............................................................................................................5-5
Schedule 3: Preparation........................................................................................................5-7
S3.1 Setting out..........................................................................................................5-5
S3.2 Stages of the Embankment Construction .........................................................6-6
S3.3 Placing and compaction of Embankment material ...........................................6-7
Annexure 01.................................................................................................................................8-8
Annexure 02.................................................................................................................................9-9
2
1. Technical Specification
Copies of above Publication shall be purchased from the Construction Industry Development
Authority (CIDA), “Sausiripaya”, No.123, Wijerama Mawatha, Colombo 7.
3
2. Schedules
Schedule 1: Information
This method statement provides the details of the materials, the equipment, the procedure
and relevant documents related to the construction of embankment. Construction Manager,
Geotechnical Engineer, licensed surveyor and sectional Engineers within whose scope of
works shall be responsible for referred construction activities in related to construction of
embankment and work shall carry out according to the method stipulated in this statement
unless otherwise changed by the Engineer.
.
4
Schedule 2: Performance Specification
S2.1 Materials
Soil used as embankment material is naturally occurring shall not include highly plastic
clay, slits, peat or other organic soil or any soil that is contaminated with top soil vegetable
and other deleterious matter. The material used for the top 500mm of embankment will
conform to the requirements of type I material, and the material for lower layers of
embankment will conform to the requirements of type II material as given below.
Type I Embankment soil having a maximum dry density under standard conditions of
compaction not less than 1600 Kg/m3
Type II Embankment soil having a maximum dry density under standard conditions of
compaction not less than 1500 kg/m3
All suitable materials available at site (Available soil stockpile) will be used for
Schedule 3: Preparation
After the site has been cleared, the limits of embankment will be set out as required. The
pegs or stakes showing the limits of the embankment will be fixed at 1.5m distance outside
the actual limits of the fill.
5
S3.2 Stages of the Embankment Construction
In such instances before the placing of any embankment fill, the surface over the
bottom width of the foundation shall be trimmed and levelled as necessary and
conforms sub grade material to Type II. Then it will be compacted to achieve
maximum dry density not less than 95% (Modified Proctor).
S3.2.3 Stage 03: Upper Portion of the Embankment (Top 500mm thickness)
All materials which are deposited in place prior to compaction will be evenly
spread over the whole of the designated area for the layer concerned and in such
quantity that the thickness of any one layer, when measured after compaction will
comply with the requirements mention herein.
Before transporting the materials to the site should be wet & thoroughly mixed
(Moisture content approximately close to the optimum moisture content at stock
pile)
The initial spreading will be carried out using Motor Grader & Backhoe Loader
and prior to compaction a Motor Grader will be adopted to make smooth and
levelled surface to receive uniform compaction from the roller.
6
The un- compacted layer thickness shall be not be more than 200mm & refer the
figure 01, 02 & 03 for placing of embankment layers.
Any new layer less than 75mm in compacted thickness will be bonded to the
previous layer by scarifying the previous layer to a depth not less than 25mm or to
such depth the total compacted thickness of new layer plus the scarified portion of
the previous layer will not be less than 100mm.
7
Annexure 01
Location of Embankment
8
Annexure 02